Higgins v. City of Fillmore

639 P.2d 192, 1981 Utah LEXIS 934
CourtUtah Supreme Court
DecidedDecember 28, 1981
Docket17018
StatusPublished
Cited by3 cases

This text of 639 P.2d 192 (Higgins v. City of Fillmore) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Higgins v. City of Fillmore, 639 P.2d 192, 1981 Utah LEXIS 934 (Utah 1981).

Opinion

STEWART, Justice:

Plaintiff, a general contractor, brought an action against the City of Fillmore for breach of a construction contract. The City filed a counterclaim alleging it was entitled to liquidated damages because the contract was not completed within the time specified in the contract. The court ruled against the City on all counts and awarded plaintiff $78,120.08. The City appeals, asserting insufficient evidence to support á finding of breach.

On September 7, 1971, Higgins and the City entered into a written construction contract for the installation of a sewer system for the City of Fillmore. Higgins was a licensed and experienced contractor, having previously constructed various sewage systems, water systems, and sewage and water treatment plants. Under the terms of the contract, Higgins was required to complete the work within 180 calendar days of receipt of notice to proceed. The contract provided for liquidated damages of $50 each day beyond the contract completion date, but excused delays resulting from specific orders of the engineer, failure of the owner to provide the right of way, owner’s neglect, or unforeseeable causes beyond the contractor’s control. On October 22,1971, Higgins received notice to proceed. Work commenced on October 28, 1971.

Progress on the project was impeded by construction of a freeway and access ramp above the proposed sewage line, the City’s failure to obtain the necessary right of ways, and the City’s determination to change twice the location of the lagoons after commencement of work at each previous location.

According to the City, the trial court “misapplied the evidence” and erred in finding Higgins completed the contract within a reasonable time. 1 The City claims this led to an erroneous ruling entitling Higgins to $17,600 in liquidated damages.

The evidence must be evaluated in the light most favorable to the prevailing party, Ute-Cal Land Development Corp. v. Sather, Utah, 605 P.2d 1240 (1980); Hardy v. Hendrickson, 27 Utah 2d 251, 495 P.2d 28 (1972). When the evidence is in conflict, as in the instant case, we presume the court relied on the evidence supporting its findings. Fillmore City v. Reeve, Utah, 571 P.2d 1316 (1977); Robertson v. Hutchinson, Utah, 560 P.2d 1110 (1977).

One who causes a delay is not entitled to recover for a resulting failure to meet completion dates, even under a liquidated damages provision. 2 United States v. United Engineering & Contracting Co., 234 U.S. 236, 34 S.Ct. 843, 58 L.Ed. 1294 (1914); Carter v. Sherburne Corp., 132 Vt. 88, 315 *194 A.2d 870 (1974), see also 13 Am.Jur.2d, Buildings and Construction Contracts, § 48.

Although the evidence is conflicting, the lower court’s finding that the June 1973 completion date was reasonable and justified is substantiated by evidence of the City’s delay in making the lagoon site available, failure to anticipate the effect of the new freeway on construction, and failure to obtain certain necessary permits in a timely fashion.

Defendant also asserts the contract was divisible and that delays on one portion did not affect work on the remainder. But since the matter was not raised in the trial court, it would be inappropriate for this Court to address the issue. Shayne v. Stanley & Sons, Inc., Utah, 605 P.2d 775 (1980); Park City Utah Corp. v. Ensign Co., Utah, 586 P.2d 446 (1978).

We conclude the lower court correctly found defendant not entitled to withhold liquidated damages.

The City’s second contention is that the trial court erred in awarding plaintiff $23,313.72 damages for increased labor expense between July 1, 1972, the effective date of the new union contract, and the end of June 1973, the completion date of the project. Absent the delays encountered, the sewer system would have been completed prior to the effective date of the new union contract. The City again reargues the facts stressing particular portions of the record and ignoring the testimony relied on by the lower court. The evidence supports the trial court’s finding that the City caused the delays which resulted in plaintiff’s obligation to pay higher wages. We find the court properly awarded damages for increased labor expense.

The City next argues that Kiggins is not entitled to damages for increased wages on projects paid on a lump sum basis since that basis was negotiated after the wage increase went into effect. The record shows, however, that the change to a lump sum basis was merely an accounting matter and not a contract renegotiation resulting from increased wage rates.

The City’s fourth contention is that the trial court erred in awarding Higgins damages for loss of efficient use of men and machines during the 1972-73 winter. The City asserts the award could only result from a judicial rewriting of the contract, since there was no contractual compensation for efficiency loss and no obligation to proceed with work during inclement periods. The City’s position is incorrect; the award is appropriate under the law of damages.

Damages may be recovered for loss of efficiency as a natural consequence of the breach of a construction contract. See Luria Brothers & Co. v. United States, 369 F.2d 701, 177 Ct.Cl. 676 (1966); Abbett Electric Corp. v. United States, 142 Ct.Cl. 609, 162 F.Supp. 772 (1958). The delays resulted from the City’s failure to furnish the proper right of ways, easements, and a proper location for the lagoon. The consequential delays forced the work into an unanticipated second winter, presenting unfavorable work conditions. We find the award for lost efficiency appropriate in this instance.

The fifth contention is error in an $11,556.99 damage award for the increased cost of gravel which was used instead of excavated material to backfill trenches crossing the state highway. Because of inadequate inspection by the City, the State assigned its own inspector to the project. He determined that the excavated material generally used throughout the project to backfill trenches was not suitable for the sewer lines in the trenches crossing the state highway. As a result, Higgins was obligated to acquire and use gravel to fill these trenches. Consequently, the amount of gravel backfill actually used was substantially greater than the amount anticipated in the contract. Although the use of gravel backfill under the State highway was initially unanticipated by both parties, the contract provision providing a per cubic yard price of $3.81 for gravel backfill under pipes can be read to apply to this use.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hutton Contracting Co. v. City of Coffeyville
487 F.3d 772 (Tenth Circuit, 2007)
Alpha Partners, Inc. v. Transamerica Investment Management, L.L.C.
2006 UT App 331 (Court of Appeals of Utah, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
639 P.2d 192, 1981 Utah LEXIS 934, Counsel Stack Legal Research, https://law.counselstack.com/opinion/higgins-v-city-of-fillmore-utah-1981.