Flour Mills of America, Inc. v. American Steel Building Co.

449 P.2d 861
CourtSupreme Court of Oklahoma
DecidedJanuary 27, 1969
Docket41154
StatusPublished
Cited by16 cases

This text of 449 P.2d 861 (Flour Mills of America, Inc. v. American Steel Building Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Flour Mills of America, Inc. v. American Steel Building Co., 449 P.2d 861 (Okla. 1969).

Opinion

LAVENDER, Justice.

This is an action for money judgment and for the establishment and foreclosure of a mechanics’ and materialmen’s lien.

The case arose out of three contracts. The first was a written contract dated April 14, 1961, between the plaintiff in error (hereinafter called “Flour Mills”), owner of the real property involved, and H. T. Petersen, a sole trader doing business as P & M Sales (hereinafter called “Petersen”), as prime contractor, for the construction on Flour Mills’ property in the City of Alva, Oklahoma, of a certain building as an addition to Flour Mills’ grain storage facilities on such property. The building was to be built according to plans and specifications included in the contract as a part thereof, for a basic contract price of $281,500.00. The second contract, admittedly entered into April 14, 1961, was between Petersen and the plaintiff in the trial court, American Steel Building Co., Inc. (hereinafter called “American”). Under this agreement American was to furnish all of the structural steel and do all of the structural steel work, and provide and install a corrugated steel roof on the building, required by the prime contract, for a basic price of $127,770.00. The third contract, entered into on or about June 1, 1961, between American and Belger Cartage Service, Inc. (hereinafter called “Bel-ger”), was one in which Belger agreed to provide, and did provide, certain heavy equipment and operators therefor for use by American in performing its subcontract with Petersen, at a total cost of $8,333.26.

At the time of the commencement of the action, American’s subcontract with Petersen, and Petersen’s prime contract with Flour Mills, had been fully performed, ex *865 cept that Flour Mills claimed that the roof of the building leaked when it rained, because of defects in materials or workmanship, or both, the curing of which defects would cost at least $40,000.00. Petersen claimed that he had been required to expend the sum of $5,340.74 for labor and materials in performing work which American had failed to perform in accordance with its subcontract with Petersen. Flour Mills had withheld from Petersen $40,000.-00 of the contract price, and refused to pay Petersen for certain “extra” items not covered by the prime contract, which Petersen claimed he had furnished as changes in the plans and specifications at the request of Flour Mills, although Flour Mills admitted that Petersen had furnished some of the extra items claimed by him, at its request. Petersen had not paid American the full amount it claimed to be due under its subcontract and for extra items furnished by it at Petersen’s request and had not paid the comparatively small claims of a number of other parties. American had not paid Belger the $8,333.26 due under their contract.

It was undisputed that timely and proper statements of claim of mechanics’ and ma-terialmen’s liens against the real property involved had been filed by all of the claimants except Petersen — at least, his pleadings do not claim any such lien. It was also shown that prior to the trial, Flour Mills had, by agreement with Petersen and his surety, satisfied all of the claims except those of Petersen, American, and Belger, and Petersen admits that Flour Mills is entitled to credit against him for the amounts so paid.

American, as plaintiff, commenced this action against Flour Mills and Petersen and all of the lien claimants, praying for . personal judgment against Flour Mills and Petersen in the amount of $64,388.53, with interest thereon at the rate of six per cent per annum from date of judgment until paid, with attorney’s fee and the costs of the action, and also asking for judgment against all of the defendants, establishing its claimed mechanics’ and materialmen’s lien as a first and prior lien against the real property involved and ordering the property sold to satisfy its judgment. American’s claim in the amount of $64,-388.53 is based upon the subcontract price of $127,770.00, with five separate adjustments for “extra” items not covered by the subcontract that would result in a net increase of $4,959.17, plus a performance bond premium, provided for in the subcontract, in the amount of $1,303.86, and $355.50 for additional materials required in performing the subcontract because of errors in the preliminary work of others, less credits for cash payments totaling $70,000.-00.

