Fitzgerald v. Danaher

CourtVermont Superior Court
DecidedJuly 25, 2005
DocketS0225
StatusPublished

This text of Fitzgerald v. Danaher (Fitzgerald v. Danaher) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fitzgerald v. Danaher, (Vt. Ct. App. 2005).

Opinion

Fitzgerald v. Danaher, No. S0225-04 CnC (Katz, J., July 25, 2005)

[The text of this Vermont trial court opinion is unofficial. It has been reformatted from the original. The accuracy of the text and the accompanying data included in the Vermont trial court opinion database is not guaranteed.]

STATE OF VERMONT SUPERIOR COURT Chittenden County, ss.: Docket No. S0225-04 CnC

FITZGERALD

v.

DANAHER and XL BUILDING

FINDINGS OF FACT CONCLUSIONS OF LAW

On the basis of evidence presented at trial July 19–20, 2005, the following decision is announced.

1. Defendants at all times conducted their business under X-L Building & Design, Inc. There is no reason to impose personal liability upon either Mr. or Mrs. Danaher.

1 2. The largest single dispute in this home and barn-building dispute is whether defendant builder contracted to supply a slab for the barn project, as part of the house contract. The parties envisioned construction of a barn at the time they entered into the house contract. They provided for a barn frost wall as part of the house contract with the words: “and frost wall for barn with an unexcavated center, and preparation for slab on grade.” The contract also speaks of “barn to be a 4' frost wall only.” These parties made a written contract. It is the court’s obligation to apply that contract, not to rewrite it. Morrisseau v. Fayette, 164 Vt. 358, 366–67 (1995); H.P. Hood & Sons v. Heins, 124 Vt. 331, 336 (1964). In so doing, it is our foremost obligation to understand the agreement of the parties, to discern their intent. New Eng. P’ship, Inc. v. Rutland City Sch. Dist., 173 Vt. 69, 79 (2001). Any rule of contract interpretation is merely subservient to the purpose of discerning that intent. 11 S. Williston & R. Lord, A Treatise on the Law of Contracts § 30.2, at 22–25 (4th ed. 1999). Here, we think the plain language of the contract is controlling. Isbrandtsen v. North Branch Corp., 150 Vt. 575, 579–80 (1988). It clearly provides for “preparation” for slab, and for “frost wall only.” To somehow interpret this language to mean “supply slab” would be to wholly twist it beyond its clear meaning. The fact that specification 4 speaks of “slabs” in the plural does not change this result. It is best understood as referring to any slab which might be provided shall meet the then-stated specifications. The parties’ intention, as revealed by their signed agreement, must be discerned from their agreement as a whole, not from one sentence read in isolation. John A Russell Corp. v. Bohlig, 170 Vt. 12, 17 (2002). Viewing the pertinent provisions, we find: C frost wall for barn with an unexcavated center and preparation for slab on grade; C barn to be 4' frost wall only;

2 C all slabs to be 4" thick; C barn construction to be determined by separate contract. Fairly read, three of the provisions point to the conclusion that the barn was to be built under a separate contract, but the “frost wall only” is included in this contract, plus preparation for slab. The fourth provision, indicating specifications for a slab is pertinent to both house and barn, but does not by itself indicate a duty to pour a slab for the barn. The only support for plaintiff’s position is a single s making slab into a plural, and thereby implying a duty to provide more than one slab. Read as a whole, we conclude that an interpretation which assigns more weight to that lone s than to “frost wall only” and “preparation for slab” and “separate contract” would be wholly unreasonable. See Colgan v. Agway, 150 Vt. 373, 375 (1988) (“Clarity of language, like ambiguity, is a relative and not an absolute concept.”). The provisions just discussed are from the August 23, 2002 house contract executed by the parties. On October 9 of that year, they executed a barn contract. It contains the same slab specifications, again in the plural, as the house contract. Hence, the parties’ later expression manifested an intent that they were, then, contracting for a slab. Parenthetically, the footing and slab provisions are identical in both contracts, even to their typographical errors. At least in terms of understanding the intent of X-L, it shows that this was a standard specification. It does not support a shared understanding of more than one slab. Each contract uses the plural, but each contract clearly intended only one slab to be installed. The later contract shows the ongoing, shared intent of the parties to the earlier. Isbrandtsen, 150 Vt. at 578–79; see also 9A V.S.A. § 2–208 (course of performance and usage of trade); Rutland & B.R. Co. v. Crocker, 29 Vt. 540, 542–43 (C.C.D.Vt. 1857) (two instruments between substantially the same parties made at the same time and constituting the same transaction may explain each other).

