Dale's Sand & Gravel Co. v. Westwood Construction Co.

661 P.2d 1378, 62 Or. App. 570, 1983 Ore. App. LEXIS 2562
CourtCourt of Appeals of Oregon
DecidedApril 13, 1983
Docket39 159, CA A22245
StatusPublished
Cited by9 cases

This text of 661 P.2d 1378 (Dale's Sand & Gravel Co. v. Westwood Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dale's Sand & Gravel Co. v. Westwood Construction Co., 661 P.2d 1378, 62 Or. App. 570, 1983 Ore. App. LEXIS 2562 (Or. Ct. App. 1983).

Opinion

*572 WARDEN, J.

This case originated as a suit to foreclose a construction lien. Dale’s Sand & Gravel Co., Inc. (Dale’s) was a subcontractor that performed excavation and compacting work on a construction project. Instead of suing the owner of the property, LandAmer Realty, Inc. (LandAmer), to foreclose its lien, Dale’s sued the general contractor, West-wood Construction Co. (Westwood). Westwood brought a third-party indemnity action against LandAmer, which in turn sought indemnity from Waker Associates, Inc. (Waker), the engineers who prepared the specifications for the project. The trial court refused to foreclose the lien but awarded Dale’s a judgment against Westwood for damages on a quantum meruit basis, together with pre-judgment interest on the damage award, for extra work done. The trial court also awarded judgment against Westwood in its indemnity action against LandAmer. Westwood appeals from both judgments. 1

We first must resolve the question of our scope of review. Westwood contends that because the case was initiated as a lien foreclosure, an equitable proceeding, and because the parties never objected to the court sitting in equity hearing all the claims, legal and equitable, our review of the entire matter is de novo under ORS 19.125(3). Westwood relies on Allan & Leuthold v. Terra Inv., 271 Or 335, 532 P2d 218 (1975), and Davison v. Parker, 50 Or App 129, 622 P2d 1113, rev den 290 Or 853 (1981). Allan & Leuthold is unpersuasive authority, because it was decided before the amendments to ORS 87.060(2) and (3). See Or Laws 1975, chapter 466, § 16. Those sections now read:

“(2) In suits to enforce the liens created by ORS 87.010, the court shall allow or disallow the lien. If the lien is allowed, the court shall proceed with the foreclosure of the lien and resolve all other pleaded issues. If the lien is disallowed, and a party has made a demand for a jury trial as provided for in subsection (3) of this section, the court shall empanel a jury to decide any issues triable of right by a jury. All other issues in the suit shall be tried by the court.
*573 “(3) A party may demand a trial by jury of any issue triable of right by a jury after the lien is disallowed, if that party serves a demand therefor in writing upon the other parties at any time prior to commencement of the trial to foreclose the lien. The demand shall be filed with the court. The failure of a party to serve a demand as required by this subsection shall constitute a waiver by the party of trial by jury. A demand for trial by jury made as provided in this subsection may not be withdrawn without the consent of the parties.”

They do not exactly answer the question. The sentence, “[a]ll other issues in the suit shall be tried by the court,” leaves unclear whether it refers to a court sitting in equity or law. However, we have relied upon this statute for the proposition that in a case involving a lien foreclosure as well as legal claims, “once the lien has been disallowed the case then continues as an action at law” and that the determination of a legal issue by the court is “the equivalent of a jury verdict.” Betz Construction v. Peterson, 47 Or App 333, 337, 614 P2d 1184, rev den 289 Or 677 (1980). Allan & Leuthold is thus no longer controlling. In Davison v. Parker, supra, citing Allan & Leuthold, we held that a party who fails to move, at the conclusion of the lien proceeding, to have the case transferred to the law side of the court, waives any objection to equity jurisdiction over the legal claims. 2 Motions to transfer a case from law to equity or from equity to law may have made sense at a time when procedure in the two sides differed. See, e.g., Oregon Farm Bureau v. Thompson, 235 Or 162, 176, 378 P2d 563, 384 P2d 182 (1963) (opinion on rehearing). Procedural distinctions between law and equity have been abolished by ORCP 2, 3 and a motion to transfer a case from equity to law now has little significance. We therefore adhere to our ruling in Betz Construction v. Peterson, supra, that even without a request for a jury, legal claims which have been joined with equitable claims are heard in law and reviewed for substantial evidence, while the equitable claims *574 are reviewed de novo. In this case, Dale’s argues in its cross-appeal only that the trial judge miscalculated the damages awarded, not that its lien was valid and should have been foreclosed. Our scope of review is thus for substantial evidence. 4

Much of Westwood’s appeal is based on its claim that there was insufficient evidence to support the trial court’s findings. Westwood and Dale’s initially both submitted bids to LandAmer for the construction of streets, storm drains, and water and sewer systems at Stafford Park, a commercial development in Wilsonville. Dale’s was the low bidder, but Westwood, which had had previous dealings with LandAmer, was awarded the contract. Westwood then subcontracted with Dale’s for six items, for a total price of $49,841.60. Dale’s was to perform work involving excavation, grading and compaction of fill materials. Part of the work, item 2.A on bid schedules prepared by Waker and submitted to LandAmer by bidders, was described as “grading, including roadway and channel excavation (approximately 12,000 cubic yards), spread and compacted on site.” This language, as well as the project specifications which Waker had prepared for LandAmer, was incorporated into the subcontract between Dale’s and Westwood. Unknown to all parties, however, Waker had inadvertently omitted from the specifications a paragraph which required that compaction of placed fill be at least 90 percent, with 95 percent compaction in the upper two feet of all fills.

During construction, an agent of Waker on the site noticed that Dale’s was placing fill without compacting it, i.e., Dale’s was not using a compactor. The use of heavy equipment, of course, was producing some degree of compaction. Results of a test by a soil engineering firm revealed compaction in the range of 71-78 percent. Waker’s mistake in omitting the compaction specification was discovered, but Waker insisted that Dale’s perform the compaction anyway, relying on the compaction standards of the *575 “Standard Specifications for Public Works Construction” published by the Oregon chapter of the American Public Works Association (APWA), which was referred to in the subcontract. Dale’s denied that the subcontract required the compaction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strader v. Grange Mutual Insurance
39 P.3d 903 (Court of Appeals of Oregon, 2002)
Gerber v. O'DONNELL
724 P.2d 916 (Court of Appeals of Oregon, 1986)
Banister Continental Corp. v. Northwest Pipeline Corp.
709 P.2d 1103 (Court of Appeals of Oregon, 1985)
Bollam v. Fireman's Fund Insurance
709 P.2d 1095 (Court of Appeals of Oregon, 1985)
Erickson Hardwood Co. v. North Pacific Lumber Co.
690 P.2d 1071 (Court of Appeals of Oregon, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
661 P.2d 1378, 62 Or. App. 570, 1983 Ore. App. LEXIS 2562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dales-sand-gravel-co-v-westwood-construction-co-orctapp-1983.