Belger filed its answer, with cross-petition for personal judgment against American in the amount of $8,333.32, and against Flour Mills and Petersen in the amount of $8,333.32, with interest thereon at the rate of six per cent per annum from August 1, 1961, until paid, and for the costs of the action, including a reasonable fee for its attorney, and for judgment against the plaintiff and all of the other defendants, establishing its claimed mechanics’ and ma-terialman’s lien and the priority thereof, and ordering the real property sold to satisfy its judgment. Petersen filed an answer denying that Belger was entitled to any judgment against him, and praying that Belger’s cross-petition be denied as against him. Flour Mills’ answer denied that it was indebted to Belger in any amount, but alleged that, if it was, it was entitled to judgment against Petersen in the same amount, with costs and attorney’s fee, and prayed for judgment accordingly.

In its pleadings, as amended, Flour Mills admits the execution of its prime contract with Petersen, the execution of the subcontract between Petersen and American, the existence of some kind of agreement between American and Belger concerning American’s use of Belger machinery and operators in performing the subcontract, and the substantial completion of the building and work covered by the prime contract and subcontract. As its basic defense to American’s action, and Petersen’s *866 cross action, against Flour Mills for amounts claimed to be due them under the prime contract and subcontract and for “extra” items actually furnished in accordance with provisions therefor in the prime contract, Flour Mills alleges that under provisions of the prime contract final payment did not become due, and would not become due, until the project engineer issued a certificate of completion, and the project engineer had never issued such a ■certificate because Petersen and American had failed to comply with the contract in that the roof was not weather-tight, but allowed rain to leak in, and Petersen and American failed and refused to do the things required by the project engineer to correct the defects. In a cross action against Petersen and American, Flour Mills alleges that it will be necessary for it to expend at least $40,000.00 to correct the defects in the roof to make it weather-tight as provided for in the prime contract and subcontract; that, as a result of the failure on the part of Petersen and American to provide a weather-tight roof as called for in the prime contract and subcontract, grain belonging to Flour Mills and stored in the building was spoiled, ruined and down-graded to its damage in the amount of $25,000.00; that Petersen and American failed to complete the various storage bins into which the building is divided by partitions within the times provided in the time schedule in the prime contract, and, under the provisions of the prime contract, Flour Mills is entitled to withhold an amount equal to $200.00 per day, as liquidated damages resulting from such delays, totaling $20,000.00, or, in the alternative, is entitled to damages for loss of anticipated profits in the amount of $96,000.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MERRELL LOGISTICS v. GREGORY GAS SERVICES
2021 OK CIV APP 47 (Court of Civil Appeals of Oklahoma, 2021)
Lester And Susan Riley v. David And Susan Valaer
Court of Appeals of Washington, 2020
Terry Matthews, Inc. v. C & L CONTRACTING, INC.
959 F. Supp. 1434 (W.D. Oklahoma, 1997)
Transpower Constructors v. Grand River Dam Authority
905 F.2d 1413 (Tenth Circuit, 1990)
First National Bank of Pauls Valley v. Crudup
656 P.2d 914 (Supreme Court of Oklahoma, 1982)
State Surety Co. v. Lamb Construction Co.
625 P.2d 184 (Wyoming Supreme Court, 1981)
Keith v. Burzynski
621 P.2d 247 (Wyoming Supreme Court, 1980)
Quin Blair Enterprises, Inc. v. Julien Construction Co.
597 P.2d 945 (Wyoming Supreme Court, 1979)
In re B.O.W.
40 Fla. Supp. 93 (Miami-Dade County Circuit Court, 1974)
Moore v. CONTINENTAL CASUALTY COMPANY
353 F. Supp. 105 (W.D. Oklahoma, 1973)
OK Johnson Electric, Inc. v. HESS-MARTIN CORPORATION
464 P.2d 206 (Supreme Court of Kansas, 1970)
ANTRIM LUMBER COMPANY v. Bowline
1969 OK 161 (Supreme Court of Oklahoma, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
449 P.2d 861, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flour-mills-of-america-inc-v-american-steel-building-co-okla-1969.