Davis v. La Crosse Hospital Ass'n

99 N.W. 351, 121 Wis. 579, 1904 Wisc. LEXIS 45
CourtWisconsin Supreme Court
DecidedApril 19, 1904
StatusPublished
Cited by39 cases

This text of 99 N.W. 351 (Davis v. La Crosse Hospital Ass'n) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. La Crosse Hospital Ass'n, 99 N.W. 351, 121 Wis. 579, 1904 Wisc. LEXIS 45 (Wis. 1904).

Opinion

Maeshall, J.

Whether the judgment should be affirmed Qr not depends upon the solution of three plain propositions: First, did the stipulation in the contract, to deliver the building free of all claims, liens, and charges, preclude respondents from filing a lien to enforce payment of any sum they might be compelled to recover of appellant by action ? Sec- [583]*583and, was tlie court warranted in holding that the provision of the contract'as to forfeiture of claims for extra work was waived? Third, was the court warranted in ignoring the architect’s certificate as regards whether the building could reasonably have been completed by the time stipulated in the contract? We will consider each of such propositions.

1. A builder may waive his right to the lien remedy given by statute, and does so by agreeing not to exercise such right. Seeman v. Biemann, 108 Wis. 365, 84 N. W. 490. Such an. agreement may he made by an express stipulation not to file-a lien (Fidelity Mut. L. Asso. v. Jackson, 163 Pa. St. 208, 29 Atl. 883; Schroeder v. Galland, 134 Pa. St. 277, 19 Atl. 632; Benedict v. Hood, 134 Pa. St. 289, 19 Atl. 635; Ballman v. Heron, 160 Pa. St. 377, 28 Atl. 914); or by agreement in form that no lien shall be filed on the building under the lien laws of the state (Seeman v. Biemann, supra); or by an agreement that the builder “will not suffer or permit a lien to be filed” (Scheid v. Rapp, 121 Pa. St. 593, 15 Atl. 652); or by the giving of a bond by the builder that no lien shall be filed on the building (Pinning v. Skipper, 71 Md. 347, 18 Atl. 659); or in any other way clearly showing such to be the intention of the parties. But where the terms of a contract are ambiguous on the question, the doubt should be resolved against the waiver, since it should be presumed, in the absence of clear evidence to the contrary, that one has not disabled himself from the use of so valuable a privilege as that given by statute for the enforcement of a builder’s rights in the circumstances involved in such a case as this. The stipulation here was for the delivery of the building, “free from all claims, liens, and charges” on or before November 1, 1900, etc. Payment of the contract price was agreed to be on monthly estimates made by the architect, less fifteen per cent., which reserved amount it was stipulated should be .paid when the contract was completed and the architect satisfied that the building was in fact free from all [584]*584liens. Now it seems quite plain that the liens referred to in the last clause mentioned are the same as those referred to in the other clause. If so, it is obvious that the claims and liens in question are of a special class. It would be absurd to provide that a contractor shall be paid the amount due him for constructing a building upon satisfactory proof being made that he has no lien; while a provision that payment will be made upon such proof being made as regards those claiming under him would be reasonable, and is the common form of-agreement. Our construction of the language of the contract is that it called for a delivery of the building free from any lien or claim for a lien through or under the builder. It could not reasonably have had reference to any lien filed by the builder, because the contract contemplated the probable lapse of time for making the last payment, after the completion of the building, — time sufficient to enable the architect to determine whether there were any liens, claims, or charges thereon. It was contemplated that there would be nothing due him till the happening of conditions precedent, which might not occur till after the day of delivery. Such was the case. The building was delivered before respondents had any cause of action against appellant. There was no lien on file at the time of the delivery, nor for some time thereafter, nor was there, so far as appears, any claim that might ripen into a lien, except that of respondents. It is considered that it was not intended by the parties to the contract that respondents should-not have the statutory lien remedy to enable them to collect any sum that might be in the end due them, and payment of which they might be compelled to enforce by action.

