Hudson v. McCartney

33 Wis. 331
CourtWisconsin Supreme Court
DecidedJune 15, 1873
StatusPublished
Cited by45 cases

This text of 33 Wis. 331 (Hudson v. McCartney) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hudson v. McCartney, 33 Wis. 331 (Wis. 1873).

Opinion

Dixon, C. J.

The questions argued by counsel for'the defendant are all fairly presented by the exceptions taken to the order overruling the second motion for a nonsuit made at the close of the testimony, and to the order denying the motion for a new trial; and the same need not, therefore, be examined with reference to the charge of the court, or the exceptions taken, or supposed to have been, to the charge.

And the questions so presented are by no means intricate or doubtful. In view of the numerous adjudications which have been made upon them, and which are collected and referred to by counsel for the defendant, they may be said to be very plain and easy ones. Our views respecting them correspond very nearly, if not fully, with those expressed by the defendant’s counsel. It was clearly competent for the plaintiffs to stipulate that they should only demand or receive payment for the work as the same was executed to the full and complete satisfaction of McDonald, the superintendent of the erection of the dwelling, and upon his certificates as the work progressed; and such [341]*341satisfaction of the superintendent, and the execution of the certificate by him, became and was a condition precedent to the right of the plaintiffs to demand or sue for the price agreed ■ to' be paid by the defendant Cor the work, unless the refusal to certify should be disregarded or annulled on the ground of fraud or bad faith, or clear evidence of mistake on the part of the superintendent. And should the certificate be fraudulently or corruptly withheld by the superintendent, it would still be the opinion of some most respectable courts that there could be no recovery against the defendant, unless the withholding was in collusion with him and by his procurement. It has been, held that the refusal to accept or certify must be shown to have been the wrongful or fraudulent act of the defendant or opposite party to the contract, as well as of the surveyor or architect. Clarke v. Watson, 18 C. B., N. S. (114 E. C. L.), 278; Batterbury v. Vyse, 2 Hurl. & Colt., 42.

And the case of Thomas v. Fleury, 26 N. Y., 26, cited and relied upon by counsel for the plaintiff, and some remarks in the opinion in which seem to be at variance with the uniform tenor of decision both in that state and elsewhere, clearly recognizes the precedent and qualifying nature of the condition requiring the certificate to be procured. Speaking of the earlier stages of the work, and before it had been completed and .possession taken of it by the defendant, the court say : “At these stages, if the architect was not satisfied, he could withhold the certificate, and withoutit the defendant could refuse to pay.”

But we are not called upon to ponder or decide the question as to when or under what circumstances bad faith or fraud in the superintendent will operate to relieve against his refusal to give the certificate, or to make the promise to pay obligatory upon the defendant without the certificate. There was no evidence that the superintendent acted either frahdulently or corruptly in his refusal to certify, or in the suspension of the further prosecution of the work by the plaintiffs. His conduct appears to have been fair and just, and in pursuit of what he [342]*342conceived to be bis duty in the situation. There may have been a scintilla of evidence, but no more, tending to show some disagreement or rupture between the superintendent and one of the plaintiffs a considerable time before; but there was nothing to justify the conclusion that he was actuated by malice or ill will, or that he behaved dishonestly and partially in the premises.

