MILTON CONST. CO. v. State Highway Dept.

568 So. 2d 784, 1990 Ala. LEXIS 667, 1990 WL 155158
CourtSupreme Court of Alabama
DecidedSeptember 14, 1990
Docket89-514
StatusPublished
Cited by40 cases

This text of 568 So. 2d 784 (MILTON CONST. CO. v. State Highway Dept.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MILTON CONST. CO. v. State Highway Dept., 568 So. 2d 784, 1990 Ala. LEXIS 667, 1990 WL 155158 (Ala. 1990).

Opinion

This is an appeal from a summary judgment in favor of the defendants, the State of Alabama, State of Alabama Highway Department, and Royce King, as director of the State of Alabama Highway Department (hereinafter collectively referred to as "Highway Department"). The plaintiff, Milton Construction Company ("Milton"), had sought a judgment declaring that the disincentive clause of an incentive/disincentive payments provision in each of two highway construction contracts that it had entered into with the Highway Department was void and unenforceable as a penalty and requested that the trial court order the Highway Department to pay Milton the amounts of disincentive payments that it withheld.

The issues before us are whether a clause of a construction contract that authorizes the withholding of disincentive payments is void and unenforceable as a penalty; whether Milton is estopped from asserting a claim that the disincentive clause is void where it has previously received incentive compensation pursuant to the incentive clause of the incentive/disincentive payments provision in a prior contract; and whether the trial court erred in failing to strike an affidavit allegedly based on hearsay.

Summary judgment is proper where there is no genuine issue of material fact and the moving party is entitled to a judgment as a matter of law. Rule 56, A.R.Civ.P. All inferences must be viewed in the light most favorable to the nonmoving party, and all reasonable doubts concerning the existence of a genuine issue of material fact must be resolved against the moving party. See Wilson v. Brown, 496 So.2d 756 (Ala. 1986); see, also, McMillian v. Wallis, 567 So.2d 1199 (Ala. 1990). This case was filed after June 11, 1987; therefore, the applicable standard of review is the "substantial evidence" rule. Ala. Code 1975, § 12-21-12; see, also, Watters v. Lawrence County,551 So.2d 1011 (Ala. 1989); see, also, Koch v. State Farm Fire Casualty Co., 565 So.2d 226 (Ala. 1990).

The facts of this case are substantially undisputed. The Highway Department and Milton entered into contracts for widening and repairing a portion of Interstate Highway 65 (hereinafter referred to as the "I-65 *Page 786 Project")1 in Jefferson County and for concrete pavement rehabilitation of, and the addition of median lanes to, a portion of Interstate Highway 59 (hereinafter referred to as the "I-59 Project")2 in Jefferson County.

The total cost of the I-65 Project was $7,745,320.29, and the total cost of the I-59 Project was $4,399,883.25. Subsequent to the filing of this lawsuit, the parties stipulated to all amounts due and payable to Milton (which have now been paid) except for the disputed amounts of $300,000 and $240,000 that the Highway Department deducted from Milton's contract price for the I-65 and I-59 Projects, respectively, pursuant to an incentive/disincentive payments provision. (The incentive clause of the incentive/disincentive payments provision is not at issue.)

The incentive/disincentive payments provision3 of each contract reads, in pertinent part, as follows:

"The Contractor's attention is directed to the fact that it is in the public's interest to complete this project at the earliest possible date taking into account the traffic control plan and sequence of construction specified in the plans. The completion of the entire project and final acceptance by the Department must be accomplished within 330 Calendar Days [in the I-65 Project; 210 Calendar Days in the I-59 Project].

". . . .

"1. If and when the Engineer determines that the Contractor will exceed the contract time allowed, as previously specified, the Engineer will suspend further payments otherwise due the Contractor until the amount of the suspended payments equal[s] the maximum decrease described below:

"For each day of overrun, up to 60 Calendar days, total payment due to the Contractor will be decreased by $5,000.00 [in the I-65 Project, and $4,000.00 in the I-59 Project] per calendar day. This disincentive payment will be in addition to the liquidated damages specified in Article 108.11.

