Bavin & Burch Co. v. Bard

255 P. 200, 81 Cal. App. 722, 1927 Cal. App. LEXIS 859
CourtCalifornia Court of Appeal
DecidedMarch 15, 1927
DocketDocket No. 5305.
StatusPublished
Cited by8 cases

This text of 255 P. 200 (Bavin & Burch Co. v. Bard) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bavin & Burch Co. v. Bard, 255 P. 200, 81 Cal. App. 722, 1927 Cal. App. LEXIS 859 (Cal. Ct. App. 1927).

Opinion

PARKER, J., pro tem.

In this action plaintiff sues to recover on an express contract for work and labor performed for, and materials furnished to, defendants. It seeks, further, to enforce a claim of lien against the premises benefited by such labor and materials. Judgment went for plaintiff against defendants and the case comes here on appeal by defendants.

The defendants Bard and Berkowitz are lessees of the premises owned by the remaining defendants, and the judgment was against the said lessees only, with decree foreclosing the lien.

There is no question presented involving the procedure as to the lien as separate from the judgment, nor is there any controversy as to the rights of the defendants in their separate capacities as owners or lessees. The questions raised concern the judgment; and for the purposes hereof *725 it will be deemed that if the judgment should be affirmed, in whole or in part, the lien follows.

Plaintiff and defendants (Bard and Berkowitz) entered into a written contract, wherein the said defendants were described as owners and the plaintiff as contractor. The dispute between the parties involves certain charges made for extras under the contract. The original work specified was duly performed and the price paid, and no controversy is presented as to such work or payment. It may be stated that the contract was quite general in its terms, and consists of an agreement, plans, specifications, drawings, and an addenda to the specifications. Prom none of these does it appear precisely what was to be done under the original undertaking. This may be due merely to the absence of the drawings, and possibly by reason of the fact that the questions here for determination do not require such detail. The general purpose of the contract was the renovation and alteration of the premises in order to convert the existing building into a moving-picture theater. In studying the original agreement it seems obvious, and the case as a whole supports the conclusion, that the parties were not informed as to exactly what might be necessary to secure the result desired, as would appear in part from a provision of the contract as follows: “Should the owners at any time during the progress of work require any alterations, deviations from, additions to or omissions from the contract, or the drawings or specifications, they shall be at liberty to do so, and the same shall in no way affect or make void this contract, but the amount thereof shall be added to or deducted from the amount of the contract price as the same may be by fair and reasonable valuation.”

The claim of plaintiff, and upon which the trial court predicated its judgment, embraces some thirty items for extras in the way of labor and materials. Without giving the items in detail they were referred to throughout the records as orders, and they may be divided into three groups, as follows: Orders 1 to 5, inclusive; orders 6 to 26, inclusive (incidentally, here it may be noted that there was no order 25); orders 28, 29, 30. Plaintiff recovered judgment for the sum of five thousand eight hundred and eighty-two dollars and thirty-nine cents ($5,882.39).

The argument of appellants is as follows:

*726 First—Lack of written orders for various items of extra work.

Second—Extras caused by reason of plaintiff’s failure to comply with, requirements of city building department.

Third—Items charged as extras which were provided for in original contract.

Fourth—Failure of evidence to sustain findings on certain items.

Fifth—Failure of court to allow credit for items omitted from original contract.

Sixth—Set-off claimed as damages for delay in completion.

(1) Lack of written orders.

Necessarily of controlling importance here are the terms of the contract. In the contract it is provided: “No changes or modifications from the plans and specifications will be permitted excepting upon written permission from the architect, and the cost of any such change, whether a deduction or extra, must be agreed upon in writing before the same is started. The architect reserves the right to make any such changes or deviations without in any way invalidating the contract or bond.”

The facts as disclosed by the evidence are that it was the practice of the architect to visit the work at frequent intervals and go over the requirements with the contractor. When there appeared the necessity for any particular item agreed upon as an extra the architect would orally direct the contractor to proceed and the price would be fixed. Thereafter a written order would follow. With the exception of orders 2'8, 29, and 30 the contractor did receive a written order from the architect for every item claimed as extra work, and in each instance the order was received before the work was completed. As to the items excepted there were no written orders. The testimony regarding orders 6-26 is not at all clear. All that appears concerning these is the statement that these orders were prepared by the contractor and left at the office of the architect, and that they would usually lay around for a week or so, and that the work on some of the items was commenced before the orders were actually received.

The provision in the contract requiring the written order of the architect and agreement as to price is a provision designed for the protection of the owner and *727 is to be construed in his favor. Courts generally have held this provision in a building contract as valid and binding, and have further held that without compliance therewith by the contractor the owner cannot be charged for extra work. The California cases are in accord with the general rule (Gray v. La Societe Francaise, 131 Cal. 566, 569 [63 Pac. 848]; White v. San Rafael & S. Q. R. R. Co., 50 Cal. 417]). Indeed, in almost every jurisdiction the rule is accepted, though in some courts a tendency has developed to modify the strictness of the rule by declaring a waiver when benefits have been accepted and retained. The purpose of a provision of this sort in a contract is" to protect the owner from unnecessary or unwarranted expense and to assure him that there will be some limit to his outlay. The average person desiring to construct a home or other building would be wholly at the mercy of his architect and contractor if the courts were to hold such a provision ineffectual for any purpose. No harm can come to the contractor nor can any loss or damage ensue to him by a strict enforcement of a provision of this character. He has his contract, and is bound only by the provisions thereof. He is not obliged to do anything extra without the written order, and knows that if he does he must speculate upon the owner’s pleasure as far as payment is concerned. We are called upon to determine whether or not this provision in the present contract has been met.

Appellants concede that the labor for which payment is sought was actually performed and that likewise the materials were supplied. They accept the finding of the court that the charge was reasonable, and the record discloses that the benefits of the labor and material have accrued to the premises.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Connersville Country Club v. F. N. Bunzendahl, Inc.
222 N.E.2d 417 (Indiana Court of Appeals, 1967)
C. F. Bolster Co. v. J. C. Boespflug Construction Co.
334 P.2d 247 (California Court of Appeal, 1959)
Wilson v. Keefe
309 P.2d 516 (California Court of Appeal, 1957)
United States ex rel. T. M. Page Corp. v. Hensler
125 F. Supp. 887 (S.D. California, 1954)
Opdyke & Butler v. Silver
245 P.2d 306 (California Court of Appeal, 1952)
Division of Labor Law Enforcement v. Ryan Aeronautical Co.
236 P.2d 236 (California Court of Appeal, 1951)
Roscoe Moss Co. v. Jenkins
130 P.2d 477 (California Court of Appeal, 1942)
Cavanagh v. Keplinger
266 P. 287 (California Supreme Court, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
255 P. 200, 81 Cal. App. 722, 1927 Cal. App. LEXIS 859, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bavin-burch-co-v-bard-calctapp-1927.