Marietta Manufacturing Co. v. United States

73 Ct. Cl. 528, 1932 U.S. Ct. Cl. LEXIS 516, 1932 WL 2195
CourtUnited States Court of Claims
DecidedJanuary 18, 1932
DocketNo. E-546
StatusPublished
Cited by2 cases

This text of 73 Ct. Cl. 528 (Marietta Manufacturing Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marietta Manufacturing Co. v. United States, 73 Ct. Cl. 528, 1932 U.S. Ct. Cl. LEXIS 516, 1932 WL 2195 (cc 1932).

Opinion

Williams, Judge,

delivered the opinion:

The plaintiff and the United States, represented by the Director General of Railroads, entered into two contracts, dated November 8, 1918, and November 9, 1918, known as L. M. R. 4-8 and 4-9, in each of which the plaintiff agreed to construct and deliver to the defendant two twin-screw tunnel towboats. The two contracts are identical in provisions, except as to dates.

The plaintiff in this suit seeks to recover on three separate claims aggregating $45,594.94, alleged to be due it under the contract. The first and second of its claims, amounting to $18,949.59, are conceded by the defendant to be due the plaintiff, and need not be discussed.

The third claim, known in the record as the claim for “ excess steel,” amounting to $26,645.35, is the only contested claim arising under these contracts.

The plaintiff’s bid was made in response to a letter from an authorized representative of the defendant, in which the general dimensions of the boats were given, and a statement was made to the effect that the amount of steel required in each boat would be, approximately, plates 430,000 pounds, shapes 240,000 pounds, and rivets 50,000 pounds. The plaintiff prior to making its bid conferred with naval architects of the Government in reference to the amount off steel that Avould be required in each boat and was assured that the amount would be approximately that stated in the letter received by plaintiff inviting its bid.

The contract provided that the plaintiff would build the boats for $360,000 each, half to be allocated to the hull and [541]*541half to machinery installation. The controversy in suit arises under the provision for the payment of hull construction, which reads:

“ Payments on account of hull construction, total amount one hundred eighty thousand dollars ($180,000), less the estimated cost of steel, twenty-three thousand five hundred dollars ($23,500) for each towboat.
“ The Director General agrees to furnish to the contractor at the point of purchase by the Director General such steel material as he shall be directed by the contractor to furnish, at the price and in the amounts and at the times substantially as shown in the schedule marked ‘ Specifications for the Construction of a Twin Screw Steel Tunnel Towboat for Mississippi Eiver, Addition No. 2 to Contract,’ which is hereto attached and hereby made a part hereof, as fully as though set forth herein. * * * For the purpose of computing the amounts to be paid by the Director General direct to the contractor in advance of completion of the towboats herein referred to, the deduction from the purchase price for the estimated cost of such steel is figured at twenty-three thousand five hundred dollars ($23,500) for each towboat.”

The contract provided that the Director General should furnish the steel required in the construction of the boats at prices fixed by the American Iron and Steel Institute, as of October 1, 1918, and that the prices so fixed should be deducted from the contract price of the boats.

Addition No. 2 to the contract, referred to above, showed the steel required in the construction of each boat, consisting of plates, shapes, flats, and rounds, exclusive of rivets, to be 338 short tons. Upon the basis of prices as of October 1, 1918, the cost of steel, which it was estimated would complete the boats, and which the defendant had a right to deduct from the purchase price was $23,500.

It became evident soon after the plaintiff started the construction of the boats that 338 short tons of steel were wholly inadequate for completion of the boats in accordance with the plans and specifications, and the 'many changes in design, made from time to time by the defendant as the work progressed. It was soon found, also, that it was more convenient and more expeditious for the plaintiff to buy certain of the steel direct, than to have it furnished by the Govern[542]*542ment, and the naval architects authorized the plaintiff, subject to certain restrictions, to buy a part of the steel required direct. Pursuant to the authorization, plaintiff purchased and paid for large amounts of steel. In view of the enormous increase in the amount of steel necessary to complete the boats, over that estimated in the contract, and the heavy financial burden which the direct purchase of large amounts of steel imposed on it, the plaintiff entered into negotiations with the defendant looking to an adjustment of the matter. At a conference held on August 17, 1920, the-matter of the excess steel required in the construction of the boats, and numerous other matters not involved in this suit, were discussed by plaintiff and representatives of the Government. As a result of these negotiations an agreement, was reached by the parties as to the excess steel, which agreement is referred to in the record as the supplemental agreement, the pertinent provisions of which are:

“Addition No. 2 to contract calls for 338 tons of steel invoice weight. It is ascertained that to complete the boats on the above contract, 559 tons of steel will be required, the excess steel 221 tons requiring 16.6 tons of rivets. On the total excess steel and rivets you will be allowed additional compensation at the rate of $264 per ton, less the value of the scrap on excess steel, or a total of $62,284.20 per boat and for the contract $124,568.80.”

The amount of steel required and actually used in the construction of the boats was 582.62 tons per boat, or 23.62 tons; per boat in excess of the 559 tons “ ascertained ” to be required in the supplemental agreement of August 17. The cost to the plaintiff of installing this excess steel, together with rivets, in the four boats covered by the contract, after deducting the proper allowance for scrap, was $26,645.35.

The issue for decision is the plaintiff’s right to recover this amount. Determination of the question involved hinges on the construction and meaning of the supplemental agreement of August 17. Was this agreement, as the Government contends, a lump-sum settlement for any and all steel which might be required in the construction of the boats, or did it, as the plaintiff contends, merely fix the price of excess steel [543]*543required to complete the boats over the amount estimated in the original contracts, and provide for the payment of such excess up to 559 tons per boat ?

We think the supplemental agreement should be construed in the light of the negotiations leading up to it, the circumstances and facts surrounding its execution, and the results sought to be attained by the respective parties at the conference when the agreement was reached. It is clear that at the time the original contracts were entered into neither the Government nor the plaintiff had even approximate knowledge of the amount of steel that would be required in the construction of the boats. Certainly the plaintiff had no knowledge of the amount that would be required, and had to rely wholly upon estimates furnished by the Government. The plaintiff’s bid was predicated upon the Government’s representation that 338 tons of steel would be used in the construction of the boats. This representation was grossly inaccurate and misleading.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flour Mills of America, Inc. v. United States
72 F. Supp. 603 (Court of Claims, 1947)
Chippewa Indians v. United States
80 Ct. Cl. 410 (Court of Claims, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
73 Ct. Cl. 528, 1932 U.S. Ct. Cl. LEXIS 516, 1932 WL 2195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marietta-manufacturing-co-v-united-states-cc-1932.