Seabold Construction v. Koz 2211 SW 4th Avenue

344 Or. App. 688
CourtCourt of Appeals of Oregon
DecidedNovember 13, 2025
DocketA178493
StatusPublished
Cited by1 cases

This text of 344 Or. App. 688 (Seabold Construction v. Koz 2211 SW 4th Avenue) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seabold Construction v. Koz 2211 SW 4th Avenue, 344 Or. App. 688 (Or. Ct. App. 2025).

Opinion

688 November 13, 2025 No. 965

IN THE COURT OF APPEALS OF THE STATE OF OREGON

SEABOLD CONSTRUCTION CO., INC., Plaintiff-Appellant, v. KOZ 2211 SW 4TH AVENUE, LLC, a Washington limited liability company, Defendant-Respondent, and ORIX RE HOLDING, LLC, a Texas limited liability company, Defendant. Multnomah County Circuit Court 21CV04914; A178493

Judith H. Matarazzo, Judge. (General Judgment) Adrian L. Brown, Judge. (Supplemental Judgment) Argued and submitted December 19, 2024. Jonathan Henderson argued the cause for appellant. Also on the briefs were Elizabeth E. Lampson and Davis Rothwell Earle & Xóchihua, P.C. Kathleen C. Bricken argued the cause for respondent. Also on the brief were Justice J. Brooks and Foster Garvey, PC. Before Aoyagi, Presiding Judge, Egan, Judge, and Joyce, Judge. EGAN, J. Affirmed. Cite as 344 Or App 688 (2025) 689 690 Seabold Construction v. Koz 2211 SW 4th Avenue

EGAN, J. Plaintiff, Seabold Construction Co., Inc., a construc- tion contractor, brought this action against defendant KOZ 2211 SW 4th Ave, LLC, the owner and developer of property to be improved, alleging claims for breach of contract and quantum meruit, arising out of defendant’s alleged failure to pay plaintiff for completed construction. The trial court entered a general judgment for defendant on plaintiff’s amended complaint and a supplemental judgment awarding defendant attorney fees. Plaintiff appeals both the general and supplemental judgments, assigning error to the trial court’s dismissal (from the original complaint) of its quan- tum meruit claim for failure to state a claim and to its dis- missal of the amended complaint with prejudice for untime- liness, lack of compliance with a court order, and failure to state a claim. Plaintiff also assigns error to the award of attorney fees to defendant in the supplemental judgment. We conclude that the trial court did not err in dismissing the quantum meruit claim as alleged in the original com- plaint and did not err in dismissing the amended complaint with prejudice. Because plaintiffs’ arguments about the attorney fees turn on the success of its other assignments, our conclusions regarding the general judgment also resolve the assignment regarding fees. We therefore affirm. As pertains to the breach of contract claim, plain- tiff’s original complaint alleged: “4. On or about February 23, 2018, [plaintiff] and [defendant] entered into a written contract (the ‘Contract’) for the performance of labor and furnishing of materials to be used in construction of the Property. “5. [Plaintiff] completed performance under the Contract. However, [defendant] has refused to pay [plain- tiff] the full amounts due and owing to [plaintiff]. “6. The total amount due to [plaintiff] is $1,647,159, inclusive of [plaintiff’s] construction lien (‘Lien’) against the Property, less credits and offsets, which Lien is in the sum of $261,072.44. “7. [Plaintiff] filed its Lien on October 15, 2020 within the time prescribed by ORS 87.035 to secure payment of the amount of $261,072.44. Cite as 344 Or App 688 (2025) 691

“* * * * * “18. [Defendant] breached the Contract by failing and refusing to pay [plaintiff] all amounts due under the Contract. The total owing to [plaintiff] under the Contract is $1,647,159. “19. As a result of [defendant’s] breach of the Contract, [plaintiff] has been damaged in the sum of $1,647,159 plus attorneys’ fees and interest as required by the Contract or as otherwise permitted by law.” For its quantum meruit claim, plaintiff alleged: “21. The labor and materials alleged and described herein above were actually used for the benefit of the Property. “22. The amount, type, and quantity of the labor and materials provide by [plaintiff] and used in the construc- tion of the improvement were reasonable. “23. [Defendant] had a duty to afford [plaintiff] a fair and reasonable opportunity to begin and complete the work within the time originally specified in the Contract, and to furnish sufficient plans and specifications so that [plaintiff] could begin and finish the work within the con- tractually prescribed period without being subjected to unreasonable costs or expenses on account of delays or interference caused by [defendant]. [Defendant] breached these duties by failing to furnish sufficient plans and spec- ifications, including without limitation, permitted plans for the mechanical system for the project, which hindered and delayed [plaintiff’s] work. Consequently, [plaintiff] is entitled to recover from [defendant] the market value of its work, including its profit, overhead and interest.” Defendant filed a motion to dismiss plaintiff’s com- plaint, asserting that the complaint failed to state a claim under ORCP 21 A(1)(h).1 In the alternative, defendant sought an order requiring plaintiff to make the complaint more definite and certain. Defendant attached a copy of the parties’ contract to the motion, which had not been attached to the original complaint. Defendant argued that, as cor- rectly construed, the contract shows that plaintiff’s claims

1 When defendant filed its motion, ORCP 21 A(1)(h) was numbered ORCP 21 A(8). In this opinion, we refer to the rule as currently numbered. 692 Seabold Construction v. Koz 2211 SW 4th Avenue

in fact arise out of plaintiff’s breach of the construction con- tract in failing to timely perform its obligations under the contract. Such delays, defendant contended, occurred as a result of plaintiff’s failure to comply with the change order provisions of the contract. Defendant cited three provisions of the contract that it argued provided the only possible circumstances under which plaintiff could seek damages under the con- tract and argued that none of those existed. Most signifi- cantly, defendant quoted a provision of the contract that related to change orders: “No Change in the Work, whether by way of alteration or addition to the Work, shall be the basis of an addition to the Contract Price or a change in the Contract Time unless and until such alter[ation] or addition has been authorized by Change Order or written Construction Change Directive executed with and in strict compliance with the require- ments of the Contract Documents. This requirement is of the essence of the Contract.” Defendant argued that it could not determine from the alle- gations of the complaint the services that plaintiff alleged it had performed for which it did not receive payment. Defendant thus argued that plaintiff did not have a claim for breach of contract, or that plaintiff should be required to make the complaint more definite and certain. Defendant further argued that plaintiff did not have a claim for quantum meruit, because the allegations of the complaint show that the quantum meruit claim was based on a valid and enforceable contract. Plaintiff argued that, after conferring with defen- dant’s counsel, it had drafted and sent to the court and to defendant a proposed amended complaint that identified specific provisions of the contract that plaintiff asserted imposed on defendant a duty not to interfere with plain- tiff’s performance. Plaintiff’s proposed amended complaint, which the court said it had read, alleged a new theory of con- tractual relief—an implied covenant of noninterference. It also alleged that, in their past dealings and course of perfor- mance, the parties had waived the contract’s requirements relating to change orders. Plaintiff attempted to argue those Cite as 344 Or App 688 (2025) 693

theories to the court, but the court declined to consider the theories raised in the proposed amended complaint, which had not yet been filed with the court, explaining that the operative pleading against which defendant’s motion must be evaluated was the original complaint, not the drafted proposed amended complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seabold Construction v. Koz 2211 SW 4th Avenue
344 Or. App. 688 (Court of Appeals of Oregon, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
344 Or. App. 688, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seabold-construction-v-koz-2211-sw-4th-avenue-orctapp-2025.