Murphy v. City of Albina

29 P. 353, 22 Or. 106, 1892 Ore. LEXIS 34
CourtOregon Supreme Court
DecidedMarch 4, 1892
StatusPublished
Cited by14 cases

This text of 29 P. 353 (Murphy v. City of Albina) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murphy v. City of Albina, 29 P. 353, 22 Or. 106, 1892 Ore. LEXIS 34 (Or. 1892).

Opinion

Bean, J.

This is an action to recover on a quantum meruit for work and labor alleged to have been performed by plaintiff, in grading, cutting, and filling one of defendant’s streets, known as Margaretta avenue. This is the second appeal in this case. For the purposes of this appeal, the facts sufficiently appear in the case as reported (20 Or. 379), except from this record it appears that plaintiff by his written contract was to grade Margaretta avenue, a public street of the defendant, to the grade established by the city, as surveyed and established by Hulbert & McQuinn, and according to a profile made by them and made a part of the contract, the work to be done under the supervision of the committee on streets and public property, who should furnish the contractor with all necessary heights and distances, for which work he was to receive, on the approval in writing of the committee on streets and public property and engineer in charge, a certain rate per cubic yard for [107]*107all necessary excavations and fills made by him, reference being made to a tracing made by the engineer in charge as to the number of yards of excavation or fill required.

The evidence tended to show that plaintiff proceeded to perform his contract, the engineer in charge setting stakes along the line of the.work, giving the height as established by the defendant and provided in the contract. After he had finished grading according to the stakes set by the engineer, and was ready for laying sidewalk and planking, the engineer made a change in the grade stakes of from three to ten inches of a rise in the grade, the entire length of the street, and directed plaintiff to bring the surface of the street up to this line. Plaintiff complained to the mayor and two members of the council of the action of the engineer in changing the grade, and was by the mayor told “to go ahead and finish his work according to the engineer’s instructions, and quit his complaining or he would not get paid for his work, or something to that effect”; that he did finish the work according to the instructions of the engineer, and was compelled to do four hundred and sixty-six dollars and twenty cents worth of work more than called for in his contract and the estimates accompanying the same; that he told one member of the council and the mayor that if they did not rectify the mistake there would be damages claimed, and on the day the street committee was examining the work after its completion he told them he should sue defendant for damages; that after the work was completed, the defendant accepted and paid for all the work provided in the contract, but refused to pay for any extra work as ordered by the engineer. It does not appear that the council as an official body authorized or assented to the change in the contract or street grade by the engineer, or directly ratified the same; nor does it appear that the common council directed or had knowledge that the plaintiff was doing the extra work, or knew that it had been done at the time the [108]*108work under the contract was accepted, unless it might be inferred from the fact that the mayor and two members, of the council knew of the change in the grade, and the mayor directed the work, and a majority of the individual members of the council knew that plaintiff threatened to make some claim for compensation for the extra work ordered by the engineer.

The errors complained of are in the giving and refusal of certain instructions by the trial court. The instruction requested by plaintiff and refused by the court, the refusal of which we held to be an error on the former appeal, to the effect that if the extra work was ordered by the engineer and performed by plaintiff under the direction of the mayor and two members of the council, and the city, acting through its proper officers, accepted the same, the defendant is liable, was in substance given in the general charge, the court adding an explanation in the opinion proper and necessary to a clear understanding by the jury, as to who are the proper officers and how they must act in order to hind the city, and therefore requires no further consideration here. On this point the former decision was, that if the work was performed in improving the streets of defendant without regular authority, by direction of some person assuming to act for it, and was afterwards accepted by defendant, this would be a ratification and equivalent to an original authority. But as to what would constitute an acceptance of the work, was not in the case, nor considered or decided by the court. The record then before us showed “that when said work (extra work) was completed, as ordered by the city surveyor, the same was accepted by the city of Albina,” so that the only question was, whether under such a state of facts the city was liable for the reasonable value of the work.

But on the second trial the question of acceptance was the vital point in the case, and it was therefore proper and necessary for the court to instruct the jury fully upon this [109]*109question, and the instruction as requested by plaintiff furnished no guide for the. jury as to who are the proper officers of the city, and as to what would amount to an acceptance of the work. It follows therefore that this case must depend upon the correctness of the instructions as given by the court, i’he jury was instructed in effect, that in order for plaintiff to recover, it must appear that there was work done by plaintiff outside of his contract, at the request and with the knowledge of a majority of the members of the council, and that plaintiff made claim for the extra work, and the council, as an official body, recognized the claim and accepted the work, and that conversations with individual members of the council on the street would not amount to a contract or acceptance of the work, but in order to bind the city the council must have been together, acting as a body; and that if plaintiff did perform work outside of his contract, and the council simply undertook to accept the completion of the contract and pay what was earned under it, the city would not be liable for any extra work, although the members of the council may have been informed on the street as individuals that plaintiff claimed something for extra work. Certainly the defendant is not liable if it did not as a municipal corporation contract with or in any way authorize the plaintiff to do the extra work necessary to bring the street up to the grade established by its engineer, or by some corporate act ratify the contract or accept the work. Though it may be charged with the duty of regulating and repairing the streets, undoubtedly no action will lie against it for work or labor put upon them without its assent or authority. There is no room here for the contention that the defendant in any way contracted with or authorized plaintiff to perform this extra work. The only contract it made with him was the written one which provided expressly that the work should be done according to the grade as established by Hulbert & McQuinn. The provision in the contract, that the work [110]*110should be done under the supervision of the committee on streets and the engineer in charge, conferred no authority upon either of them to change or modify in any essential particular the provisions of the contract. (Bonesteel v. New York, 22 N. Y. 162; Rens v. Grand Rapids, 73 Mich. 237; Dillon v. Syracuse, 9 N. Y. Sapp. 98; Genovese v. Mayor, 55 N. Y. Superior, 397.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Helberg v. Civil Service Commission
498 P.2d 789 (Court of Appeals of Oregon, 1972)
State Ex Rel. Hjelle v. Bakke
117 N.W.2d 689 (North Dakota Supreme Court, 1962)
T.S.C. Motor Freight Lines, Inc. v. United States
186 F. Supp. 777 (S.D. Texas, 1960)
Webster v. Texas & Pacific Motor Transport Co.
166 S.W.2d 75 (Texas Supreme Court, 1942)
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1942
Johnson v. Ladd
24 P.2d 17 (Oregon Supreme Court, 1933)
Phez Co. v. Salem Fruit Union
233 P. 547 (Oregon Supreme Court, 1924)
Williams v. Inhabitants of Vinalhaven
124 A. 213 (Supreme Judicial Court of Maine, 1924)
Reed v. Hollister
212 P. 367 (Oregon Supreme Court, 1923)
State ex rel. Lemke v. Union Light, Heat, & Power Co.
182 N.W. 539 (North Dakota Supreme Court, 1921)
Taggart v. School District No. 1
188 P. 908 (Oregon Supreme Court, 1920)
Seaweard v. First Nat. Bank
165 P. 232 (Oregon Supreme Court, 1917)
Steiner v. Polk County
66 P. 707 (Oregon Supreme Court, 1901)
Abells v. City of Syracuse
7 A.D. 501 (Appellate Division of the Supreme Court of New York, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
29 P. 353, 22 Or. 106, 1892 Ore. LEXIS 34, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murphy-v-city-of-albina-or-1892.