Schneider v. City of Ann Arbor

162 N.W. 110, 195 Mich. 599, 1917 Mich. LEXIS 723
CourtMichigan Supreme Court
DecidedMarch 30, 1917
DocketDocket No. 101
StatusPublished
Cited by13 cases

This text of 162 N.W. 110 (Schneider v. City of Ann Arbor) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schneider v. City of Ann Arbor, 162 N.W. 110, 195 Mich. 599, 1917 Mich. LEXIS 723 (Mich. 1917).

Opinion

Fellows, J.

In the summer of 1918 the defendant city contemplated the construction of two sewers in districts Nos. 56 and 60. On August 20th plaintiff submitted a proposal in which he offered to do all the excavation and back-filling at the following prices per lineal foot: Class 1, for trenches less than-6 feet deep, 35 cents; class 2, for trenches between 6 to 8 feet deep, 50 cents; class 3, for trenches between 8 and 10 feet deep, 80 cents; class 4, for trenches between 10 and 12 feet deep, 95 cents. On August 28th, he entered into a contract with the city to do this work at the figures named. There are many provisions and details in the contract. Those deemed important to an understanding of the case will be given as we proceed. After the work was completed he was given a warrant for the sum of $4,039.70, the amount certified by the engineer. Later he filed his claim against the city for an additional sum claimed by him to be due, and upon refusal to pay brought this suit. The trial judge directed a verdict for the defendant, __and the case comes to this court for review on case-made.

The plaintiff insists upon a recovery upon two characters of claims which are covered by three special counts in his declaration and which we shall discuss in their order. Under the first count he claims the right to recover $688.45 beyond what he has already received for the excavation and back-filling performed by him pursuant to the terms of the contract. To sustain a recovery on this count plaintiff produced the blueprints prepared by the city engineer showing the proposed plans and profiles of district 56, which he claims he examined before making his bid; also an[602]*602other set of blueprints prepared by the engineer, showing the elevations and levels of the sewer as actually constructed by plaintiff. The city engineer; who was called by plaintiff to identify these blueprints, on cross-examination, testified that the set of blueprints which plaintiff examined before he made his bid was prepared to give the board of public works and common council an idea of what the sewer would cost; that the elevation of the street, represented by a heavy line, was' taken in the center, although the sewer is quite certain to be placed several feet one side or the other; that the sewers are actually constructed from pins set on one side or the other of the trench, and the constructor measures down from these pins to get the levels for the bottom of the trench. These pins are usually set on the high side of the trench. Testimony was also given by plaintiff that before he made his bid the city engineer informed him that the heavy line on the profile represented the surface of the ground at the center of the trench, and he so used it in making his general estimates. It also appeared that the city in all cases of sewer construction prepared “cut sheets” showing the actual depth measured down from the pins or stakes, which were placed along the side of the trench every 25 feet, and plaintiff was always furnished copies of these cut sheets. Plaintiff says he always understood he settled with the city in substantial accordance with the profiles, although he knew that the city engineer used the cut sheets in checking up the amount due under the contract. He also testifies that the grade pins were often placed below the level of the ground at the line of the trench, but that they were placed where he wanted them and were changed at his request. He gives evidence tending to show that, taking the original blueprints, which he saw before he made his bid, there was in class 1, 308 lineal feet of excavation; class 2, 3,193.07 lineal [603]*603feet; class 3, 3,496.60 lineal feet, and in class 4, 256 lineal feet. The changes in the levels actually made in the sewers altered the amounts of excavation in the respective classes as follows: Class 1, 83 lineal feet more; class 2, 843.93 lineal feet more; class 3, 989.9 lineal feet less; and class 4, 28 lineal feet less. Plaintiff then proved that the average depth of excavation in the classes as shown by the original blueprints differs from the average depth as shown on the later ones, and showed the. amount of such difference, and on the basis of these averages, taking the original set of blueprints as exactly correct, he would have been required to have excavated under the terms of his contract 148,652.98 cubic feet, and at the price per lineal foot agreed upon in the various classes he would have received 3.19 cents per cubic foot; that, taking 3.19 cents per cubic foot as the basis of his compensation, and taking the number .of cubic feet actually excavated under the changed levels, there would be due him $4,601.07 for excavating and back-filling, from which should be deducted the amount paid, and the balance would be due him on this count.

