General Electric Co. v. E. Fred Sulzer and Co.

207 A.2d 346, 86 N.J. Super. 520
CourtNew Jersey Superior Court Appellate Division
DecidedFebruary 18, 1965
StatusPublished
Cited by12 cases

This text of 207 A.2d 346 (General Electric Co. v. E. Fred Sulzer and Co.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Electric Co. v. E. Fred Sulzer and Co., 207 A.2d 346, 86 N.J. Super. 520 (N.J. Ct. App. 1965).

Opinion

86 N.J. Super. 520 (1965)
207 A.2d 346

GENERAL ELECTRIC COMPANY, A NEW YORK CORPORATION, PLAINTIFF,
v.
E. FRED SULZER AND COMPANY, A NEW JERSEY CORPORATION, CONTRACTOR, AND FRANK BRISCOE COMPANY, INC., A NEW JERSEY CORPORATION, BUILDER, AND AMERICAN CYANAMID COMPANY, A MAINE CORPORATION, OWNER, AND BARNET H. EPSTEIN, TRUSTEE OF THE ESTATE OF E. FRED SULZER AND COMPANY, A BANKRUPT CORPORATION, DEFENDANTS.

Superior Court of New Jersey, Law Division.

Decided February 18, 1965.

*524 Messrs. McCarter & English, attorneys for plaintiff (Mr. James R.E. Ozias and Mr. Julius B. Poppinga, appearing).

Messrs. Levy, McCloskey, Schlesinger & Tischler, attorneys for defendants (Mr. Milton M. Breitman and Mr. John J. McCloskey, appearing).

LORA, J.S.C.

This is an action on a mechanic's lien claim wherein plaintiff materialman seeks judgment generally against the electrical subcontractor with whom it had contracted and specially against the owner of the lands and building.

Plaintiff General Electric Company (G.E.) seeks to enforce a lien claim against property of defendant American Cyanamid Company (Cyanamid) for materials and labor furnished *525 in the construction of Cyanamid's Executive and Administrative Center in Wayne Township, for which construction Frank Briscoe Company, Inc. (Briscoe) was the general contractor.

The electrical subcontractor, defendant E. Fred Sulzer and Co. (Sulzer), is in bankruptcy, and both Sulzer and Barnet H. Epstein, trustee of the estate of E. Fred Sulzer and Co., a bankrupt corporation, have failed to appear in this action and default has been entered against them pursuant to plaintiff's request for entry of default dated August 3, 1962 and filed herein.

By written contract dated February 1, 1961 Cyanamid, as owner, engaged Briscoe, as general contractor, to construct the said Center upon lands owned by Cyanamid.

Under date of February 13, 1961, by written contract, Briscoe engaged Sulzer to perform the electrical work on said project. On August 1, 1961, G.E., by its division, General Electric Supply Company (which is not separately incorporated), caused to be filed in the office of the Passaic County Clerk a notice of intention in proper statutory form and thereafter gave due notice of such filing to both Cyanamid and Briscoe. All of this was done in accordance with N.J.S. 2A:44-65, 71 and 72.

It has been stipulated that after August 1, 1961 and prior to January 10, 1962 G.E. delivered, on requisition or order of Sulzer, materials and services having an aggregate value of $312,975.01. One or more of the deliveries were made between December 25 and 29, 1961. It has also been stipulated that some materials and services were delivered and rendered prior to August 1, 1961.

Neither the Cyanamid-Briscoe nor the Briscoe-Sulzer contract was filed pursuant to N.J.S. 2A:44-75.

On April 25, 1962, which date was within four months from the date of the furnishing of the last materials or services by G.E., said company caused to be filed a mechanic's lien claim in proper statutory form in the Passaic County Clerk's Office upon which commencement of suit was endorsed by said county clerk pursuant to N.J.S. 2A:44-91, 92 and *526 99, and instituted this action by the filing of its complaint in the office of the Clerk of the Superior Court of New Jersey in accordance with N.J.S. 2A:44-98. By successive orders of this court, the time period prescribed by N.J.S. 2A:44-99 for prosecution of the claim to judgment has been extended to March 15, 1965.

