United States ex rel. T. M. Page Corp. v. Hensler

125 F. Supp. 887, 1954 U.S. Dist. LEXIS 2788
CourtDistrict Court, S.D. California
DecidedNovember 19, 1954
DocketNo. 15695
StatusPublished
Cited by2 cases

This text of 125 F. Supp. 887 (United States ex rel. T. M. Page Corp. v. Hensler) is published on Counsel Stack Legal Research, covering District Court, S.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. T. M. Page Corp. v. Hensler, 125 F. Supp. 887, 1954 U.S. Dist. LEXIS 2788 (S.D. Cal. 1954).

Opinion

JAMES M. CARTER, District Judge.

This is an action within the jurisdiction of this court, pursuant to the provisions of the Miller Act, 40 U.S.C.A. §§ 270a and 270b, and concerns the claim of a subcontractor against the prime contractor and his insurance carrier in connection with work at the Naval Air station at Mojave.

Because much of the case concerned accounting as to yardage of earth processed, the matter was referred to a Master, who conducted lengthy hearings and has filed his report and recommendations and findings of fact and conclusions of law. The matter comes before this court on motion to approve the Master’s findings and conclusions of law, and objections thereto.

The defendant Hensler had a prime contract with the Department of the Navy, Bureau of Yards and Docks, for the reconstruction of an extension of runways at the Mojave Air Station, for the lump sum of $1,307,000, executed on August 20, 1951. On August 23, 1951, Hensler entered into a written subcontract with the use plaintiff T. M. Page Corporation, hereinafter referred to as the plaintiff, for the performance of certain portions of the work required to be performed under the prime contract, generally consisting of earth work, reconstruction of existing base runways and pavement to form a sub-base and certain clearing activities. The subcontract called for the processing of approximately 226,100 cubic yards of earth for a price of $104,006. This figured 46 cents per cubic yard. The contract also provided, “any change in quantity is to be charged or credited at forty-six cents (.46) per cubic yard, measured in excavation [cut]”. This part of the subcontract is ordinarily referred to as a unit price contract. In addition, the subcontract provided for the payment of the sum of $20,400 for “clearing” certain of the area involved.

Certain matters are not in dispute. The Master, found, and the parties concede that as part of the work performed by plaintiff, 241,715 cubic yards have been processed by the plaintiff, and have been paid for by defendant at 46 cents per yard. In addition, 2,038.1 additional cubic yards have been likewise processed by the plaintiff, and there is no serious contention as to the Master’s findings in this respect. At 46 cents per cubic yard, this amounts to $937.53. It is likewise not in dispute and found by the Master that the defendant on one occasion overpaid the plaintiff by $1,000. These two items leave a balance of $67.47 due the defendant and not in dispute herein.

The Master has also found that the plaintiff is entitled to $20,400 for [889]*889the clearing. Although there is serious contention by the defendant as to its liability for this item, it is included in the subcontract. The record shows the work was done and the set-off credit claimed by the defendant was for sums assertedly due under a separate equipment rental agreement. The Master has found that the equipment was never furnished to the plaintiff or used by him, and that it was never in the contemplation of the parties' that the equipment was to be so furnished or used. The Master’s findings are clearly correct, and this portion of his findings are approved.

The real controversy in the case concerns additional earth processed, and hinges around the events prior to and after a change-order made in the prime contract between the Navy department, the principal, and Hensler, the prime contractor, defendant herein. Both parties conceded in the hearing before this court, and the Master found, that in the course of attempting to comply with the contract and subcontract in compacting the soil at the designed subgrade, to 95'% maximum density, an unexpected and unanticipated soil condition was encountered, which made compaction impossible in the manner provided for by the prime contract, and the plans and specifications carried over by reference into the subcontract. It was also conceded that the Navy department agreed that such an unexpected and unanticipated situation existed and that it was not covered by the prime contract.

The Navy department was notified and negotiations ensued. Shortly prior to March 28, 1952, the change order was negotiated, although it was not issued and was not effective until May 20, 1952. It was referred to as Change Order D, and consisted of twenty-one separate items running from (A) to (U) inclusive, only one of which, item (L) possibly concerned the subcontract or the plaintiff subcontractor. Item (L) in the change order added $76,000 to .the figure of the prime contract and in the change order reads, “remove any unsatisfactory material and replace with pit-run material —38,000 cubic yards at $76,000.”

Excavations Below Subgrade Line Prior to Change Order.

Prior to the negotiation of this change order in March of 1952 (executed on May 20, 1952), plaintiff had processed considerable earth in connection with the unsuitable and unexpected materials that were encountered. The Master found 61,625 cubic yards were so processed and both parties at the proceedings before this court conceded this was a correct determination. Plaintiff’s first amended complaint as further amended, alleges that 53,895 cubic yards were processed. However, there are other blanket allegations of processing of additional yardage without segregating them to ordinary performance of the subcontract, or to the performance of work on the so-called unsuitable material, that brings the yardage claimed by the plaintiff to well above any amounts found by the Master and conceded by the parties.

In obtaining the required compaction in the areas where the unsuitable material was encountered, it was necessary for the subcontractor to excavate and fill 12 to 16 inches below the designed sub-grade of the contracts and to mix, manipulate and water the material as it was replaced in 3-inch to 4-ineh layers. Section 3-09 (b) of the specifications provided in part, “excavation shall be carried on to such depth that sufficient material will be left above the designated grade to allow for compaction to the required grade. Any soft and unsuitable material and other portions of the sub-grade or finished grade that will not compact readily shall be removed as directed.”

In view of the unsuitable material discovered, which subsequently was indicated by Navy laboratory tests to be some unidentified, floury material, it was not possible to compact the material in place. The problem was encountered shortly after work was commenced on the contract in August of 1951. The [890]*890problem was discussed on many occasions between plaintiff, defendant and Navy representatives on the job. Heavy equipment was brought in and tried out. Finally it was found that the only successful method was to excavate below the subgrade line in many areas to the full depth of the required compaction of 12 inches. It was only by removing the material to this depth, mixing it elsewhere with other material and replacing the mixed materials in 3-inch and 4-inch layers, that the required density of compaction was obtained. Even by these methods compaction had failed in some areas.

The matter was officially brought to the attention of the Navy by the defendant in a letter dated November 27, 1951, asking for a change order. On February 21, 1952, defendant again claimed the right to a change order, relying on Article 4B of the prime contract, which read in part, “provided that in the case of subsurface latent or unknown conditions this contract may be modified.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Death Row Records, Inc. (In Re Brown)
219 B.R. 373 (E.D. Pennsylvania, 1998)
United States ex rel. Soda v. Montgomery
152 F. Supp. 309 (M.D. Pennsylvania, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
125 F. Supp. 887, 1954 U.S. Dist. LEXIS 2788, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-t-m-page-corp-v-hensler-casd-1954.