This text of 597 P.2d 945 (Quin Blair Enterprises, Inc. v. Julien Construction Co.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quin Blair Enterprises, Inc. v. Julien Construction Co., 597 P.2d 945, 1979 Wyo. LEXIS 430 (Wyo. 1979).

Opinion

RAPER, Chief Justice.

The principal questions raised in this appeal concern appropriate damages for delay in completing a building contract, the effect of a contractual provision requiring the contractor to request in writing an extension of time to complete the contract, the effect on other contract remedies of an escrow agreement and a “punch-list” which required the contractor to redo work that was incorrectly or defectively done, and the ef-feet of a failure to timely serve notice of suit upon a surety-defendant whom plaintiff alleges is united in interest with the contractor-defendant.

The plaintiff is Quin Blair Enterprises, Inc. (Blair) and the defendants are Julien Construction Company (Julien) and American Insurance Company (American). 1 The district court entered a judgment in favor of Blair in the amount of $28,514.38 and costs of $1,104.20 as damages resulting from the failure of Julien to complete on time the construction of a Holiday Inn in Cody, Wyoming owned by Blair and because Julien constructed portions of that building in a negligent and defective manner. The district court’s judgment by reference incorporated findings of fact and conclusions of law announced by the trial judge in a memorandum opinion. Rule 52, W.R.C.P. 2

Blair asserts:

“1. The district court extended the time for completing the contract because the owner failed to clear the site. This ruling violates the contract which provides that a time extension could be granted for delay caused by the act or neglect of the owner only if a written claim for exten *948 sion was made by the contractor. No written, or even oral, claim for extension was ever made.
“2. Using the rental value theory adopted by the district court, the appellant was entitled to damages caused by the delay in completion in the amount of $92,240. “3. If [the Supreme Court] rejects the rental value approach used by the district court, the appellant contends that it presented evidence which allowed the court to determine loss of profits.” (Bracketed material substituted.)

Julien asserts:

“1. * * * Blair’s claim for damages for noncompletion within its contractual 240 day period of time should be barred by [Blair’s] own actions which contributed substantially to the delay.
“2. The damages found for negligent construction had been resolved by the ‘Escrow Agreement’ entered into by the parties on April 6, 1973 and the activities pursuant to that agreement and for failure to give written notice of defects as required by the contract.
“3. * * * [T]he damages found by the lower court for delayed completion were excessive in that the court did not include all expenses in determining lost profits and over compensated [Blair] for net profits from the Restaurant, Bar, and Related Activities.” (Bracketed material added.)

American asserts:

“1. The action brought by * * * Blair against * * * American * * should be dismissed as not having been brought timely under the provisions of the Performance Bond.”

We will affirm in part, reverse in part and remand with directions.

The factual background is for the most part not in dispute; the legal consequences of the facts are the source of differences. In the late summer of 1971, Julien submitted a bid pursuant to the invitation of Blair to construct a Holiday Inn complex in Cody for the sum of $848,732.00. This bid, along with others, was opened on September 9, 1971, and it was determined that Julien was the “low” bidder. Julien’s bid represented that he “proposes to complete the project within total period of 240 calendar days, which time is to commence upon date of signing of the contract.” Julien’s bid was effective for thirty days to expire on October 8, 1971. After it was determined that Julien was low bidder, there were a series of oral discussions between Blair and Julien which served to inform Julien that he was the “successful” bidder and which eventually resulted in Julien’s preparing a contract at the request of Blair. (American Institute of Architects [AIA] Document A101 — “Standard Form of Agreement Between Owner and Contractor.”) The contract, in its body, sets out that it was made on October 8, 1971, was signed by Blair on October 22, 1971, and by Julien on October 25, 1971.

Other facts will be considered in connection with our discussion of the issues raised: first, the time to complete the contract, the delay charged and damages in that connection; next, faulty construction; and finally, the performance bond.

With respect to time, Article 4 of the contract states:

“The Work to be performed under this Contract shall be commenced immediately and completed 240 days ” (emphasis indicates blanks in the contract form which were filled in by a typewriter).

The general conditions provide in part:

8.1.2 “The date of commencement of the Work is the date established in a notice to proceed. If there is no notice to proceed, it shall be the date of the Agreement or such other date as may be established therein.” (Emphasis added.)

Article 4 was followed by a parenthetical sentence: “(Here insert any special provisions for liquidated damages relating to failure to complete on time.)” No special provisions were inserted. Article 8, paragraph 8.2, made a listing of the contract documents which constituted the entire agreement between the parties. One of the documents there listed was, “Contractor’s Proposal, Pages A4a-01 & A4A-02 dated *949 Sept. 9, 1971 Submitted by the Julien Construction Company and signed by H. W. Julien, Pres.” This document is the one referred to above as Julien’s Bid which contained the language that Julien was to complete the building project within 240 days commencing upon date of signing the contract. 3

There was much testimony in the record about the clearing of the site on which the Holiday Inn was to be constructed. The site was occupied by a number of small log cabins which were a part of the original “Buffalo Bill Village” complex. Blair undertook to remove these cabins so as to preserve them for reuse within the Village. Julien asserts that as a result of Blair undertaking to clear the site, he was delayed in beginning his construction work for a substantial period of time. Another contractual document, AIA Document A201— “General Conditions of the Contract for Construction,” was made a part of the Contract by Article 1. Article 8 of AIA Document A201 deals with “Time.” The pertinent paragraphs read:

“8.3 DELAYS AND EXTENSIONS OF TIME

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Big-D Signature Corp. v. Sterrett Properties, LLC
2012 WY 138 (Wyoming Supreme Court, 2012)
KM Upstream, LLC v. Elkhorn Construction, Inc.
2012 WY 79 (Wyoming Supreme Court, 2012)
Davison v. Wyoming Game & Fish Commission
2010 WY 121 (Wyoming Supreme Court, 2010)
Davison v. WYOMING GAME AND FISH COM'N
2010 WY 121 (Wyoming Supreme Court, 2010)
City of Gillette v. Hladky Const., Inc.
2008 WY 134 (Wyoming Supreme Court, 2008)
Pbs Enterprizes, Inc. v. Cwcapital Asset Management LLC
2008 WY 53 (Wyoming Supreme Court, 2008)
Belden v. Thorkildsen
2007 WY 68 (Wyoming Supreme Court, 2007)
Cotton v. McCulloh
2005 WY 159 (Wyoming Supreme Court, 2005)
State v. Jones
788 A.2d 303 (New Jersey Superior Court App Division, 2002)
Brashear v. Richardson Constr., Inc.
10 P.3d 1115 (Wyoming Supreme Court, 2000)
Schuler v. Community First National Bank
999 P.2d 1303 (Wyoming Supreme Court, 2000)
Bouwkamp v. McNeill
902 P.2d 725 (Wyoming Supreme Court, 1995)
Leavell v. Linn
884 P.2d 1364 (Wyoming Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
597 P.2d 945, 1979 Wyo. LEXIS 430, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quin-blair-enterprises-inc-v-julien-construction-co-wyo-1979.