It is difficult to follow plaintiff through this maze of computations, impossible to follow his conclusions arrived therefrom, that this contract, which expressly provides for payment for excavations per lineal foot, can, by any system of mathematical calculations, be transferred into or construed to be a contract to pay for excavations at 3.19 cents per cubic foot or any other sum per cubic foot, or that cubic foot excavation can be used to measure his compensation or his damages in this action. It is urged in the brief that plaintiff made very low prices in one of the classes expecting to make up the deficiency in other classes, and that he could afford to do the work in one class without a profit when he could make up in another class. The system of computations used' by plaintiff as a [604]*604basis for his bid is unimportant. The fact that is important is that he contracted to do the excavating in this sewer district at certain figures per lineal foot, and he contracted to do all of it, whether it be much or little. One contracting to furnish all the labor or material which may be required for a given purpose is not relieved of the obligation of his contract because the amount exceeds or falls short of the estimates. Wolff v. Wells Fargo & Co., 115 Fed. 32 (52 C. C. A. 626); Callmeyer v. City of New York, 83 N. Y. 116.

The exhibition to the plaintiff before he bid of the original blueprints prepared by the city engineer did not constitute a warranty that the exact amount of excavation there delineated would be done in the actual carrying on of the work. Whatever excavating plaintiff did in each particular class was to be paid for at the price named in that class; it was not a lump sum bid. The contract itself contemplated that there would be changes in the plans and work done. It was agreed therein:

“Should any change or alteration be made in the plans of said work or material be required whereby a diminution of the work to be done, or material to be furnished shall be occasioned, it is agreed by the parties hereto that a pro rata reduction from the moneys which shall or may be due or become due under this contract shall be made in accordance with the schedule of prices for such extra work and material in the proposal for the construction of such sewer work.”

It was also provided in the contract:

“The sewer shall be located on the line shown on the plan of the work. This line whenever practicable, will be on the center line of the street. The board reserves the right to remove the line of sewer to the right or left whenever it shall deem a change of line desirable.”

And the following was also agreed to:

[605]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L Loyer Construction Co. v. City of Novi
446 N.W.2d 364 (Michigan Court of Appeals, 1989)
Lanzo Construction Co. v. City of Port Huron
276 N.W.2d 613 (Michigan Court of Appeals, 1979)
E C Nolan Co. v. Department of State Highways
206 N.W.2d 472 (Michigan Court of Appeals, 1973)
Superior Ambulance Service v. City of Lincoln Park
173 N.W.2d 236 (Michigan Court of Appeals, 1969)
Chambless v. JJ Fritch, General Contractor, Inc.
336 S.W.2d 200 (Court of Appeals of Texas, 1960)
Kaplan v. City of Huntington Woods
99 N.W.2d 514 (Michigan Supreme Court, 1959)
Sittler v. Board of Control
53 N.W.2d 681 (Michigan Supreme Court, 1952)
Utica State Savings Bank v. Village of Oak Park
273 N.W. 271 (Michigan Supreme Court, 1937)
Attorney General Ex Rel. O'Hara v. Montgomery
267 N.W. 550 (Michigan Supreme Court, 1936)
Baker v. City of Kalamazoo
256 N.W. 606 (Michigan Supreme Court, 1934)
Rosoff v. Haussamen
228 N.W. 830 (North Dakota Supreme Court, 1930)
Hull v. Board of County Road Commissioners
203 N.W. 474 (Michigan Supreme Court, 1925)
Wilson v. Salt Lake City
174 P. 847 (Utah Supreme Court, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
162 N.W. 110, 195 Mich. 599, 1917 Mich. LEXIS 723, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schneider-v-city-of-ann-arbor-mich-1917.