Rens v. City of Grand Rapids

41 N.W. 263, 73 Mich. 237, 1889 Mich. LEXIS 1116
CourtMichigan Supreme Court
DecidedJanuary 11, 1889
StatusPublished
Cited by16 cases

This text of 41 N.W. 263 (Rens v. City of Grand Rapids) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rens v. City of Grand Rapids, 41 N.W. 263, 73 Mich. 237, 1889 Mich. LEXIS 1116 (Mich. 1889).

Opinion

Long, J.

This action is in assumpsit on the common counts, brought in the superior court of Grand Rapids. Plaintiff had judgment for $700. Defendant brings error.

It appears that on June 5, 1886, plaintiff entered into a written contract with defendant for the improvement of Ellsworth avenue, a public street of the city, from the south line of Fulton street, for the sum of $9,720, and agreed to prosecute the same with all due diligence, and finish and complete the same, on or before September 1, 1886, to the full satisfaction of the board of public works, and according to the plans and specifications of [239]*239the work, which were made part of the contract, .and annexed thereto.

The claim of the plaintiff is that he fully completed all the work under this agreement, and that such work was accepted by defendant, and paid for in full; that several months after this contract was made, and a large part of the work performed, an agreement was entered' into between him and defendant, through the city surveyor, for extra work outside of the contract, and for which this suit is brought; and that no part of the work for which suit is brought was contemplated by or done under the contract. This agreement for such extra work and material, made with the city surveyor, was not in writing, but under it plaintiff' claims to have done the work and furnished the material mentioned in his bill of particulars.

The claim in the bill of particulars is:

To hauling 8,500 yards of dirt 450 feet............ §850 00
To 48 loads of stone delivered to defendant...... 96 00
To 84 loads of gravel delivered to defendant_____ 42 00
To 224 loads of screened gravel delivered.......... 224 00
To excavating and grading 85 feet of Cherry street _________________________________________ 48 00
To excavating and graveling 15 feet of Williams street-......................-.................. 85 00
To paving and graveling on Waterloo street----- 81 00
To 120 days’ labor............................... 180 00
Total........................................ §1,506 00

Upon filing this bill of particulars defendant pleaded the general issue, and gave notice:

1. That if the work was done and materials furnished as claimed, it was so done and furnished under and by virtue of such special contract in writing, made, on June 5, 1886.

2. That defendant has performed the contract on its part, and paid the full contract price.

3. That plaintiff did not finish and complete said work •on or before September 1, 1886, but, on the contrary, did not finish and complete the same until the month of July, [240]*2401887, to the damage of defendant $1,000, which sum defendant will recoup on the trial.

4. That by the terms of the contract the time specified for the completion of the work was declared to be material, and of the very essence thereof, and that for each and every day the contract should remain unperformed after the time named therein for its performance it was stip- • ulated and agreed that the sum of $10 might be deducted from the amount to be paid by defendant thereon, and that amount should not be paid by defendant, and also, in addition thereto, the amount of the par diem of the inspector employed to oversee the work might be deducted; that such inspector was employed by defendant until the 'completion of said work, and all the time the same was going on; that by reason of the non-performance of said contract within the time agreed the said defendant has suffered damages, in that it has been obliged to and has paid out for the inspection of said work, to an inspector thereof, the sum of $300 for inspection during the time elapsing between the time the contract should have been performed by its terms and the time it was actually completed, to wit, a period of eight months, — all which inspection account and said $10 per day, amounting to $3,000, are valid and subsisting counter-claims and set-offs against the claim of plaintiff, etc.

The mode and manner in which contracts for public improvements of the nature of the one which defendant claims is involved in this case should be made, carried out, and paid for is regulated by the provisions of the charter and board of public works act of said city. It is provided by this act that the common council must first determine that the improvement is a necessary public improvement. The board of public works thereupon determines the kind and quality of the material to be used, estimates the probable cost, prepares the necessary plans and specifications, and reports such estimates to the common council as a basis for assessing or otherwise raising the funds to carry on and complete such work. Such work must be done under the direction and supervision of the board of public works, and upon contracts and [241]*241■under plans and specifications prepared by the city surveyor., and approved by such board, and the moneys raised or appropriated by the council for such purposes shall be expended by said board, so far as necessary, upon estimates made by the board and reported to the council in accordance with such contract; and no money shall be drawn from the city treasury except upon orders of the council, and such contract shall first be submitted to the council before adoption and execution. Local Acts of 1877, No. 339, § 9.

The material parts of the contract for the improvement of Ellsworth street are that—

“Said first party does hereby agree with said party of the second part to improve Ellsworth avenue, and furnish all the materials necessary therefor, and do all the work incident thereto, and furnish all the material for such incidental work, and to construct said work as to material, size, and every other particular in accordance with the plan, specifications, and profile relative thereto, now on file in the office of the board of public works for said city/5 etc.
“The party of the second part reserves the right to change any portion of the work from time to time, and to make all necessary additions thereto or deductions therefrom. And it is mutually agreed that the city surveyor shall estimate and decide the additions or deductions to be made to, or taken from, the price specified for the work in consequence of such changes, additions, or deductions.
“And the party of the first part will commence said work on June 12, 1886, and prosecute the same with all due diligence, and finish and complete the same, on or before September 1, 1886, to the full satisfaction of the board of public works, for the sum of $9,720; that said first party shall not be entitled to demand or receive pay-, ment for said work or material, or any portion thereof,, until the funds to meet such payment shall have been collected and paid into the city treasury, upon assessments made, and to be made, for the doing of said work, so the city of Grand Kapids shall not be liable to advance. [242]*242any money for the doing of said work, or any portion thereof, save from the special fund and assessment aforesaid. ***** *****

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Superior Ambulance Service v. City of Lincoln Park
173 N.W.2d 236 (Michigan Court of Appeals, 1969)
Kaplan v. City of Huntington Woods
99 N.W.2d 514 (Michigan Supreme Court, 1959)
Sittler v. Board of Control
53 N.W.2d 681 (Michigan Supreme Court, 1952)
Utica State Savings Bank v. Village of Oak Park
273 N.W. 271 (Michigan Supreme Court, 1937)
Baker v. City of Kalamazoo
256 N.W. 606 (Michigan Supreme Court, 1934)
Prange v. City of Flint
187 N.W. 356 (Michigan Supreme Court, 1922)
Schneider v. City of Ann Arbor
162 N.W. 110 (Michigan Supreme Court, 1917)
Sharpless Separator Co. v. Brown
140 N.W. 528 (Michigan Supreme Court, 1913)
Edwards Hotel & City Street Railroad v. City of Jackson
51 So. 802 (Mississippi Supreme Court, 1910)
Reimink v. Strabbing
122 N.W. 183 (Michigan Supreme Court, 1909)
Ereño v. Porto Rico
2 P.R. Fed. 290 (D. Puerto Rico, 1906)
Coit v. City of Grand Rapids
73 N.W. 811 (Michigan Supreme Court, 1898)
Collins v. Township of Grand Rapids
66 N.W. 586 (Michigan Supreme Court, 1896)
Campau v. City of Detroit
64 N.W. 336 (Michigan Supreme Court, 1895)
City of Detroit v. Detroit City Ry. Co.
56 F. 867 (U.S. Circuit Court for the District of Eastern Michigan, 1893)
Murphy v. City of Albina
29 P. 353 (Oregon Supreme Court, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
41 N.W. 263, 73 Mich. 237, 1889 Mich. LEXIS 1116, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rens-v-city-of-grand-rapids-mich-1889.