3 3. The box sill issue centers on plaintiff’s claim that this perimeter house component was left uninsulated. It will be quite a project to rip out the cellar sheetrock; install insulation; and replace, retape and repaint new sheetrock. Based on all the evidence, we are not persuaded that insulation was probably omitted from the finished portion of the basement. It was omitted at least in portions of the mechanical room, but we are not persuaded that it was omitted in the balance. This is a fact that the witnesses’ testimony put in dispute.

4. Plaintiff had a circulating hot water pipe freeze during very cold weather. We are persuaded that this resulted from not using the heating system and relying instead on a wood stove in the basement to heat the house. As to whether the hot water system was inadequately insulated, this is a close question. But we are persuaded that good workmanship would provide that joists extending out into a cantilevered porch should probably have been caulked and insulated. It may be that such insulating would prevent intrusion of cold air into the wall and cellar areas adjacent to the problem heating pipes. The reasonable costs of caulking the point where the deck joists pass through the exterior wall to thereby better protect these heating pipes in that limited area is $435. In addition, it appears reasonable to require cutting through a small section of upstairs drywall; insulating the pipe length; and then repairing, retaping, and repainting that small section. Although parties did not offer an estimate of this particular task, through either Meunier or Danaher, based on other evidence presented we find that $225 would have been the reasonable cost to defendant to cure that problem, which was its responsibility. The cutting, insulating, retaping, and repainting, although in a small area, are at the same time similar to tasks being done in other locations for corrections such as nail pops and cracks.

4 5. Plaintiff has raised an issue about the timeliness of the barn’s construction. It is not clear where this issue takes us, as even if a breach of the time issue is shown, no damages were proved from delayed construction. Carter v. Sherburne Corp., 132 Vt. 88, 92–93 (1974) (“Ordinarily, in contracts where time is not of the essence, a failure to complete the work within the specified time will not terminate the contract, but it will subject the contractor to damages for the delay.”). We understand that plaintiff’s animals lost the protection of a barn for a whole winter, but no evidence was presented that she suffered recoverable damages as a result. See, e.g., Sutton v. Hisaw & Assoc. Gen. Contractors, Inc., 65 S.W.3d 281, 285 (Tex. App. 2001) (breach of contract requires proof of damages). The barn contract provides “Completion time will be approximately 6-10 weeks from commencement.” Commencement is not defined, but its reasonable meaning would be commencement of construction of the barn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quin Blair Enterprises, Inc. v. Julien Construction Co.
597 P.2d 945 (Wyoming Supreme Court, 1979)
Sutton v. Hisaw & Associates General Contractors, Inc.
65 S.W.3d 281 (Court of Appeals of Texas, 2002)
Morrisseau v. Fayette
670 A.2d 820 (Supreme Court of Vermont, 1995)
New England Partnership, Inc. v. Rutland City School District
786 A.2d 408 (Supreme Court of Vermont, 2001)
Highgate Associates, Ltd. v. Merryfield
597 A.2d 1280 (Supreme Court of Vermont, 1991)
Carter v. Sherburne Corporation
315 A.2d 870 (Supreme Court of Vermont, 1974)
Isbrandtsen v. North Branch Corp.
556 A.2d 81 (Supreme Court of Vermont, 1988)
Colgan v. Agway, Inc.
553 A.2d 143 (Supreme Court of Vermont, 1988)
John A. Russell Corp. v. Bohlig
739 A.2d 1212 (Supreme Court of Vermont, 1999)
Sid Grinker Co. v. Craighead
146 N.W.2d 478 (Wisconsin Supreme Court, 1966)
Nelson v. Marchand
691 N.E.2d 1264 (Indiana Court of Appeals, 1998)
Tour Costa Rica v. Country Walkers, Inc.
758 A.2d 795 (Supreme Court of Vermont, 2000)
H. P. Hood & Sons v. Heins
205 A.2d 561 (Supreme Court of Vermont, 1964)
Rutland & Burlington Railroad v. Crocker
29 Vt. 540 (U.S. Circuit Court, 1857)

Cite This Page — Counsel Stack

Bluebook (online)
Fitzgerald v. Danaher, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fitzgerald-v-danaher-vtsuperct-2005.