State Surety Co. v. Lamb Construction Co.

625 P.2d 184, 1981 Wyo. LEXIS 291
CourtWyoming Supreme Court
DecidedFebruary 11, 1981
Docket5330, 5331
StatusPublished
Cited by26 cases

This text of 625 P.2d 184 (State Surety Co. v. Lamb Construction Co.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Surety Co. v. Lamb Construction Co., 625 P.2d 184, 1981 Wyo. LEXIS 291 (Wyo. 1981).

Opinion

ROSE, Chief Justice.

This litigation was initiated by a subcontractor against the owners, the general contractor and the general contractor’s surety company in an effort to recover payment for work performed in the construction of a restaurant building near Torrington, Wyoming.

Lamb Construction Company, subcontractor-plaintiff, filed a complaint against Robert F. Bell and Dorothy J. Bell, husband and wife, d/b/a Big T Family Restaurant, owners; Pinetree Builders, Inc., a Nebraska corporation, general contractor; and State Surety Company, an Iowa corporation, surety company. 1 State Surety and Pinetree had jointly issued a Labor and Material Payment Bond and a Performance Bond.

The original action by Lamb sought to recover $14,892.55, plus interest and attorney fees, against all of the defendants, and asked that a materialman’s lien, which it had filed, be foreclosed.

■ The Bells filed a cross-claim against Pine-tree seeking damages for delay in completing construction of the project, recovery for the costs of replacing and completing defective and nonconforming work, recovery for work not completed under the terms of the contract and for recovery of all attorney fees and costs incurred in connection with defense of the suit. They also sought recovery against State Surety under the bonds issued by the surety company.

Pinetree, in turn, filed a cross-claim against the Bells asking recovery for amounts alleged due under the terms of the original contract and for extra work performed. The Bells admitted that money was owed Lamb for paving and surfacing the parking lot, but took the position that that was Pinetree’s obligation. All other claims were denied by the respective parties and the matter was submitted to trial.

Lamb was awarded judgment for $14,-892.55, together with interest and costs, against Pinetree and State Surety jointly, along with judgment in the sum of $4,500.00 for attorney fees against State Surety. Additionally, the court found Lamb’s lien on the Bells’ property to be valid and ordered it foreclosed.

Pinetree was awarded judgment against the Bells on its cross-claim in the amount of $1,531.32. According to the Amended Findings of Fact and Conclusions of Law, this figure was reached by determining that the Bells should recover $9,406.18 from Pinetree for payment of uncompleted work under the contract, and that Pinetree was entitled to recover $10,937.50 from the Bells for work performed and materials provided. The trial judge “netted” these figures and awarded Pinetree judgment against the Bells for $1,531.32. The trial court denied the Bells recovery for any attorney fees or costs. State Surety and the Bells have both perfected appeals.

The Bells identify the issues in their appeal as follows:

“1. Did the trial court err in refusing to award damages incurred by Appellants for breach of contract as a result of Pine-tree not completing the contract project within the time period specified in the contract?
“2. Did the trial court err in not awarding recovery in full to Appellants for landscaping and site work which Pine-tree failed to complete under the terms of the contract and which Appellants completed at their expense?
“3. Did the trial court err in denying recovery of attorney fees and costs to Appellants from Pinetree and State Surety as required by the Labor and Material Bond, Performance Bond and Section 29-2-115, Wyoming Statutes, 1977?”

*187 State Surety describes the issues on appeal with which it is concerned as follows:

“1. Do the provisions of W.S. 26-15-126 extend to Surety Companies, and did the trial Court error [sic] in determining that State Surety Company was subject to the provisions of that Statute?
“2. In view of certain disputes between the Owner, General Contractor, and the Subcontractor concerning amounts due and owing among each of the foregoing, was State Surety, justified in withholding payment on its bond, pending a resolution of such disputes, and did the trial Court err in its determination that State Surety acted unreasonably, and without good cause, under W.S. 26-15-126?”

PACTS

Pinetree, a general contractor, and the Bells, as owners, entered into an agreement, dated the 19th day of August, 1977, for the construction of a Tastee Freez building near Torrington, Wyoming.

On September 30, 1977, State Surety and Pinetree issued a Labor and Material Payment Bond and a Performance Bond, both of which named Pinetree as principal, the Bells as owners, and State Surety as surety.