Neither do we think the case was one where the jury should have been permitted to go into evidence of the manner in which the work was executed, for the purpose of impeaching the decision of the superintendent or arbiter. The case should no more have been submitted to the jury upon this as evidence to establish fraud in the superintendent, than upon the other evidence just spoken of and which was offered with the same design. If fraud in the arbiter can ever be established by proof that he refused to certify the execution of the work when the same had been duly and properly performed, it can only be in those cases where the refusal is shown to have been grossly and palpably perverse, oppressive and unjust, so much so that the inference of bad faith and dishonesty would at once arise when the facts are known. No such facts were presented by this case, and, as argued by counsel for the defendant and sustained by the adjudications, it is not upon every claim made by the mechanic or workman that he has complied with his contract, or upon every controversy arising between him and the arbiter, that the power of deciding is to be taken away from the latter, and the question carried into a court of law, there to be determined by a jury of twelve inexperienced men, or by the judge of the court alone. If this were otherwise, and if, upon every difference springing up between the superintendent and the party contracting to do the work, the former is deprived of a,11 authority to decide, then such covenants and stipulations en.tered into between parties become utterly nugatory and useless. But such is not the view which has uniformly been taken by the courts, by which such stipulations have been held valid and effectual to secure to the party in whose favor they are made [343]*343the advantage of having the work inspected and its quality and character determined, with reference to the requirements of the contract, by a person of adequate skill and ability to form a correct judgment in such matters. “ Every man is the master of the contract he may choose to make; and it is of the highest importance that every contract should be construed according to the intention of the contracting parties. And it is important in a case of this description, that the person for whom the work has been done should not be called upon to pay for it until some competent person shall have certified that the work has been properly done according to the contract and specifications.” Per Erle, C. J., in Clarke v. Watson, supra. It is manifest that this important object will be defeated, and the protection of a skilled and experienced superintendent lost, if in every case of disagreement or dissent on the part of the contractor, the opinion of a jury is to be substituted. Having deliberately and of his own free will made choice of a person as fit and competent to decide, and by whose determination he has agreed to abide, it is but reasonable and proper that the contractor should be held to the performance of his agreement. The case here presented differs not, therefore, from those which have frequently arisen and been decided upon contracts of this description, and with respect to which the general rule of law is correctly stated in Baasen v. Baehr, 7 Wis., 521. That was the , case of an agreement to pay for extra work at the estimate of an architect agreed upon, and it was held that the contractor must abide by such estimate. This court said: “The parties saw fit to make the architect the umpire between them, and if he exercised his best judgment, in good faith, and with an honest intention of determining the real value of the extra work, his estimates are binding upon them. His decision ought not to be disturbed without some statement going to show that it was made under a mistake, or was not honest. Clauses in contracts analogous in principle to the one now under consideration, have frequently been construed by courts, and the general [344]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ekstrom v. State
172 N.W.2d 660 (Wisconsin Supreme Court, 1969)
Price v. Ross
172 N.W.2d 633 (Wisconsin Supreme Court, 1969)
City of Wauwatosa v. Jacobus & Winding Concrete Construction Co.
271 N.W. 21 (Wisconsin Supreme Court, 1937)
Reaugh Construction Co. v. Corlett
23 Ohio N.P. (n.s.) 336 (Cuyahoga County Common Pleas Court, 1920)
Shine v. Hagemeister Realty Co.
172 N.W. 750 (Wisconsin Supreme Court, 1919)
Keachie v. Starkweather Drainage District
170 N.W. 236 (Wisconsin Supreme Court, 1919)
Hoskins v. Powder Land & Irr. Co.
176 P. 124 (Oregon Supreme Court, 1918)
Hennebique Construction Co. v. Boston Cold Storage & Terminal Co.
119 N.E. 948 (Massachusetts Supreme Judicial Court, 1918)
First Savings & Trust Co. v. Milwaukee County
148 N.W. 22 (Wisconsin Supreme Court, 1914)
Bush v. Jones
144 F. 942 (Third Circuit, 1906)
Halsey v. Waukesha Springs Sanitarium Co.
104 N.W. 94 (Wisconsin Supreme Court, 1905)
Davis v. La Crosse Hospital Ass'n
99 N.W. 351 (Wisconsin Supreme Court, 1904)
Plumbing Co. v. Carr
46 S.E. 458 (West Virginia Supreme Court, 1903)
McGlauflin v. Wormser
72 P. 428 (Montana Supreme Court, 1903)
Vanderhoof v. Shell
72 P. 166 (Oregon Supreme Court, 1903)
National Contracting Co. v. Commonwealth
66 N.E. 639 (Massachusetts Supreme Judicial Court, 1903)
J. G. Wagner Co. v. Cawker
88 N.W. 599 (Wisconsin Supreme Court, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
33 Wis. 331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hudson-v-mccartney-wis-1873.