District of Columbia v. Gallaher

124 U.S. 505, 8 S. Ct. 585, 31 L. Ed. 526, 1888 U.S. LEXIS 1887
CourtSupreme Court of the United States
DecidedFebruary 6, 1888
Docket141
StatusPublished
Cited by74 cases

This text of 124 U.S. 505 (District of Columbia v. Gallaher) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
District of Columbia v. Gallaher, 124 U.S. 505, 8 S. Ct. 585, 31 L. Ed. 526, 1888 U.S. LEXIS 1887 (1888).

Opinion

Mr. Justice Matthews

delivered the opinion of the court.

This suit was brought against the District of Columbia for the recovery of the sum of $138,459.55 ; of this $35,436.49 were alleged to be payable as the balance due upon a contract for building and completing the brick arch upon.stone abutments of Tiber Creek sewer, as.set out and described in the *506 contract and specifications attached to the petition, at the price of $113 per lineal foot. The additional sum. of $98,130.44 was alleged to be due on account of extra work and materials furnished by the contractors beyond the requirements of the contract in and about the same work. This indebtedness was denied, and the defendant also filed a plea of set-off in the sum of $82,176; of this, $7176 was for the value of stone alleged to have been sold by the defendant to the claimants; $35,000 on account of deficiencies in the construction of the sewer, and $40,000 as the reasonable cost and expense of filling the canal for the whole length of the sewer, which the defendant claimed the petitioners were bound by their contract to do. Upon the facts found by the court, it was held that the claimants were entitled to recover upon their claims the sum of $43,935.74; that the defendant was entitled to recover upon the set-off and counterclaim the sum of $1479 ; and judgment was rendered in favor of the petitioners for the difference, being the sum of $42,456.74.

The facts as found by the court, so far as material, are as follows:

The Tiber Creek, prior, to the year 1871, was a natural stream of water flowing through the city.of "Washington and discharging into what was then known as the Washington Canal, on Third Street west, between Maine and Missouri avenues, and by that into the Eastern Branch.

Among the improvements projected by the Board of Public Works was that of utilizing this stream in connection with the sewerage system of the city, and the general plan adopted was that of constructing a main sewer of masonry and brickwork along its course, through which the stream should flow, receiving and conducting the sewage from lateral connections on either side.

It was constructed for the most part in sections by contract with different parties, and the part here in controversy was the final or outlet section. It was commonly styled the Tiber Creek sewer or arch.

■ On and before July 14, 1873, a portion of this sewer had been completed, which ("so far as is here material) extended *507 from the north side of Pennsylvania Avenue, across the Botanical Garden, into Third Street, and along and under Third Street to a point 3 feet north of the south building line of Maryland Avenue, at which terminus the sewer was (so far as here material) of the following construction and size, namely : The side walls were of masonry, about 3 feet high and 5 feet 0 inches thick, supporting an approximate semi-elliptic arch of 30 feet span and 7 feet 10 inches rise. The extrados of the arch, including the skew-back course, was backed up with rubble masonry to the level of its crown.

The timber sleepers for the foundations were 41 feet in length.

