Highgate Associates, Ltd. v. Merryfield

597 A.2d 1280, 157 Vt. 313, 1991 Vt. LEXIS 179
CourtSupreme Court of Vermont
DecidedAugust 23, 1991
Docket90-032
StatusPublished
Cited by61 cases

This text of 597 A.2d 1280 (Highgate Associates, Ltd. v. Merryfield) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Highgate Associates, Ltd. v. Merryfield, 597 A.2d 1280, 157 Vt. 313, 1991 Vt. LEXIS 179 (Vt. 1991).

Opinion

*315 Dooley, J.

Plaintiff, Highgate Associates, Ltd., the owner of a federally subsidized housing project in Barre, appeals the trial court’s ruling that the late charge provision contained in its lease agreements is void as an unenforceable penalty. We affirm.

Defendant, Lorna Merryfield, occupied an apartment in the project beginning in January of 1986. The lease contained the following provision:

If the Tenant does not pay the full amount of the rent by the end of the 5th day of the month, the Owner may collect a fee of $5.00 on the 6th day of the month, the Owner may collect a fee of $1.00 for each additional day the rent remains unpaid during the month it is due. The owner may not terminate this Agreement for failure to pay rent charges, but may terminate this Agreement for non-payment of rent.... The charges herein discussed are liquidated damages, are not to be considered charges for the use or forbearance of money, are in addition to the regular monthly rent payable and are being incurred to cover administration costs caused by late rent payments.

Defendant was not a model tenant; her rent payments were late on numerous occasions, and by the time she had vacated her apartment in July of 1988, she had accrued late charges of $397. Plaintiff brought this action to recover unpaid rent, damages to the apartment, and the late charges. After an expedited hearing, the trial court awarded judgment to plaintiff on the unpaid rent and on part of the claimed damages. The court denied recovery on the late charges. On appeal, the sole issue is whether the trial court erred in concluding that the late payment provision was void as an illegal penalty.

We begin by emphasizing our limited standard of review in this matter. The trial court’s findings of fact must stand unless they are clearly erroneous, viewing the supporting evidence in a light most favorable to the prevailing party and excluding the effect of modifying evidence. Lawrence v. Pelletier, 154 Vt. 29, 33, 572 A.2d 936, 939 (1990). A finding will not be disturbed merely because it is contradicted by substantial evidence; rather, an appellant must show there is no credible evidence to support the finding. See Gokey v. Bessette, 154 Vt. 560, 564, 580 A.2d 488, 491 (1990). Where the trial court has *316 applied the proper legal standard, we will uphold its conclusions of law if reasonably supported by its findings. Goodrich v. United States Fidelity & Guaranty Co., 152 Vt. 590, 596, 568 A.2d 385, 389 (1989).

The ultimate test for the validity of a liquidated damages clause is whether the clause is reasonable under the totality of the circumstances. See Wassenaar v. Panos, 111 Wis. 2d 518, 525, 331 N.W.2d 357, 361 (1983). We recently articulated three factors that should be considered in determining whether’ a contract provision is a reasonable liquidated damages clause rather than an unlawful penalty:

[A] liquidated damages clause must meet three criteria to be upheld: (1) because of the nature or subject matter of the agreement, damages arising from a breach would be difficult to calculate accurately; (2) the sum fixed as liquidated damages must reflect a reasonable estimate of likely damages; and (3) the provision must be intended solely to compensate the nonbreaching party and not as a penalty for breach or as an incentive to perform.

New England Educational Training Service, Inc. v. Silver Street Partnership, 156 Vt. 604, 613, 595 A.2d 1341, 1346 (1991). These factors are not exclusive or necessarily conclusive. They do, however, provide a framework for the trial court’s determination of whether a particular clause is reasonable. Koenings v. Joseph Schlitz Brewing Co., 126 Wis. 2d 349, 361, 377 N.W.2d 593, 600 (1985).