2. In support of the court’s ruling that the provision of the contract in regard to forfeiting claims for additions to the contract work and material, was waived, counsel for respondents suggest that such a provision can be waived, and cite Bannister v. Patty’s Ex’rs, 85 Wis. 215. True, such a [585]*585provision can be waived; bnt that does not warrant holding, whenever a thing is done under a contract for which, by the terms thereof, additional compensation is dependent upon a certain specified condition being complied with, that such condition was waived as a matter of course because no notice was taken thereof. Such a method of dealing with a contract would result in sanctioning the very looseness, and suggest and give countenance to the very class of controversies, such provisions are designed to prevent. There would be, then, little or no use of making a written contract at all, containing such guards, because if one were made the court, upon a controversy thereunder occurring, would look to what was in fact done and test the contract by that instead of testing what was done by the contract in determining the legal rights of the parties. There is, at times, rather too much of a tendency to do that,- the court acting as a mere arbitrator instead of judicially giving to each party his legal rights. Parties must be left to make their own contracts, and without any protection from improvident provisions embodied therein, in the absence of clear evidence of a modification or some relievable fraud or mistake. A contract once made can be subsequently varied by the parties thereto, and by parol, but a mere breach of contract, or failure to comply with the provisions therein upon which certain advantages are made to depend, should not be deemed a waiver of those parts of the agreement which would otherwise condemn the party guilty of the breach to damages, or condemn the party failing to perform such agreement to lose the advantages just as the contract provides. In the circumstances before us, a provision should not be deemed waived in the absence of clear and satisfactory evidence showing such to have been the intention of the parties, or showing an estoppel in pais. Certainly, the mere failure to do the very thing which the parties stipulated should work a forfeiture, is not sufficient. Otherwise the rule would be that, instead of a provision in a contract work[586]*586ing a forfeiture under the circumstances therein prescribed, the doing of the thing which was stipulated should work a forfeiture would always be held not to do so, but to waive the conditions of the contract in that regar d__/lf, under a. contract containing such a provision, a builder were requested to and did perform extra work of such magnitude that the idea that it was intended he should have no additional pay therefor would appear highly-unreasonable or absurd, a court-might, nothing appearing to the contrary, conclude that there was a mutual intention to waive such provision. But such is not the case here. The written contract on its face contemplated that additions and deductions from the contract work might occur from time to time during the progress of the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Welsbach Elec v. Mastec N. Am
859 N.E.2d 498 (New York Court of Appeals, 2006)
Welsbach Electric Corp. v. MasTec North America, Inc.
859 N.E.2d 498 (New York Court of Appeals, 2006)
Wassenaar v. Panos
331 N.W.2d 357 (Wisconsin Supreme Court, 1983)
Faust v. Ladysmith-Hawkins School Systems
277 N.W.2d 303 (Wisconsin Supreme Court, 1979)
Flour Mills of America, Inc. v. American Steel Building Co.
449 P.2d 861 (Supreme Court of Oklahoma, 1969)
Andrews Lumber Co. v. Cheske
107 N.W.2d 481 (Wisconsin Supreme Court, 1961)
Fullerton Lumber Co. v. Torborg
70 N.W.2d 585 (Wisconsin Supreme Court, 1955)
United States v. Cunningham
125 F.2d 28 (D.C. Circuit, 1941)
Nelson v. Cohen
84 P.2d 658 (Oregon Supreme Court, 1938)
Olson Construction Co. v. Commercial Building & Investment Co.
256 N.W. 22 (Nebraska Supreme Court, 1934)
Union Central Life Insurance v. Audet
21 P.2d 53 (Montana Supreme Court, 1933)
Eclipse Lumber Co. v. Bitler
241 N.W. 696 (Supreme Court of Iowa, 1932)
Roseliep v. Herro
239 N.W. 413 (Wisconsin Supreme Court, 1931)
Burgoyne v. Pyle
261 Ill. App. 356 (Appellate Court of Illinois, 1931)
Van Dyck Heating & Plumbing Co. v. Central Iowa Building Co.
205 N.W. 650 (Supreme Court of Iowa, 1925)
Carl Miller Lumber Co. v. Meyer
196 N.W. 840 (Wisconsin Supreme Court, 1924)
Southern Surety Co. v. Metropolitan Sewerage Commission
187 Wis. 206 (Wisconsin Supreme Court, 1923)
Kokomo, Frankfort & Western Traction Co. v. Kokomo Trust Co.
137 N.E. 763 (Indiana Supreme Court, 1923)
Leigland v. Rundle Land & Abstract Co.
208 P. 1075 (Montana Supreme Court, 1922)
Sheffield-King Milling Co. v. Jacobs
175 N.W. 796 (Wisconsin Supreme Court, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
99 N.W. 351, 121 Wis. 579, 1904 Wisc. LEXIS 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-la-crosse-hospital-assn-wis-1904.