Welsbach Elec v. Mastec N. Am

859 N.E.2d 498, 7 N.Y.3d 624, 825 N.Y.S.2d 692
CourtNew York Court of Appeals
DecidedNovember 20, 2006
StatusPublished
Cited by79 cases

This text of 859 N.E.2d 498 (Welsbach Elec v. Mastec N. Am) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Welsbach Elec v. Mastec N. Am, 859 N.E.2d 498, 7 N.Y.3d 624, 825 N.Y.S.2d 692 (N.Y. 2006).

Opinion

7 N.Y.3d 624 (2006)
859 N.E.2d 498
825 N.Y.S.2d 692

WELSBACH ELECTRIC CORP., Respondent,
v.
MASTEC NORTH AMERICA, INC., Appellant.

Court of Appeals of New York.

Argued October 17, 2006.
Decided November 20, 2006.

*625 Goldberg Segalla LLP, Albany (Thomas M. Moll of counsel), for appellant.

Murtagh, Cohen & Byrne, Rockville Centre (Edward T. Byrne and Paul J. Murdy of counsel), for respondent.

*626 Goetz Fitzpatrick, LLP, New York City (David E. Wolff, Denis B. Frind and David Kuehn of counsel), for American Subcontractors Association, Inc., amicus curiae.

Chief Judge KAYE and Judges CIPARICK, GRAFFEO, READ, SMITH and PIGOTT concur.

OPINION OF THE COURT

ROSENBLATT, J.

For well over a century, parties to construction contracts in New York were permitted by decisional law and by statute to *627 agree to "pay-if-paid" provisions. Agreements of that type create a condition precedent by which the subcontractor will not be paid unless the contractor has been paid. In 1995, however, we held in West-Fair Elec. Contrs. v Aetna Cas. & Sur. Co. (87 NY2d 148 [1995]) that such contracts violate New York's public policy as expressed in Lien Law § 34. That section provides in pertinent part: "Notwithstanding the provisions of any other law, any contract, agreement or understanding whereby the right to file or enforce any lien created under article two is waived, shall be void as against public policy and wholly unenforceable."

In the case before us, plaintiff subcontractor is a Delaware corporation and defendant general contractor is a Florida corporation. The parties agreed that Florida law would govern their contract. Unlike New York, Florida allows pay-if-paid contracts. We must determine whether New York's public policy against such contracts is so fundamental that it should override the parties' choice of law. We hold that it is not, and that the parties' choice of law controls. As we said in Cooney v Osgood Mach. (81 NY2d 66, 79 [1993]), "plainly not every difference between foreign and New York law threatens our public policy. Indeed, if New York statutes or court opinions were routinely read to express fundamental policy, choice of law principles would be meaningless."[1]

I

On September 10, 1999, Telergy Metro LLC engaged defendant MasTec North America, Inc. to construct a fiber optic telecommunications network from Pleasant Valley to New York City. On November 28, 2000, MasTec subcontracted with plaintiff Welsbach Electric Corp. to do the electrical work for the project. The subcontract included a pay-if-paid clause stating that:

"Upon final acceptance of the Work by Contractor and Owner, Contractor will pay Subcontractor for the Work at the prices and schedule and in the manner described in Schedule 1; provided that, all payments to Subcontractor by Contractor are expressly contingent upon and subject to receipt of payment for *628 the Work by Contractor from Owner. . . ." (Emphasis added.)

The parties also agreed that termination, suspension or delay of the primary contract between Telergy and MasTec automatically terminated, suspended or delayed the subcontract on both the same basis and effective date. In the event of termination, suspension or delay, Welsbach would be allowed to recover from the owner amounts payable to MasTec less any anticipated gross profit from the work.

In August 2001, Telergy became insolvent and terminated its contract with MasTec, effectively terminating the subcontract. MasTec, and in turn, Welsbach, were not fully paid for their work. Welsbach sued MasTec for the unpaid balance under the subcontract.

In its fifth and eleventh affirmative defenses MasTec asserted that: (1) Florida law, which enforces pay-if-paid provisions, governs the subcontract; MasTec never received payment from Telergy and therefore owes no money to Welsbach and (2) Welsbach can seek recovery only from Telergy, pursuant to the termination provision in the subcontract.

Welsbach moved for partial summary judgment and dismissal of those affirmative defenses, arguing that the subcontract's pay-if-paid provision violates Lien Law § 34. MasTec cross-moved for leave to serve an amended answer with two counterclaims. Supreme Court struck the two affirmative defenses, otherwise denied Welsbach's motion, and granted MasTec's cross motion. The court held that although pay-if-paid clauses are enforceable in Florida, they violate Lien Law § 34 because the subcontractor is forced to assume the risk that the owner will fail to pay the general contractor. On an appeal to the Appellate Division from so much of Supreme Court's order as struck the affirmative defenses, that Court, with one Justice dissenting, affirmed. We now reverse.

II

Both sides agree that the subcontract's pay-if-paid clause violates New York's public policy.[2] Were we not dealing with choice of law, we would simply apply Lien Law § 34 as interpreted *629 in West-Fair and the case would be closed. The issue before us, however, is whether our public policy is so unyielding that it trumps the parties' agreement to apply the law of another state. Put differently, there are two conflicting policies at work here: one, that parties should be free to chart their own contractual course, the other, that there are certain contracts the State will not allow.

Generally, courts will enforce a choice-of-law clause so long as the chosen law bears a reasonable relationship to the parties or the transaction (Cooney, 81 NY2d at 70-71). A basic precept of contract interpretation is that agreements should be construed to effectuate the parties' intent (see Greenfield v Philles Records, 98 NY2d 562, 569 [2002]; see R/S Assoc. v New York Job Dev. Auth., 98 NY2d 29, 32 [2002]; W.W.W. Assoc. v Giancontieri, 77 NY2d 157, 162 [1990]). Where an agreement is clear and unambiguous, a court is not free to alter it and impose its personal notions of fairness (see Vermont Teddy Bear Co. v 538 Madison Realty Co., 1 NY3d 470, 475 [2004]; Greenfield, 98 NY2d at 570; Reiss v Financial Performance Corp., 97 NY2d 195, 199 [2001]).

The freedom to contract, however, has limits. Courts will not, for example, enforce agreements that are illegal[3] or where the chosen law violates "some fundamental principle of justice, some prevalent conception of good morals, some deep-rooted tradition of the common weal" (Cooney, 81 NY2d at 78, quoting Loucks v Standard Oil Co. of N.Y., 224 NY 99, 111 [1918]; see generally Restatement [Second] of Conflict of Laws § 187 [2]). "If . . . the foreign law does not entail any such violation . . . full effect should be given to the law of our sister State" (Ehrlich-Bober & Co. v University of Houston, 49 NY2d 574, 584 [1980]). Crucially, however, we have reserved the public policy exception "for those foreign laws that are truly obnoxious" (Cooney, 81 NY2d at 79).

*630 This appeal requires us to examine the policy considerations underlying Lien Law § 34 to determine whether it embodies a concept so fundamental to our law as to meet this test. We have characterized concepts as "fundamental" in other contexts. For example, in Scheiber v St. John's Univ.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
859 N.E.2d 498, 7 N.Y.3d 624, 825 N.Y.S.2d 692, Counsel Stack Legal Research, https://law.counselstack.com/opinion/welsbach-elec-v-mastec-n-am-ny-2006.