Abells v. City of Syracuse

7 A.D. 501, 40 N.Y.S. 233
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 1, 1896
StatusPublished
Cited by22 cases

This text of 7 A.D. 501 (Abells v. City of Syracuse) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abells v. City of Syracuse, 7 A.D. 501, 40 N.Y.S. 233 (N.Y. Ct. App. 1896).

Opinions

Ward, J.:

The complaint in this action, alleged that a firm, Abells & Strong, in June, 1893, entered into a contract with the defendant (the city [503]*503of Syracuse), whereby it was agreed that Abells & Strong should grade Boyden street in that city from line to line, from Pattison street to Teall avenue, according to specifications made, for which grading, labor and materials furnished by them the defendant agreed to pay thirty-three cents per cubic -yard for all excavations, and thirty-three cents per cubic yard for all embankments — such payment to be made as the work progressed, upon estimates to be made by the commissioner of public works of the city, which estimates were required to be made monthly after the commencement of the work, the said defendant being allowed to retain of the moneys payable on the contract the sum of ten per cent for a period of six months after completion. The complaint further alleged that the contractors entered upon the performance of the contract, and that during the progress of. the said work it became necessary to build a stone wall as a retaining wall to properly grade said street, and that, defendant, through its officers and agents, being duly authorized, directed the said Abells & Strong, and employed them, to furnish material, excavate and build said wall, which the said Abells & Strong did, and that the labor and materials so furnished and performed were reasonably worth the sum of $913.63, which sum the defendant promised to pay, etc., and which became due and payable before the action was commenced.

The complaint alleged, also, that there was due the plaintiff, by reason of the premises, the sum of $1,604.99, with interest from July 6, 1894. The cause of action was assigned before the commencement of this action by the contractors to this plaintiff.

The defendant’s answer put in issue the matter in controversy m the action.

The firm of Abells & Strong, pursuant to a notice duly advertised, issued by the common council of the defendant, dated June 26, 1893, for proposals to grade Boyden street, from Pattison street to Teall avenue, on the 3d of July, 1893, filed with the city a bid to construct the work for the price stated in the complaint, and further provided “ for all extra work done by written order of the Commissioner of Public Works — its actual reasonable cost to the contractor, as determined by the Commissioner, plus fifteen per cent of said cost.” This bid was accepted by the city,' and the contract was entered into between the parties in writing for the work in July, [504]*5041893, pursuant to bid. This contract provided, among other things, that the work should be carried on as directed by the commissioner of public works of the defendant, and further provided that the engineer of the city could make alterations in the line and grade, and the commissioner of public works in place, form, position, dimension or material of the work before or after the commencement of the construction. If such alteration diminished the quantity of work to be done no- claim should arise to the contractors for anticipated profits; but if the alteration increased the amount of work, .such increase, should be paid for according to the quantity actually done, and “ at the price established .for such work under the contract, or, in case there is no price established, it should be paid for at its actual reasonable cost, as determined by the Commissioner; ” and that all extra .work should be done by written .order of the conunis-' sioner. The contract also provided that when an embankment was made it should at the top be of the width of the street from line to line, and the sides should be sloping and formed of earth of such a slope as to properly support the embankment. The work proceeded under the direction of the engineer and with the knowledge of the commissioner of public works, who, being out of health, substantially relegated his duties in the premises to the engineer.

