Carter v. Sherburne Corporation

315 A.2d 870, 132 Vt. 88, 1974 Vt. LEXIS 305
CourtSupreme Court of Vermont
DecidedFebruary 5, 1974
Docket89-72
StatusPublished
Cited by10 cases

This text of 315 A.2d 870 (Carter v. Sherburne Corporation) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carter v. Sherburne Corporation, 315 A.2d 870, 132 Vt. 88, 1974 Vt. LEXIS 305 (Vt. 1974).

Opinion

Shangraw, C.J.

This is an appeal by the defendant from a judgment of the Eutland County Court. The subject matter of the litigation is work done and materials furnished by the plaintiff in connection with a development of the defendant’s near Sherburne Mountain. The plaintiff claimed that he was not fully paid for labor and materials furnished under written contracts, and that he was entitled to further amounts on a quantum meruit basis for labor and materials furnished without express agreement as to price. The defendant claimed defective performance and payment for everything due, and asserted a counterclaim for expense necessitated by plaintiff’s alleged failure to fulfill contractual commitments. The court found that the plaintiff was in substantial compliance under his contracts, that the defendant had no right to terminate the contracts, and that the defendant’s counterclaim was without foundation. The court also found that the plaintiff performed other work for the defendant without compensation under a promise for additional work which was not fulfilled by the defendant. Plaintiff was awarded various sums for unpaid invoices, payment for other work done for the defendant, and interest. The defendant corporation has appealed.

The facts as found by the court are, in substance, as follows:

There were four written contracts between the parties covering (a) the furnishing and placing of gravel on one road, (b) the drilling and blasting of rock on various residential roads, (c) road construction, and (d) the cutting and grubbing of a gondola lift-line. The contracts called for weekly progress payments based upon work completed with a provision for retaining 10% until ten days after final acceptance. The billings from the plaintiff to the defendant *91 amounted to $52,571.25, of which $41,868.05 was paid by the defendant. The difference between the $52,571.25 billed, and $41,368.05 paid, comprised $4,596.45 retained by the defendant under its holdback provision, and adjustments claimed by the defendant of $6,606.75. The court found that adjustments in the amount of $4,747.25 were improperly taken by the defendant and that amount was decreed to the plaintiff. In addition the court found that the plaintiff was entitled to all the retainage held by the defendant.

As to the defendant’s contention that the plaintiff’s performance was unsatisfactory and, in particular, that the plaintiff failed to abide by the completion schedules in the contracts, the court found that on the whole, the plaintiff rendered substantial performance under the contracts without major complaints from the defendant up to the time it terminated the contracts. The court found further, that time was not of the essence of the contracts, that many of the delays were due to the directions of the defendant in constantly shifting the plaintiff’s activities from one contract to another, and that other delays were financial in origin, in that the plaintiff had difficulty meeting his outstanding obligations because of payments withheld by the defendant without justification.

The court also found that the defendant’s representatives promised the plaintiff extensive additional work contracts, that in return for this promise the plaintiff agreed to do certain work without compensation, that the plaintiff did in fact do some of this work, and that the additional work promised by the defendant was not awarded to the plaintiff. The court held that the plaintiff was justified in his reliance on defendant’s promise, and that he could recover his expenses and the value of his services from the defendant on a quantum meruit basis.

Defendant claims the court erred in its ruling that the plaintiff was in substantial compliance under his contracts and in its finding that the plaintiff was entitled to recover certain sums under the gondola lift-line contract. In addition, defendant claims that the court was in error in allowing the plaintiff recovery on a quantum meruit basis as parole evidence was improperly admitted, and the recovery granted was not in accordance with the terms of the contract.

*92 The defendant makes exhaustive challenges to the court’s findings of fact, urging that they are unsupported by substantial evidence. The standard by which such challenges are tested is stated in V.R.C.P. 52(a). This Court has held that the standard used under the previous statutory requirement, 12 V.S.A. § 2385, is essentially the same as that found in V.R.C.P. 52(a), and that therefore, Vermont case law applies to the present rule. Seaway Shopping Center Corpora tion v. Grand Union Stores, Inc., 132 Vt. 111, 315 A.2d 483 (1974). We have examined the record and find no basis for disturbing the facts as found by the county court. The findings are clearly and reasonably supported by the evidence, and must stand. Largess v. Tatem, 130 Vt. 271, 291 A.2d 398 (1972); Little v. Little, 124 Vt. 178, 200 A.2d 276 (1964); Seaway Shopping Center Corporation v. Grand Union Stores, Inc., supra.

The defendant’s primary contention is that the court’s ruling that the plaintiff was in substantial compliance under his contracts is error. The contention is that this ruling was based on the erroneous conclusion that time was not of the essence of the contracts, and that as time was of the essence and plaintiff failed to perform within the time specified, plaintiff was not in substantial compliance and defendant is entitled to the amounts withheld as retainage.

Where time is of the essence, performance on time is a constructive condition of the other party’s duty, usually the duty to pay for the performance rendered. Jones v. United States, 96 U.S. 24 (1877). Time may be made of the essence of a contract by a stipulation to that effect, Cheney v. Libby, 134 U.S. 68, 33 L.Ed. 810, 10 S.Ct. 498 (1890), or by any language that expressly provides that the contract will be void if performance is not within a specified time. Sowles v. Hall, 62 Vt. 247, 20 A. 810 (1890). Where the parties have not expressly declared their intention, the determination as to whether time is of the essence depends on the intention of the parties, the circumstances surrounding the transaction, and the subject matter of the contract. Kennedy v. Rutter, 110 Vt. 332, 6 A.2d 17 (1939).

As a general rule, time is not of the essence in a building or construction contract in the absence of an express *93 provision making it such. 13 Am.Jur.2d Building and Construction Contracts § 47.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pavelic v. Mack
Vermont Superior Court, 2025
Fitzgerald v. Danaher
Vermont Superior Court, 2005
Reid v. Seei
9 Am. Samoa 3d 50 (High Court of American Samoa, 2004)
McGee Construction Co. v. Neshobe Development, Inc.
594 A.2d 415 (Supreme Court of Vermont, 1991)
Colony Park Associates v. Gall
572 A.2d 891 (Supreme Court of Vermont, 1990)
Sullivan v. Lochearn, Inc.
464 A.2d 745 (Supreme Court of Vermont, 1983)
Higgins v. City of Fillmore
639 P.2d 192 (Utah Supreme Court, 1981)
Quin Blair Enterprises, Inc. v. Julien Construction Co.
597 P.2d 945 (Wyoming Supreme Court, 1979)
Dodge v. Washington Electric Cooperative, Inc.
359 A.2d 647 (Supreme Court of Vermont, 1976)
Sherburne Corporation v. Carter
340 A.2d 82 (Supreme Court of Vermont, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
315 A.2d 870, 132 Vt. 88, 1974 Vt. LEXIS 305, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carter-v-sherburne-corporation-vt-1974.