"3. There will be no further incentive or disincentive adjustment for underruns or overruns exceeding 60 days. The maximum amount to apply to incentive or disincentive will be $300,000.00 [in the I-65 Project and $240,000.00 in the I-59 Project]. Liquidated damages as specified in Article 108.11 will apply until completion and acceptance of the entire project."

(Emphasis added.)

In addition, each contract contained a provision for recovery of actual damages, found in Article 108.12 ("Default of Contract"). It provides, in pertinent part, as follows:

"If the Contractor:

"9. For any other cause whatsoever, fails to carry on the work in an acceptable manner, the Engineer will give notice in writing to the Contractor and his surety of such delay, neglect and default.

". . . The Department may appropriate or use any or all materials and equipment on the ground as may be suitable and acceptable and may enter into an agreement for the completion of said contract according to the terms and provisions thereof, or use such other methods as in the opinion of the Engineer will be required for the completion of said contract in an acceptable manner.

"All costs and charges incurred by the Department together with the cost of completing the work under contract, *Page 787 will be deducted from any monies due or which may become due said Contractor. If such expense exceeds the sum which would have been payable under the contract, then the Contractor and the Surety shall be liable and shall pay to the Department the amount of such excess."

Furthermore, each contract contained a clause for liquidated damages.4 Article 108.11 ("Failure to Complete Work Within Contract Time") reads, in pertinent part, as follows:

"Should the Contractor, or in case of default, the surety, fail to complete the work within the time stipulated in the contract or the adjusted time as granted under the provisions of Article 108.09, a deduction for each calendar day or work day that any work shall remain uncompleted, [in] an amount indicated by the Liquidated Damages Schedule shown in Article 108.11 or provided in the contract document shall be deducted from any monies due the Contractor on monthly estimates. . . .

"Liquidated damages assessed as provided in these Specifications is not a penalty, but is intended to compensate the State for increased time in administering the contract, supervision, inspection and engineering, particularly the engineering and inspection which requires maintaining normal field project engineering forces for a longer time on any construction operation or phase [than] originally contemplated when the contract period was agreed

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Autauga Quality Cotton Association v. Tim L. Crosby
893 F.3d 1276 (Eleventh Circuit, 2018)
Safeway Ins. Co. of Ala., Inc. v. Thomas
264 So. 3d 98 (Court of Civil Appeals of Alabama, 2018)
Woodfin v. Bender
238 So. 3d 24 (Supreme Court of Alabama, 2017)
Grimes v. Alfa Mutual Insurance Co.
227 So. 3d 475 (Supreme Court of Alabama, 2017)
In re Atchison
557 B.R. 818 (M.D. Alabama, 2016)
Thyssenkrupp Steel USA, LLC v. United Forming, Inc.
926 F. Supp. 2d 1286 (S.D. Alabama, 2013)
Perdue ex rel. Perdue v. Green
127 So. 3d 343 (Supreme Court of Alabama, 2012)
Faulk v. Rhodes
62 So. 3d 517 (Court of Civil Appeals of Alabama, 2010)
Poole v. Prince
61 So. 3d 258 (Supreme Court of Alabama, 2010)
Southern Electric Corp. v. Utilities Board of Foley
643 F. Supp. 2d 1302 (S.D. Alabama, 2009)
Alabama Dept. of Transp. v. Harbert Intern., Inc.
990 So. 2d 831 (Supreme Court of Alabama, 2008)
S & M Equipment Co. v. Alabama Department of Transportation
978 So. 2d 718 (Supreme Court of Alabama, 2007)
Ex Parte Alabama Dept. of Transp.
978 So. 2d 718 (Supreme Court of Alabama, 2007)
Modha v. State
962 So. 2d 383 (District Court of Appeal of Florida, 2007)
Good Hope Contracting Co. v. Alabama Department of Transportation
978 So. 2d 17 (Supreme Court of Alabama, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
568 So. 2d 784, 1990 Ala. LEXIS 667, 1990 WL 155158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milton-const-co-v-state-highway-dept-ala-1990.