The value of the materials and services for which a lien is claimed has been fixed by stipulation at $312,975.01, which sum is the amount due G.E. from Sulzer, less certain adjustments made for purposes of the stipulation of March 18, 1964. On April 22, 1964 judgment was granted against the defaulting defendants for $312,975.01, together with interest and costs.

The courts have been fairly unanimous in stating that those provisions of the statute creating the lien should be strictly construed, while those concerned with the enforcement thereof are to be liberally interpreted, Friedman v. Stein, 4 N.J. 34 (1950); Apex Roofing Supply Co. v. Howell, 59 N.J. Super. 462 (App. Div. 1960); Elliot-Farber Roofing & Siding Supply Co. v. Saitta, 79 N.J. Super. 568 (App. Div. 1963).

I.

Briscoe and Cyanamid have raised as a separate defense and contend that G.E. waived its lien rights by furnishing materials with knowledge of the provisions of the Cyanamid-Briscoe contract or of the Briscoe-Sulzer contract, or of both of said contracts.

The pertinent provisions of the aforesaid contracts are as follows:

CYANAMID-BRISCOE CONTRACT, CONDITION XI, LIENS

"CONTRACTOR shall indemnify and save harmless CYANAMID from all claims, demands, causes of action, or suits of whatever nature arising out of the labor and materials furnished by CONTRACTOR and its sub-contractors under this contract, and from all laborers', materialmen's and mechanics' liens upon the work or upon the property upon which the work is located arising out of the labor and materials furnished by CONTRACTOR and its sub-contractors under this *527 contract, and shall keep the work and said property free and clear of all liens, claims, and encumbrances arising from the performance of this contract by CONTRACTOR and its sub-contractors.

BRISCOE-SULZER CONTRACT

ARTICLE V. Sub-contractor agrees to co-operate with Contractor and all other Sub-contractors employed on the work in order to avoid complications and insure first-class workmanship in every respect, and further, that in the manufacturing, assembling and execution of the work, he will employ only men whose work will be acceptable to and in harmony with other workmen on the building. Sub-contractor further covenants and agrees on behalf of himself, his sub-contractors, materialmen and all parties acting through or under him that no mechanics' claims or liens shall be filed by him or any one acting through or under him, against the premises or buildings or fund covered by this contract. Sub-contractor shall deliver to the Contractor if and when required a complete release of all liens arising out of this contract or receipts in full in lieu thereof and if and when required an affidavit that to the best of his knowledge, information and belief the releases and or receipts include all of the labor and materials for which a lien could be filed.

* * * * * * * *

ARTICLE X * * *. The Sub-contractor shall submit to the Contractor an application for each payment, and if required, receipts or other vouchers showing payment for materials and labor. The Contractor may withhold payment to protect the Contractor from loss on account of, (a) defective work not remedied, (b) claims filed or reasonable evidence indicating the probable filing of mechanics' liens against the premises or buildings, or the fund for the construction of improvement, (c) failure of the Sub-contractor to make payments properly to materialmen and laborers, (d) a reasonable doubt that the Contract cannot be completed for the balance then unpaid."

Defendants cite the case of Bates Machine Co. v. Trenton, &c., R.R. Co., 70 N.J.L. 684 (E. & A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jersey Shore Medical Center v. Neptune Township
14 N.J. Tax 49 (New Jersey Tax Court, 1994)
Burger King Corp. v. Director
9 N.J. Tax 251 (New Jersey Tax Court, 1987)
In Re Gibson
16 B.R. 257 (D. Kansas, 1981)
Eisenberg v. Committee to Recall Levin
417 A.2d 1067 (New Jersey Superior Court App Division, 1980)
Yde v. State
376 A.2d 465 (Supreme Judicial Court of Maine, 1977)
Arcell v. Ashland Chemical Co., Inc.
378 A.2d 53 (New Jersey Superior Court App Division, 1977)
Shore Block Corp. v. Lakeview Apartments
377 F.2d 835 (Third Circuit, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
207 A.2d 346, 86 N.J. Super. 520, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-electric-co-v-e-fred-sulzer-and-co-njsuperctappdiv-1965.