Wilson v. Salt Lake City

174 P. 847, 52 Utah 506, 1918 Utah LEXIS 86
CourtUtah Supreme Court
DecidedJuly 13, 1918
DocketNo. 3135
StatusPublished
Cited by13 cases

This text of 174 P. 847 (Wilson v. Salt Lake City) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilson v. Salt Lake City, 174 P. 847, 52 Utah 506, 1918 Utah LEXIS 86 (Utah 1918).

Opinions

CORFMAN, J.

The plaintiff commenced an action to recover from the defendant certain amounts alleged to be due and owing him for extra labor and materials furnished in the construction and completion of a reservoir for the defendant. The reservoir was designed for the purpose of supplying the inhabitants of Salt Lake City with water.

A written contract had been entered into between the parties on October 5, 1914, and the construction work was commenced by plaintiff on or about October 15, 1914, and thereafter continuously prosecuted until on or about December 20 of the same year, when owing to weather conditions, work was suspended until the early spring months of 1915, when it was again resumed and continued until the completion of the reservoir, September 28, 1915.

Under the contract entered into between the parties the plaintiff was to do all the work and furnish all the materials (computed on approximate quantities) necessary to construct the reservoir in a proper and workmanlike manner according to the plans and specifications furnished by the defendant city. Payments were made by the defendant (hereinafter for convenience referred to as the city), based on par[508]*508tial estimates as the work progressed, until the total sum of $40,451.53 had been paid to the plaintiff by the city on the contract, which sum was all the city was willing to concede that the plaintiff was entitled to for the work and labor furnished for the completed reservoir. The plaintiff claimed he had not been fully paid and after presenting his claim in due form for $16,517.47 over and above the amount paid by the city, and the city having rejected his claim, brought suit therefor in the district court for Salt Lake County, upon which he obtained, after a trial to the court without a jury, judgment against the city for $12,775.57, with interest and costs. Prom this judgment the city appeals.

The complaint sets forth three separate causes of action. The first cause of action involves the labor and material furnished by the plaintiff under the contract for the construction of the reservoir. While the evidence adduced 1 by the respective parties is conflicting as to the amount of labor and material furnished, the trial court found for the plaintiff, and on this cause of action rendered a judgment against the city upon the several items alleged to be due the plaintiff, totaling the sum of $4,448.24. We find there is substantial evidence in support of all the findings with respect to the plaintiff’s first cause of action, and therefore this court has not the power to and will not disturb the same. Goan v. Ogden, L. & C. R. Co., 51 Utah, 285, 169 Pac. 949.

The second cause of action involves items in the furnishing of labor and material by plaintiff for the completion of the reservoir, alleged not to be within the terms of, nor contemplated by the parties under, the contract. The plaintiff alleged that the city engineer improperly and 2 unnecessarily required him, when the work was suspended in 1914, to put earth on the slopes of the excavation and embankment of the reservoir to protect them during the winter season and until the work of construction might be resumed, in 1915, for which plaintiff claimed $8,135.52 after giving a credit of $650.16 paid by the city; a claim for removing dirt, in the sum of $40, that was disallowed by the [509]*509trial court; a claim for $48 extra labor occasioned by an error on tbe part of tbe city in setting grade stakes, and for $25 the price of a band rail. Tbe last two items are confessed by tbe city on this appeal. The trial court again found tbe issues in favor of the plaintiff, and rendered judgment against tbe city on tbe several items allowed, the sum total being $8,208.53. As before, we find substantial evidence in tbe record to sustain tbe findings of tbe trial court both as to the amount of labor furnished and that the price charged therefor was reasonable.

Tbe plaintiff testified that the charge made therefor against the city was but the actual cost to him of the labor performed plus 15 per cent, for engineering and reasonable profit. While there is some conflict in the testimony as to the amount of extra labor performed in the cleaning of the slopes of the reservoir we think the great weight of the evidence supports the plaintiff’s contention and the finding made by the trial court, both as to the amount of extra labor and reasonableness of the charge made therefor.

However, it is contended by the city that, conceding the work now under consideration to be extra, the cleaning of the slopes of the reservoir comes within the contract entered into between the parties as to the price, and should be paid for at the contract price of thirty-five cents per cubic yard under certain provisions of the contract which read:

"The prices named in the proposal attached hereto are for the completed work, and include the furnishing of all materials, and all labor, tools, and appliances, and all expenses, direct or indirect, connected with the proper execution of the work, in accordance with the plans, profiles, and specifications for the work, and of maintaining the same until it is accepted by the board of commissioners. (Italics ours.)
"Excavating shall include the work of removing all earth, stone, loose rock, clay, shale, cement, hardpan, boulders, and all other materials necessary to he removed in excavating for the reservoir, .pipes, etc. (Italics ours.)
"The contractor shall do such extra work in connection with the work herein contracted to be done as the city en[510]*510gineer may direct, and the price thereof shall be according to the schedule of prices in this contract, except in so far as it shall be expressly stated on the face of the order that force accounts will be allowed. No allowance for extra work of any kind shall be made unless the contractor shall have been furnished with an extra order authorizing such work, signed by the city engineer and approved by the commissioner of streets and public improvements.
"On or before the tenth day succeeding the completion of the extra work authorized by an extra work order, the contractor shall present to the city engineer the original extra work order, on the back of which shall be a full and complete itemized statement of such extra work, etc., together with date of the completion of the work mentioned therein. * * * No payment shall be allowed for any extra work for which the contractor fails to present the extra work order herein-before mentioned.”

There are other provisions, not necessary to here set forth, contained in the instructions to bidders, the proposal and the specifications, all of which are embodied within and made a part of the contract, to the same effect, namely, that the work contemplated under the contract is to be confined to and done “in accordance with the plans, profiles, and specifications for the work.”'(Italics ours.)

The plaintiff contends, and throughout the trial in the district court prosecuted his case on the theory, that the labor of extra excavation and removal of earth from the slopes of the reservoir was improper, unnecessary, and not at all contemplated under the contract. This contention, directly opposed to that of the city, fínd¡3 much support in. the testimony, and the trial court found:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Higgins v. City of Fillmore
639 P.2d 192 (Utah Supreme Court, 1981)
Allen-Howe Specialties Corp. v. U. S. Construction, Inc.
611 P.2d 705 (Utah Supreme Court, 1980)
Wunderlich Contracting Company v. United States
240 F.2d 201 (Tenth Circuit, 1957)
Frank T. Hickey, Inc. v. Los Angeles Jewish Community Council
276 P.2d 52 (California Court of Appeal, 1954)
Jensen v. Logan City
83 P.2d 311 (Utah Supreme Court, 1938)
Baker v. Wycoff
79 P.2d 77 (Utah Supreme Court, 1938)
Campbell Building Co. v. State Road Commission
70 P.2d 857 (Utah Supreme Court, 1937)
England v. State
246 N.W. 628 (South Dakota Supreme Court, 1933)
Hurd v. Ford
276 P. 908 (Utah Supreme Court, 1929)
Fisher v. Bonneville Hotel Co.
188 P. 856 (Utah Supreme Court, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
174 P. 847, 52 Utah 506, 1918 Utah LEXIS 86, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilson-v-salt-lake-city-utah-1918.