Simek v. Rocky Mountain, Inc.

977 P.2d 687, 1999 Wyo. LEXIS 75, 1999 WL 320913
CourtWyoming Supreme Court
DecidedMay 24, 1999
Docket98-34
StatusPublished
Cited by6 cases

This text of 977 P.2d 687 (Simek v. Rocky Mountain, Inc.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simek v. Rocky Mountain, Inc., 977 P.2d 687, 1999 Wyo. LEXIS 75, 1999 WL 320913 (Wyo. 1999).

Opinion

TAYLOR, Justice, Retired.

At issue in this case is whether the terms of a building contract between appellant, Ronald L. Simek (Simek), and appellee, Rocky Mountain, Inc., d/b/a Chinook Log Homes (Chinook), required Simek to allow Chinook to perform remedial construction prior to bringing suit for breach of the warranty of good workmanship. The district court granted summary judgment in favor of Chinook, finding that Simek’s refusal to allow Chinook to correct alleged construction deficiencies, when it was ready and willing to do so, precluded further action against Chinook pursuant to the terms of the contract. We affirm.

I.ISSUES

Simek, as appellant, presents a single issue for review:

1. The District Court erred in granting summary judgment on Appellant’s first cause of action — breach of written contract.

Chinook, as appellee, raises three issues:

I. On appeal from summary judgment, may Appellant raise issues and theories not presented to the District Court?
II. Did Mr. Simek’s affidavit present any genuine issues of material fact?
III. May Mr. Simek pursue a claim for contract damages after deliberately refusing to carry out the contract remedies spelled out by ¶ 17 of the Construction Contract?

II. FACTS

In the winter of 1993, Simek contacted Chinook to construct a large home on property Simek owned southwest of Cody. Building commenced in the spring of 1994, and approximately one month later, Chinook and Simek executed a written contract for the construction. Simek paid as the construction proceeded. By the end of 1994, $733,580.19 had been paid, and in January 1995, Chinook billed Simek $75,301.13 for the work done in December.

Sometime in December 1994 or January 1995, Simek claims he became aware of alleged structural and non-struetural defects in the construction of the home. As a result, Chinook was told to leave the project during the first part of January. In the latter part of January, Simek informed Chinook that he had turned the matter over to his attorneys and would arrange for an inspection of the property. On February 1, 1995, Chinook met with Simek and their respective attorneys to discuss the outstanding bills. After some negotiation, Simek paid the January invoice for work done in December.

The parties and their attorneys met again on February 15, at which time Chinook gave Simek a Notice of Completion and a final statement of $31,546.14 submitted for the work done during the first part of January. The parties agreed that terms of the contract requiring an inspection within fifteen days of completion would be waived. Subsequently, Simek had the property inspected by Beau-dette Consulting Engineers, Inc., who submitted a preliminary report on March 19, 1995. Chinook responded in April, contesting some of the representations in the report, but agreeing to remedy several of the problems noted. Simek conducted another inspection on April 25, and on May 5, 1995, Simek’s attorney notified Chinook that its limited response to the alleged defects placed them in breach of the warranty provision of the contract as well as breaching the obligation to build the house in a good and workmanlike manner. Simek stated he intended to arrange for a comprehensive structural analysis, preparation of a plan of remediation, and the employment of a com *689 petent builder of log homes to complete the project.

By May 30, 1995, Simek’s engineer had agreed to a remedial program, and Chinook agreed to promptly do the work under the supervision of an engineer chosen by Simek at Chinook’s cost. In June, however, Si-mek’s attorneys notified Chinook that Simek refused to allow Chinook to do the repairs and that he had contracted with another builder to complete the home. Simek then filed a complaint in the district court in September 1995, alleging breach of written contract, breach of oral contract, and negligence.

Chinook denied any substantial construction defects and counterclaimed for the remaining invoice, alleging Simek failed to meet his duties under the contract. Chinook also maintained that Simek’s exclusive remedy, pursuant to the contract, was to allow Chinook to repair any identified defects. Chinook claims it was prepared to do so, and such repairs would not exceed $11,000.00 — a minuscule portion of the one million dollars estimated for the cost of the home.

Chinook then filed a motion for judgment on the pleadings as to Simek’s claim for breach of written contract, or in the alternative, for partial summary judgment. After a hearing on the motion, the district court granted partial summary judgment to Chinook, finding that the one-year warranty in the contract clearly required Simek to allow Chinook to perform the repairs prior to bringing suit. After the district court granted Simek’s motion for an order allowing the partial summary judgment to become a final order under W.R.C.P. 54, this timely appeal followed.

III. STANDARD OF REVIEW

Summary judgment is appropriate when there are no material issues of fact and the moving party is entitled to judgment as a matter of law. We review the record in the light most favorable to the non-moving party, using the same factual materials and the same standards as the district court. State ex rel. Bayou Liquors, Inc. v. City of Casper, 906 P.2d 1046, 1048 (Wyo.1995). Conclusory statements or mere opinions are insufficient, however, to satisfy an opposing party’s burden to present evidence of a material issue of fact. Sanchez v. Life Care Centers of America, Inc., 855 P.2d 1256, 1257 (Wyo.1993) (iquoting Boehm v. Cody Country Chamber of Commerce, 748 P.2d 704, 710 (Wyo.1987)). Moreover, we do not consider on appeal theories and points not raised in the district court, except for those issues which are jurisdictional or fundamental in nature. Bredthauer v. TSP, 864 P.2d 442, 446 (Wyo.1993) (quoting Oatts v. Jorgenson, 821 P.2d 108, 111 (Wyo.1991)).

IV. DISCUSSION

Chinook’s motion for partial summary judgment was based on paragraph 17 of the construction contract, which states:

17. WARRANTY. Contractor agrees to perform all work required of Contractor under this Contract in a good and workmanlike manner in accordance with the plans and specifications attached hereto. Said Warranty is in lieu of all other warranties, express or implied, including but not limited to warranties of fitness for particular purpose, merchantability and habitability. Contractor agrees for a period of one (1) year from the date of completion of the work to promptly correct, repair or replace, at Contractor’s expense, any defect in the construction resulting from Contractor’s defective workmanship.***

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoblyn v. Johnson
2002 WY 152 (Wyoming Supreme Court, 2002)
Gainsco Insurance Co. v. Amoco Production Co.
2002 WY 122 (Wyoming Supreme Court, 2002)
Estate of Corpening v. Corpening
2001 WY 18 (Wyoming Supreme Court, 2001)
Hovendick v. Ruby
10 P.3d 1119 (Wyoming Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
977 P.2d 687, 1999 Wyo. LEXIS 75, 1999 WL 320913, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simek-v-rocky-mountain-inc-wyo-1999.