Barber, Trustee v. Henry

252 P.2d 802, 197 Or. 172, 1953 Ore. LEXIS 164
CourtOregon Supreme Court
DecidedJanuary 21, 1953
StatusPublished
Cited by13 cases

This text of 252 P.2d 802 (Barber, Trustee v. Henry) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barber, Trustee v. Henry, 252 P.2d 802, 197 Or. 172, 1953 Ore. LEXIS 164 (Or. 1953).

Opinion

TOOZE, J.

This is a suit brought by William Gr. East, trustee, as plaintiff, against Howard H. Henry et al., as defendants, to foreclose a lien for labor and materials furnished by Eugene Construction Company, Inc., in the construction of a building upon land owned by defendant Howard H. Henry in Lane County, Oregon.

Before trial plaintiff William Gr. East, having been appointed a judge of the circuit court, resigned as trustee, and John L. Barber, Jr., was appointed trustee in his place and stead and was substituted as party plaintiff.

The trial court entered a decree awarding judgment against defendant Howard H. Henry in the sum of $14,072.34, with interest, attorney’s fees, and costs; decreeing the amount of the judgment to be a valid first lien against the premises owned by said defendant, that the lien be foreclosed, and that the land be sold to satisfy the judgment as provided by law. Defendants Howard H. Henry and Dorothy H. Henry, his wife, appeal.

At the time of the construction of the building involved in this litigation, Eugene Construction Company, Inc., an Oregon corporation, hereinafter referred *174 to as “Construction Company”, was a going concern, engaged in the contracting and building construction business in Lane county.

On June 4, 1948, the Construction Company entered into a written contract with defendant Howard H. Henry for the construction of a supermarket building on land owned by said defendant and located on the McKenzie river highway. The Construction Company agreed to erect the building, furnishing all labor and materials necessary, upon a cost plus 10 per cent basis.

Actual work of construction commenced on or about June 5,1948, and was completed on or about August 15, 1948. On August 23,1948, the Construction Company, as claimant, filed with the county clerk of Lane county its written notice of mechanic’s lien, covering the tract of land owned by defendant Howard H. Henry, upon which the building was erected. The lien notice set forth a total charge for labor and materials in the sum of $17,572.34, with a credit of $3,500, leaving a balance of $14,072.34 due the claimant. Attached to and made a part of the lien notice was an itemized statement of the labor and materials furnished and the charges therefor. However, neither in the lien notice itself, nor in the attached itemized statement, is there any segregation of the items of labor and material as applied to the particular portions of the construction. Alb charges are in lump sums.

On November 4, 1948, the Construction Company assigned its lien to William Gr. East, trustee, for the benefit of certain named creditors, firms and individuals who had furnished to the Construction Company labor and materials for the construction of the building. In the spring of 1949 the Construction Company became an involuntary bankrupt.

*175 .On this appeal defendants set forth seven assignments of error. The view we take of the case renders unnecessary a discussion of any of these assignments except that numbered VI.

Defendants by this assignment allege that “the court erred in allowing plaintiff to introduce into evidence over the objection of the appellants, plaintiff’s exhibit C, being the mechanic’s lien, in upholding the validity of the lien and in decreeing a personal judgment for the full amount of the lien”, because, as defendants assert, the lien notice is defective in the following particulars:

“1. Lienable and non-lienable items are lumped together in unsegregational form.
“2. Failure to make a true statement of the demand in the lien notice.
“3. The corporation seal does not appear on the lien notice.”

The decisive question in this case is whether lien-able and nonlienable items have been so lumped together in the lien notice that a segregation thereof cannot be made except by resort to evidence aliunde.

It has become hornbook law in this state that a lien cannot be upheld if the lien notice mingles in unsegregational form lienable and nonlienable items. Such a defect cannot be cured by oral evidence, by means of which the items for which a lien is given may be separated from those for which a lien is not given. Christman v. Salway et al., 103 Or 666, 672, 205 P 541.

In its findings and decree the trial court took notice of one nonlienable item appearing in the lien notice; viz., a charge of $20 for a water connection. This item was stricken.

*176 However, the record discloses that in the lump sum charges for labor and material as shown in the lien notice there are included, without any segregation, charges for the construction of certain equipment inside the building. Defendants maintain that these articles of equipment were trade fixtures only; that they were in no sense attached to the realty, remained personal property, and, therefore, constituted nonlienable items. If those items are nonlienable, as contended by defendants, the lien is invalid.

Acting for the Construction Company, Edward E. Scott, its then president, superintended the erection of the building. As a witness for plaintiff, Scott testified on cross-examination:

“Q And isn’t it a fact that there were items there for the placing of groceries ? Can you describe those to the Court?
“A Well, the bigger part of the — the front,inside the front windows was trays or racks for vegetables, shelving along the — I believe along the entire east side of the building for canned goods and such things, and part of the north side, I believe, up to the bat wing doors. Then west of the doors was larger shelves. I believe I am right — for bigger boxes, oh, breakfast foods and such things. Then there were all the islands that Mr. Henry requested. ■
“Q What are the islands ? Describe those, will you?
“A Well, they are the shelves for display in the center of the room, in the center of the building.
“Q They are placed in the very center of the building, aren’t they?
“A Yes. Well, they are all over the building.
‘ ‘ Q You can move them over the building where-ever you want to, isn’t that the idea?
“A Yes, that is true. They were portable units. *177 All those in the center of the building were portable units.
“Q How many units were there of that type?
“A I can’t remember that, whether six or eight, or how many of those I wouldn’t attempt to say now.
i ( * A- # * #
“Q Anyway, some of that plywood there was used for these islands in the middle of the store, is that right?
“A All the plywood.
‘ ‘

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shepherd v. Gass
488 P.2d 1180 (Oregon Supreme Court, 1971)
Lemire v. McCollum
425 P.2d 755 (Oregon Supreme Court, 1967)
General Electric Co. v. E. Fred Sulzer and Co.
207 A.2d 346 (New Jersey Superior Court App Division, 1965)
Christenson v. Behrens
372 P.2d 494 (Oregon Supreme Court, 1962)
George H. Buckler Co. v. American Metallic Chemical Corp.
332 P.2d 614 (Oregon Supreme Court, 1958)
Waldorf v. Elliott
330 P.2d 355 (Oregon Supreme Court, 1958)
Lakeview Drilling Co. v. STARK
310 P.2d 627 (Oregon Supreme Court, 1957)
Flaherty v. Bookhultz
297 P.2d 856 (Oregon Supreme Court, 1956)
ELLIOTT ET UX v. Tallmadge
297 P.2d 310 (Oregon Supreme Court, 1956)
Nelson v. Hampton Et Ux
294 P.2d 329 (Oregon Supreme Court, 1956)
State Highway Commission v. Superbilt Manufacturing Co.
281 P.2d 707 (Oregon Supreme Court, 1955)
Anderson v. Chambliss Et Ux.
262 P.2d 298 (Oregon Supreme Court, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
252 P.2d 802, 197 Or. 172, 1953 Ore. LEXIS 164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barber-trustee-v-henry-or-1953.