George H. Buckler Co. v. American Metallic Chemical Corp.

332 P.2d 614, 214 Or. 639, 1958 Ore. LEXIS 352
CourtOregon Supreme Court
DecidedDecember 3, 1958
StatusPublished
Cited by2 cases

This text of 332 P.2d 614 (George H. Buckler Co. v. American Metallic Chemical Corp.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George H. Buckler Co. v. American Metallic Chemical Corp., 332 P.2d 614, 214 Or. 639, 1958 Ore. LEXIS 352 (Or. 1958).

Opinion

LUSK, J.

This is a suit to foreclose a lien on chattels. The circuit court entered a decree granting judgment in favor of the plaintiff for the amount claimed, to-wit, $50,362.23, with interest, attorney’s fees, and costs, and ordering the property .upon which the lien is asserted sold for the satisfaction of such judgment.

[641]*641The controversy had its inception in a contract in writing entered into under date of November 20, 1951, by the plaintiff, George H. Buckler Co., an Oregon corporation, hereinafter called “Buckler”, and the defendant, The American Metallic Chemical Corp., a Delaware corporation, hereinafter called “American”, under which Buckler agreed to provide labor and materials for the proper construction and completion of a chemical plant in Portland, Oregon, for American. The work to be done by Buckler is thus specified in the contract:

“1. Rehabilitation of the former boiler erection building approximately 77'x 166' located 356' west of the Container Corporation Building at the Former Oregon Shipbuilding Corporation tract.
“2. Rehabilitation of former fire brick storage buildings, approximately 150' x 150', located adjacent to former Boiler Erection Buildings.
“3. Any and all new construction work not covered by Item 1 and Item 2, mechanical construction, electrical construction, in order to make a complete processing plant.”

The work thus described included the installation of motors, generators, plumbing, heating, piping, electrical work, bus bars, bus switches for power, bucket conveyors and hoppers, an agitator and what are designated as a Skinner Roaster, a Baker Cooler, and a Williams Mill. In consideration of the performance of the contract, American agreed to pay Buckler cost plus ten per cent profit, plus two per cent overhead, payments to be made before the 10th of each month following date of billing.

The land and buildings referred to in the contract were held by American under a five-year lease, with an option to renew for an additional period of five [642]*642years. The lease contemplated that the lessee was to adapt the premises for nse as a chemical plant and install the equipment for such purpose, and contained a provision “that all facilities including electrical fixtures and equipment and pipes which are installed by Lessee and which are part of the equipment used in manufacturing, packaging and distribution of chemicals, metals and metal products and which are moveable without destroying the basic structure of the premises leased, and all moveable stores and office fixtures shall be and remain the property of the Lessee.”

Buckler, commenced the work October 15, 1951. Its last billing was for payroll for the period commencing July 7, 1953, and ending September 27, 1953. The total amount billed was $221,548.60. The total amount paid by American was $171,185.37, leaving a balance of $50,363.23.

On September 29, 1953, Buckler filed a notice of lien on chattels with the County Clerk of Multnomah County, describing the property upon which the lien was claimed as follows:

“1—Skinner Roaster,
1—Baker Cooler,
1—Williams Mill,
1—Paddle Agitator in Leeching Tank,
1—Westinghouse Motor Generator Set and appurtenances,
ALL Bucket conveyors and hoppers,
ALL process piping,
Bus bar and all electrical installation and equipment not part of the realty.”

The notice averred that the lien was claimed “for and on account of labor, skill and materials expended upon the said property between the 15th day of October, 1951, and the 25th day of September, 1953”; that the [643]*643expenditure of labor, skill and materials was completed on September 25, 1958; that the claimant demanded therefor $159,118.60; that no part thereof had been paid except $108,756.37, and that there was a balance due of $50,362.23, for which amount a lien upon the property described was claimed.

The evidence establishes that the plaintiff performed its contract and, in particular, (disregarding criticisms by American of insufficiency in the description of certain of the items and asserted failure to prove the averment as to “all” bucket conveyors and the bus bar) that it expended labor and materials upon the chattels described in the notice of lien. All monthly statements submitted by Buckler during the progress of the work were promptly paid up to and including the statement for June, 1952. Subsequent payments were credited by Buckler to the indebtedness for work done through September and a part of October. As previously stated, and as shown by Buckler’s own evidence, the balance owing upon the entire job at the completion of the contract was $50,363.23. This is the identical amount, save for one dollar

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arrowood Indemnity Co. v. Fasching
503 P.3d 1233 (Oregon Supreme Court, 2022)
Wiggins v. SOUTHWOOD PARK CORP.
350 P.2d 436 (Oregon Supreme Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
332 P.2d 614, 214 Or. 639, 1958 Ore. LEXIS 352, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-h-buckler-co-v-american-metallic-chemical-corp-or-1958.