Ereño v. Porto Rico

2 P.R. Fed. 290
CourtDistrict Court, D. Puerto Rico
DecidedDecember 11, 1906
DocketNo. 230
StatusPublished

This text of 2 P.R. Fed. 290 (Ereño v. Porto Rico) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ereño v. Porto Rico, 2 P.R. Fed. 290 (prd 1906).

Opinion

Pokey, Judge,

delivered the following opinion:

In this case, the parties, by proper stipulation, waived a jury and tried the cause before the court. Much of the evidence had been previously taken by deposition, and that, together with what was taken orally on the recent trial, the pleadings in the ease, and the exhibits, raises all the issues of law and fact now ■ to be passed upon by the court.

The action is an ordinary suit in assumpsit to recover $2,4 6 G alleged to be due the plaintiff from the government of the island of Porto Pico on account of the fact that the plaintiff built a schoolhouse at Fajardo of dressed stone instead- of brick, as was contemplated under the contract between the parties.

The declaration alleges that a written contract was entered into in December, 1901, but the fact appears to be from the instrument itself in evidence, that it was entered into on June 29th of that year. The contract price of the building was $16,000, but that the plaintiff alleges that the agreement was verbally modified with the full knowledge and consent of - the [292]*292defendant through its commissioner of education, so as to permit the use of stone instead of brick in the construction thereof, and that, on account of the increased value of the building to the defendant and the increase in the cost of.construction by reason of the modification made, the difference was to be paid to the plaintiff in addition to the contract price. That after this verbal modification with the full knowledge and consent of the defendant, as it is alleged, the plaintiff proceeded with the construction of the said building, and that the additional cost was the sum aforesaid which he sues for. It is further alleged that the plaintiff fully carried out and performed his part of the contract, including this alleged modification thereof, but that the defendant has refused to do so, but has paid the full price mentioned in the contract, of $16,000, and refuses to pay the said alleged balance.

The declaration then proceeds to declare for the balance due, under all of the common counts, as fully as is the custom in a common-law suit in assumpsit';, that is, on account stated, for work done and materials- furnished, for money paid, laid out, and expended, and for money had and received, etc.

After some preliminary pleading, the defendant by its attorney general, by leave of the court first had, filed several pleas, setting up in detail its alleged complete defense to the whole cause- of action,, the substance of which pleas is:

(1) Denying each and. every allegation of the declaration.

(2) Alleging the entering into the contract by the parties, and that no modification-or change in the construction of the building was in fact, or could be, made under the terms thereof that would increase or diminish the cost of the work, except upon agreement in writing by the contracting parties, setting forth the changes to be made and the prices to be paid therefor, and

[293]*293(3) Alleging that on the 3d of September, 1902, a complete settlement was had between the parties under the contract and in the premises, — the plaintiff having, up to that time, received, under said contract, in various partial payments thereunder, the sum of $14,909.14, and on the latter date having received and accepted in full payment in the premises, the sum of $1,090.86.

As the parties went to trial without objection on these pleadings, it will be assumed that a replication denying the pleas was considered as filed, especially as the proofs thereafter introduce^ were directed to an issue thus raised.

The contract for the construction of the building is quite specific in its terms, is signed by Dr. Brumbaugh for the island and by plaintiff on his own account, and is accompanied by the signed proposal of the plaintiff, offering to- do the work for $16,000. There was evidence in the case tending to show that plaintiff had never submitted a bid under any advertisement calling for the same by the island, but, -if he did. not, he certainly signed one of the blank proposals just before entering into the contract, as the paper is annexed to the contract now in evidence, and is signed by him. The contract is further accompanied by the specifications in detail and the bond of the contractor, as well as by a copy of the advertisement purporting to have been issued, and all of which, under the terms of the contract itself, are made a part of it. These papers are voluminoup and go into all the details connected with the work, and have the signatures of the parties on them at all proper .places. (

The material portion of the actual contract, which, it is contended, concludes the plaintiff, reads as follows:

“If, at any time during the prosecution of the.work, it be found advantageous or necessary to make any change in the specifications as to character and quantity, whether of labor or ma[294]*294terial, as would' either increase or diminish the cost of the work, then such change or modification must be agreed upon in writing by the contracting parties, the agreement setting forth fully the reasons for such change, and giving clearly the qualities and prices of both materials and labor thus substituted for those named in the original contract: Provided, that no payments shall be made unless such supplemental or modified agreement was signed before the obligation arising from such modification was incurred.
“No claim whatever shall at any time be made upon the commissioner of education of Porto Pico, by the party or parties of the second part, for or on account of any extra work or material performed or furnished, or alleged to have been performed or furnished, under or by virtue of this contract, and not expressly bargained for and specifically included therein, unless such extra work or materials shall have been expressly required in writing by the party of the first part or his successor, the prices and quantities thereof having been first agreed upon in writing by the contracting parties.”

■ The evidence in the case as to. whether or not there ever was any binding modification of the contract in question entered into between the parties is quite conflicting. It appears that plaintiff is a very intelligent man, and a contractor for such buildings of-considerable experience. That he had theretofore constructed schoolhouses for the island at Cayey, Aibonito, Manati, and two in Ponce. It appears also that he speaks only Spanish, and-that his transactions with the department were in that language when any of the officers could speak it and through an interpreter when they could not. The substance of his own evidence and claim is that Dr. Brumbaugh, who was then the commissioner of'education for the island, had called him from [295]*295Manatí to San Juan with a view to seeing if he 'would take a contract to build the schoolhouse in question, as the department had failed to receive any bid less than $17,000 for its construction, under an advertisement theretofore issued, and which sum was considered too high. That the commissioner asked him if he would do the work for $16,000 and he answered that he could not.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whiteside v. United States
93 U.S. 247 (Supreme Court, 1876)
Hawkins v. United States
96 U.S. 689 (Supreme Court, 1877)
Pray v. United States
106 U.S. 594 (Supreme Court, 1883)
District of Columbia v. Gallaher
124 U.S. 505 (Supreme Court, 1888)
Fire Ins. Assn., Ltd. v. Wickham
141 U.S. 564 (Supreme Court, 1891)
Woodruff v. . Roch. Pitts. R.R. Co.
14 N.E. 832 (New York Court of Appeals, 1888)
Dillon v. City of Syracuse
9 N.Y.S. 98 (New York Supreme Court, 1890)
Bryant v. Stilwell
24 Pa. 314 (Supreme Court of Pennsylvania, 1855)
Badders & Britt v. Davis
88 Ala. 367 (Supreme Court of Alabama, 1889)
Jones v. Woodbury
50 Ky. 167 (Court of Appeals of Kentucky, 1850)
Rens v. City of Grand Rapids
41 N.W. 263 (Michigan Supreme Court, 1889)
Tanner v. Merrill
31 L.R.A. 171 (Michigan Supreme Court, 1895)
Belt v. Cook
3 F. Cas. 152 (U.S. Circuit Court for the District of District of Columbia, 1829)
Bowe v. United States
42 F. 761 (U.S. Circuit Court for the Northern District of Georgia, 1890)
Ricker v. Sanitary Dist. of Chicago
89 F. 251 (U.S. Circuit Court for the Northern District of Illnois, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
2 P.R. Fed. 290, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ereno-v-porto-rico-prd-1906.