Proposing to continue the sewer to its outlet with the same construction and size, the Board of Public Works, on July 14, 1873, sent to II. L. Gallaher & Co., consisting of Hugh L. Gallaher and Edwin H. Smith, a written proposal for continuing the Tiber Creek sewer from its existing terminus at Maryland Avenue and Third Stréet southwest, along the line of the Washington Canal to its junction with the James Creek Canal, the size and manner of construction of the sewer to be tire same as that of the portion of the same sewer constructed on Third Street southwest, and to be paid for at the rate of $113 per lineal foot; and they were requested by return mail to notify the board of their acceptance or rejection of the proposal. On the same day II. L. Gallaher & Co., by writing, accepted it. A written contract bearing date July 19, 1873, was executed between the parties in the same terms as that set forth in the petition. Before work was commenced under it the District engineer was instructed to give the grade of the sewer, to be laid out with the same dimensions as of the existing sewer, which he did in the summer of 1873. It was proposed, however, and consented to by both parties, to deviate from the contract, by which the continuation of the sewer was to follow and be laid in the bed of the canal, so as to take it by a curve from the point of connection on the westerly bank and then proceed parallel with and along said bank to the terminus. About the time of giving the grade Gallaher applied for a plan of the sewer, when by direction of the *508 engineer a plat or working drawing of the structure in transverse section, exhibiting its form and dimensions according to a fixed scale, and representing a structure similar to that of the completed section at the point of connection, was furnished. Gallaher and Smith then proceeded with the work in accordance with that plan', and completed some part of the excavation, and procured and brought on the ground material, but had not constructed any portion of the arch, when Joseph G. and Henry E. Loane, two of the petitioners, bought out the interest of Smith in the contract, and thereupon the original contract was cancelled and one in similar terms executed on December 22, 1873, by the Board of Public "Works with the claimants, composing the firm of Gallaher, Loane & Company, a copy of which is set out with the petition. The claimants on entering into said contract received from Gallaher & Smith the working plan furnished to them by the District engineer. It represented the plan and dimensions of the several parts of the structure of the sewer to be built under their contract, and was similar to the completed section with which it was to connect, as provided by the contract, and was the plan under which the work had been commenced and carried on. They proceeded xvith the work in accordance with the plan, and without calling the attention of the board to any alleged or apparent variation of the same from the contract, and constructing the flooring, masonry, and arch according to the dimensions appearing thereon, and had finished about 680 lineal feet thereof when the Board of Public Works was abolished by act of Congress of June 20, 1874. The work as thus far done was constructed under the direction of the District engineers, but neither they nor the Board of Public Works intimated to the claimants that the work was not progressing to their satisfaction and in accordance with the former sample work, in which the skew-back was constructed of rubble masonry.

Under the new form of government established by that act for the District, Bichard L. Iloxie was detailed as engineer on July 6, 1874, and forthwith made a careful examination of the work being clone by claimants, as to its character and con *509 formity with the specification of the contract, in the presence of one of the claimants.

He found'that, generally, it was being built in conformity with the specifications, but there were several departures.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atuar v. United States
156 F. App'x 555 (Fourth Circuit, 2005)
Chahroudi v. United States
124 Ct. Cl. 792 (Court of Claims, 1953)
Embree v. Koelsch
119 P.2d 533 (Supreme Court of Kansas, 1941)
Fidelity & Casualty Co. v. Gray
1937 OK 520 (Supreme Court of Oklahoma, 1937)
Stackhouse v. Pure Oil Co.
180 S.E. 188 (Supreme Court of South Carolina, 1935)
Chippewa Indians v. United States
80 Ct. Cl. 410 (Court of Claims, 1935)
Lackey v. General Casualty & Surety Co.
32 P.2d 241 (Supreme Court of Kansas, 1934)
Manufacturers Aircraft Ass'n v. United States
77 Ct. Cl. 481 (Court of Claims, 1933)
Gerlach v. Commissioner
27 B.T.A. 565 (Board of Tax Appeals, 1933)
City of Covington v. Union Light, Heat & Power Co.
49 S.W.2d 580 (Court of Appeals of Kentucky (pre-1976), 1932)
Marietta Manufacturing Co. v. United States
73 Ct. Cl. 528 (Court of Claims, 1932)
Maneely v. United States
68 Ct. Cl. 623 (Court of Claims, 1929)
Kirkpatrick v. Chrysler Sales Corp.
275 P. 155 (Supreme Court of Kansas, 1929)
Worthington Pump & Machinery Corp. v. United States
66 Ct. Cl. 230 (Court of Claims, 1928)
Haskell & Barker Car Co. v. Commissioner
9 B.T.A. 1087 (Board of Tax Appeals, 1928)
Pittsfield & North Adams Railroad v. Boston & Albany Railroad
157 N.E. 611 (Massachusetts Supreme Judicial Court, 1927)
Tooey v. C. L. Percival Co.
192 Iowa 267 (Supreme Court of Iowa, 1921)
Hatcher v. Ferguson
198 P. 680 (Idaho Supreme Court, 1921)
Citizens Telephone Co. v. City of Newport
224 S.W. 187 (Court of Appeals of Kentucky, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
124 U.S. 505, 8 S. Ct. 585, 31 L. Ed. 526, 1888 U.S. LEXIS 1887, Counsel Stack Legal Research, https://law.counselstack.com/opinion/district-of-columbia-v-gallaher-scotus-1888.