The contract between the owners and the builder provided that construction was to commence immediately upon execution of the agreement, and substantial completion was to be achieved not later than 120 days thereafter. Construction was not commenced, however, until the latter part of September, 1977, and the building was not substantially completed until approximately March 14, 1978. One hundred and twenty days after execution would have been December 17, 1977.

The contract provided, as detailed in the plans and specifications, that Pinetree would complete all “site and landscape improvements.” In point of fact, Pinetree did not do the landscaping on the premises as required by the parties’ agreement. At a cost to the Bells of $3,368.75, landscaping, somewhat modified from that specified in the Bells-Pinetree contract, was completed by another company and the trial court granted the Bells recovery for a portion of this amount.

THE ISSUES CONSIDERED

We will first consider State Surety’s appeal in Case No. 5330, wherein Lamb is the appellee.

Case No. 5330

The first question for our resolution is framed by State Surety as follows:

Issue No. 1

“1. Do the provisions of W.S. 26-15-126 extend to Surety Companies, and did the trial Court error [sic] in determining that State Surety Company was subject to the provisions of that Statute?”

In its brief, State Surety contends that § 26-15-126(c), W.S.1977, 2 which provides *188 that an “insurance company” is obligated to pay any judgment or defend any suit where coverage exists, does not apply because a surety company is not an insurance company within the meaning of the statute. We cannot agree.

First, we are in disagreement with State Surety’s contention that this is a penal statute which requires narrow construction. The policy behind this statute is not to penalize insurance companies but to encourage claim statements and to chill any tendencies upon the part of insurance companies to unreasonably reject claims. See, e. g., Heis v. Allstate Insurance Company, 248 Or. 686, 436 P.2d 550, 553 (1968). It has been held that such statutes are compensatory, not penal in nature. Hagey v. Massachusetts Bonding & Ins. Co., 169 Or. 132, 127 P.2d 346, 347 (1942); Wolf v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cornhusker Casualty Company v. Skaj
786 F.3d 842 (Tenth Circuit, 2015)
Thorkildsen v. Belden
2011 WY 26 (Wyoming Supreme Court, 2011)
City of Gillette v. Hladky Const., Inc.
2008 WY 134 (Wyoming Supreme Court, 2008)
Stewart Title Guaranty Co. v. Tilden
2008 WY 46 (Wyoming Supreme Court, 2008)
Bb v. Rsr
2007 WY 4 (Wyoming Supreme Court, 2007)
Forshee v. Delaney
2005 WY 103 (Wyoming Supreme Court, 2005)
Ruby Drilling Co., Inc. v. Duncan Oil Co.
2002 WY 85 (Wyoming Supreme Court, 2002)
Simek v. Rocky Mountain, Inc.
977 P.2d 687 (Wyoming Supreme Court, 1999)
Pribble v. State Farm Mutual Automobile Insurance Co.
933 P.2d 1108 (Wyoming Supreme Court, 1997)
State Farm Mutual Automobile Insurance Co. v. Shrader
882 P.2d 813 (Wyoming Supreme Court, 1994)
Sannerud v. Brantz
879 P.2d 341 (Wyoming Supreme Court, 1994)
McCullough v. Golden Rule Insurance Co.
789 P.2d 855 (Wyoming Supreme Court, 1990)
UNC Teton Exploration Drilling, Inc. v. Peyton
774 P.2d 584 (Wyoming Supreme Court, 1989)
C. Bud Racicky Agency, Inc. v. Wood Gundy, Inc.
767 P.2d 601 (Wyoming Supreme Court, 1989)
Hashimoto v. Marathon Pipe Line Co.
767 P.2d 158 (Wyoming Supreme Court, 1989)
Albrecht v. Zwaanshoek Holding en Financiering, B.V.
762 P.2d 1174 (Wyoming Supreme Court, 1988)
Compass Insurance Co. v. Cravens, Dargan & Co.
748 P.2d 724 (Wyoming Supreme Court, 1988)
Grunewald & Adams Jewelers, Inc. v. Lloyds of London
700 P.2d 888 (Court of Appeals of Arizona, 1985)
Downing v. Stiles
635 P.2d 808 (Wyoming Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
625 P.2d 184, 1981 Wyo. LEXIS 291, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-surety-co-v-lamb-construction-co-wyo-1981.