Maneely v. United States

68 Ct. Cl. 623, 1929 U.S. Ct. Cl. LEXIS 232, 1929 WL 2450
CourtUnited States Court of Claims
DecidedDecember 23, 1929
DocketNo. H-134
StatusPublished
Cited by5 cases

This text of 68 Ct. Cl. 623 (Maneely v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maneely v. United States, 68 Ct. Cl. 623, 1929 U.S. Ct. Cl. LEXIS 232, 1929 WL 2450 (cc 1929).

Opinion

GREEN, Judge,

delivered the opinion of the court:

Plaintiff in this case brings suit to recover the value of certain pipe furnished to the Government and used in construction work on the Aberdeen Proving Ground, at Aberdeen, Maryland. The pipe was furnished by the John Maneely Company, a partnership in which James F. Maneely was a partner. He subsequently died, and the other partner, Edward F. Maneely, became administrator of the estate of the deceased. The John Maneely Company still continued in business and is the plaintiff in the suit.

The evidence shows that the Maryland Dredging & Contracting Company entered into a “ cost-plus contract ” with the defendant to furnish certain material, etc., for construction work on the Aberdeen Proving Ground, the Government to pay under certain conditions the cost of what was furnished under the contract and an additional sum by way of compensation to the contractor. The contract provided for the making of subcontracts and also provided for the termination of the contract when the contracting officer deemed it advisable, and further that in case the contract was so terminated, the “ contracting officer shall assume and become liable for all such * * * unliquidated claims as [628]*628the contractor may have theretofore, in good faith, undertaken or incurred in connection with said work.” The Maryland Dredging & Contracting Company entered into a subcontract with Eiggs, Distler & Stringer, Inc., by which the last-named corporation obligated itself to furnish certain materials, etc., for the same work. The constructing officer at the Aberdeen Proving Ground issued an order, or orders, for a certain amount of pipe and other materials, which was transmitted to the subcontractor, which in turn directed the John Maneely Company to furnish the pipe so ordered and deliver it at the Aberdeen Proving Ground for the account of the said Eiggs, Distler & Stringer, Inc. The John Maneely Company carried out this order and so delivered the pipe involved in this case sometime in September, 1918. In November following the constructing officer ordered the work on the contract stopped, terminated the contract with the original contractor, and gave notice that the contract with the subcontractors had been terminated. About the same time, the constructing officer authorized and directed the original contractor to give notice that all bills that were outstanding at a specified date should be submitted to him for payment. In making settlement with the other contractors, the Government did not pay for the pipe furnished by the John Maneely Company and involved herein.

Pursuant to the notice given by the constructing officer the John Maneely Company presented its bill for the pipe that was so furnished, but the bill was not approved, the Government officials claiming that the bill was excessive and the receipt of some of the pipe was questioned. After a prolonged dispute of some three or four years, the Government officials admitted the receipt of the pipe and approved the claim in the amount of $5,840.50. This value was less than had been claimed by the Maneely Company, but that company accepted this determination, and in January, 1922, two vouchers were prepared and approved by the commanding officer at the Aberdeen Proving Ground covering payment for the pipe so furnished in the total amount of $5,840.50, which was the fair value of the pipe. In due course these vouchers were certified to the Comptroller General and by him disallowed on the ground that no privity of contract [629]*629existed • between the John Maneely Company and the Government.

The défense made herein is, first, that there is no privity of contract between the United States and the plaintiff, who was a subcontractor; and second, that in any event the statute of limitations has run against the claim.

Considering the point first named, it will be observed that the contract gave the contracting officer the right to abandon the work and terminate the contract, but in such case made the contracting officer liable for such unliquidated claims as the contractor may have in good faith incurred in connection with the work. The contract also provided in substance that when the contracting officer conformed to the provisions above stated the United States should be discharged from all claims on the part of the contractor. See Finding III. These provisions clearly constituted a promise for the benefit of the plaintiff, for although plaintiff was not named in the contract, it held an unliquidated claim at the time the contract was terminated. It is a well-settled rule that a party may maintain a suit on a promise made to another for his benefit. Hendrick v. Lindsay, 93 U. S. 143. There are some limitations to this rule, which are well expressed in Vrooman v. Turner, 69 N. Y. 280, as follows:

“ There must be, first, an intent by the promisee to secure some benefit to the third party, and second, some privity between the two, the promisee and the party to be benefited, and some obligation or duty owing from the former to the latter which would give him a legal or equitable claim to the benefit of the promise.”

The facts in the case at bar are clearly covered by the doctrine as above stated. The instant case, however, is not one of novation; that is, it is not a case where for a consideration one promises to pay the debt of another. It is simply a case where A, owing a debt to B, agrees to pay the amount thereof to C, and B, under the provisions of the agreement, is thereupon to have no claim against A. The consideration, of course, is the abandonment by B of the claim which he would otherwise have had. In our opinion the suit is clearly upon a contract made for a valuable consideration, and is one over which this court is given jurisdiction.

[630]*630As before stated, the second point made on behalf of the defendant is that the claim is barred by the statute of limitations, and in support of this claim it is urged that the claim of plaintiff accrued when the pipe was furnished and supplied to the defendant, which was more than six years before the action was commenced.

In order to determine whether the statute had run against plaintiff’s claim, it will be necessary to analyze the contract, which is very loosely drawn and must be interpreted in the light of the surrounding circumstances and the consequent understanding of the parties. From what has already been said, it will be seen that it was what is commonly known as a “ cost-plus contract.” One thing, however, is definitely fixed by the contract and that is that defendant was not to pay whatever cost or price the original contractor might have paid or agreed to pay for material furnished. On the contrary, the amount to be paid, and whether it was to be paid at all, was determined by a provision that the contractor should be reimbursed for “ such of its actual net expenditures in the performance of said work as may be approved or ratified by the contracting officer * * (See Finding III.) This is the only provision with reference to payment and under its terms nothing was due until such ratification or approval took place. Up to that time, the original contractor had no claim against the Government under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FloorPro, Inc. v. United States
98 Fed. Cl. 144 (Federal Claims, 2011)
Kawa v. United States
77 Fed. Cl. 294 (Federal Claims, 2007)
JGB Enterprises, Inc. v. United States
63 Fed. Cl. 319 (Federal Claims, 2004)
Hadden v. United States
130 F. Supp. 401 (Court of Claims, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
68 Ct. Cl. 623, 1929 U.S. Ct. Cl. LEXIS 232, 1929 WL 2450, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maneely-v-united-states-cc-1929.