These officers under the city charter were the proper officers to represent the city in this work. In the progress of the work a fill became necessary along the side of the street, 'varying from three to twelve and fifteen feet in height; so that, in attempting to perform" the contract) it was discovered that if the top of the embankment was of the width of the street, the toe of the embankment riiust necessarily extend over the premises of abutting owners sufficiently to support the embankment with the earth slope required by the contract. If the fill was fifteen feet deep, the toe of the bank would be thirty feet upon the adjoining owners’ property. The adjoining owners refused to permit any portion of the embankment upon their premises and forbade it. An emergency, therefore, suddenly arose which neither of the parties seemed to have contemplated when the contract was made, and to persist in the performance-of the contract would render all concerned liable as trespassers and the work would probably be stopped. . The only way out of the difficulty was, therefore, to construct a vertical wall. [505]*505commencing at the line of the street instead of the sloping embankment, which would involve an exji.enditure not contemplated by the parties when the contract was executed. The city engineer, with the knowledge and consent of the commissioner of public works, verbally directed the contractors to construct this wall, which was done at an expense of $913. There were 37 yards of excavation for the foundation, which, at 33 cents per cubic yard, amounted to $28.71, and there were laid 81 cords of stone wall, amounting to $884.92. Monthly estimates were made ón this contract, and the commissioner of public works certified in writing to the correctness of the claim for the construction of this wall, and also in another monthly estimate recognized in writing the propriety of this work. The common council accepted the estimate of October 23, 1893, made by the engineer, acting for and in the name of the commissioner, which embraced $550 for the stone work, and ordered it paid. This was done; but subsequently the common council ordered the commissioner of public works to make a final estimate or account, omitting the said extra work and making a statement that there was finally due the contractors on the contract but $792.36; and the common council also adopted a resolution that the stone wall was built without proper authority and the city was not liable.

The city engineer was the only witness sworn. ' He testified that the work was necessary, in order to carry out the contract, to build this vertical wall, and that it was extra work. The trial court found that it was extra work, and that the city, with full knowledge of the situation, had ratified the act of the city engineer acting for the commissioner of public works in ordering the extra work, by paying for a part thereof, recognizing it as valid and accepting the work as performed; that the extra work was worth the amount claimed therefor by the plaintiff; that, during the progress of the work, it became necessary to build the wall as a retaining wall to properly support the earth drawn upon the street for the purpose of making the fill and in order to protect the property of adjoining owners; and that the defendant, through the city engineer arid the commissioner of public works, authorized and directed the contract 'ors to build the said wall. These findings are sustained by the evidence The work was not only necessary and proper, but it was performed [506]*506in good faith.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Syrtel Building, Inc. v. City of Syracuse
78 Misc. 2d 780 (New York Supreme Court, 1974)
McKay Construction Co. v. Board of Education
33 A.D.2d 862 (Appellate Division of the Supreme Court of New York, 1969)
Amadeus, Inc. v. State
55 Misc. 2d 27 (New York State Court of Claims, 1967)
Joseph F. Egan, Inc. v. City of New York
215 N.E.2d 490 (New York Court of Appeals, 1966)
Joseph F. Egan, Inc. v. City of New York
18 A.D.2d 357 (Appellate Division of the Supreme Court of New York, 1963)
Ridgemont Development Co. v. City of East Detroit
100 N.W.2d 301 (Michigan Supreme Court, 1960)
City of New York v. National Dredging Co.
254 A.D. 530 (Appellate Division of the Supreme Court of New York, 1938)
General Valuations Co. v. City of Niagara Falls
253 A.D. 156 (Appellate Division of the Supreme Court of New York, 1938)
Vandeweghe v. City of New York
150 Misc. 815 (New York Supreme Court, 1934)
Bavin & Burch Co. v. Bard
255 P. 200 (California Court of Appeal, 1927)
Vermeule v. City of Corning
186 A.D. 206 (Appellate Division of the Supreme Court of New York, 1919)
Atlantic City v. Warren Bros.
226 F. 372 (Third Circuit, 1915)
Trustees of Village of Bath v. McBride
163 A.D. 714 (Appellate Division of the Supreme Court of New York, 1914)
New York Central & Hudson River Railroad v. City of Buffalo
85 Misc. 78 (New York Supreme Court, 1914)
Village of Fredonia v. Fredonia Natural Gas Light Co.
84 Misc. 150 (New York Supreme Court, 1914)
Van Arsdale v. Justice
75 Misc. 495 (New York Supreme Court, 1912)
Peters v. Justice
75 Misc. 504 (New York Supreme Court, 1912)
Dady v. City of New York
65 Misc. 382 (New York Supreme Court, 1909)
Greenberg v. Mendelson
49 Misc. 485 (Appellate Terms of the Supreme Court of New York, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
7 A.D. 501, 40 N.Y.S. 233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abells-v-city-of-syracuse-nyappdiv-1896.