Shepherd v. Gass

488 P.2d 1180, 260 Or. 84, 1971 Ore. LEXIS 284
Oregon Supreme Court·Decided September 22, 1971·Published·Cited by 2 cases

Opinion

TONGUE, J.

This is a suit in equity by a contractor to determine the amount due on a lien claimed by him for the [86] construction of an apartment house for defendants G-ass and Van Dolah and foreclosing that lien. Plaintiff appeals from a decree which denied plaintiff’s claim of lien and dismissed plaintiff’s complaint.

On this appeal plaintiff contends that the trial court erred in denying plaintiff’s claim of lien because: (1) approval of the work by Equitable Savings & Loan Assoc, was agreed upon by the parties as conclusive upon the owners, so as to bar defendants’ claim of faulty performance, and (2) findings of fact by the court that plaintiff willfully and intentionally departed from the plans and specifications for construction of the budding, without defendants’ consent, are not supported by substantial evidence, but are contrary to the evidence.

In support of the first of these assignments of error plaintiff cites cases holding that the parties to a construction contract may stipulate that approval of the contractor’s performance by a third person, such as an architect, is to be binding upon the parties. The contracts involved in those eases clearly provided that such approval was to be binding upon the parties as compliance with the contract plans and specifications.

Footnotes

Shepherd v. Gass, 488 P.2d 1180, 260 Or. 84, 1971 Ore. LEXIS 284 (Or. 1971).

488 P.2d 1180 (Shepherd v. Gass) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

B & D Investment Corp. v. Petticord
617 P.2d 276 (Court of Appeals of Oregon, 1980)
Walker the Weeper, Inc. v. Commercial Engineering Corp.
584 P.2d 268 (Oregon Supreme Court, 1978)