While final determination of whether a liquidated damages provision is reasonable is a legal question for the trial court, evaluation of the three factors underlying that determination requires resolution of factual issues. See, e.g., New York Life Ins. Co. v. Hartford Nat. Bank & Trust Co., 2 Conn. App. 279, 281, 477 A.2d 1033, 1035 (1984) (“The trial court found that all three conditions were met on the basis of the facts of this case. The facts found were not clearly erroneous.”); Liberty Life Ins. Co. v. Thomas B. Hartley Constr. Co., 258 Ga. 808, 809, 375 S.E.2d 222, 223 (1989) (while enforceability of liquidated damages provision is a question of law, trial court must make “tripartite inquiry” which “requires the resolution of questions of fact”); Illingworth v. Bushong, 297 Or. 675, 694, 688 P.2d 379, 390 (1984) (upholding ruling that clause was void as penalty *317 where “there was evidence ... to support the findings of the trial judge on both criteria discussed above”). Accordingly, we give some deference to the trial court’s final determination. Wassenaar, 111 Wis. 2d at 525, 331 N.W.2d at 361 (“because the trial court’s legal conclusion, that is, whether the clause is reasonable, is so intertwined with the factual findings supporting that conclusion, the appellate court should give weight to the trial court’s decision”).

Applying these principles to the present case, we conclude that the trial court’s findings on the three criteria were not clearly erroneous, and that its conclusion that the lease provision was an unenforceable penalty was supported by these findings.

The first factor concerns the difficulty of calculating or proving the damages that might follow from a breach. See Borley v. McDonald, 69 Vt. 309, 313, 38 A. 60, 61 (1897) (upholding clause where damages arising from breach are “entirely uncertain, and cannot be ascertained upon an issue of fact”). The record ■ contains extensive evidence bearing on this factor. It shows that plaintiff’s employees had considerable experience in handling late rent payments. Plaintiff’s office manager and managing agent testified that they followed an established routine when a rent payment was more than five days late. Based on this evidence, the court found that the total cost to plaintiff in responding to a late-paying tenant, including both labor and administrative costs, is approximately ten dollars per month and does not depend on the amount of rent outstanding. Although plaintiff’s managing agent testified that “costs are greatly increased if the rents are not in on a timely fashion,” there was no evidence that plaintiff’s expenses had ever exceeded ten dollars per month.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thorp v. Moonstone
Vermont Superior Court, 2025
Bourne's Inc. D/B/A v. Emmanuel Lemelson
Supreme Court of Vermont, 2025
Ac Wright v. Wind River
Vermont Superior Court, 2025
Byrneport Apts. II v. Williams
2020 Ohio 3488 (Ohio Court of Appeals, 2020)
Bourdeau Bros., Inc. v. Boissonneault Family Farm, Inc.
2020 VT 35 (Supreme Court of Vermont, 2020)
State v. Gilles Richard
2016 VT 75 (Supreme Court of Vermont, 2016)
Kirkland v. Kolodziej
199 Vt. 606 (Supreme Court of Vermont, 2016)
Janice Leaman v. Gregg Wolfe
629 F. App'x 280 (Third Circuit, 2015)
Obolensky v. Trombley
2015 VT 34 (Supreme Court of Vermont, 2015)
Barbour v. Wright
Vermont Superior Court, 2012
In re Appeal of J.P.
Supreme Court of Vermont, 2012
Glassford v. BrickKicker and GDM Home Services, Inc.
2011 VT 118 (Supreme Court of Vermont, 2011)
DeSantis v. Pegues
2011 VT 114 (Supreme Court of Vermont, 2011)
In Re Market Center East Retail Property, Inc.
433 B.R. 335 (D. New Mexico, 2010)
CASSANI v. Hale
2010 VT 8 (Supreme Court of Vermont, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
597 A.2d 1280, 157 Vt. 313, 1991 Vt. LEXIS 179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/highgate-associates-ltd-v-merryfield-vt-1991.