Bowman v. Maryland Casualty Co.

263 P. 826, 88 Cal. App. 481, 1928 Cal. App. LEXIS 323
CourtCalifornia Court of Appeal
DecidedJanuary 20, 1928
DocketDocket No. 5977.
StatusPublished
Cited by7 cases

This text of 263 P. 826 (Bowman v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bowman v. Maryland Casualty Co., 263 P. 826, 88 Cal. App. 481, 1928 Cal. App. LEXIS 323 (Cal. Ct. App. 1928).

Opinion

KOFORD, P. J.

This was an action brought by Bowman, plaintiff, the owner, against defendant Newcomb, the tractor, and defendant Maryland Casualty Company, surety company, upon the faithful performance feature of a bond given under Code of Civil Procedure, section 1183, for the construction of the Westinghouse building in the city of Los Angeles. The action was consolidated with many mechanics' liens foreclosure suits. The liens were mined in amount, paid or provided for by the judgment and none of the lien claimants are appellants herein. The judgment determined many points of dispute between the owner and contractor and was in a general way like an accounting between the owner and contractor. The full contract price was $330,000. In the settlement made by the judgment, compensation for extra work and material was allowed to the contractor in the sum of $5,441.66 and deductions from the contract price on account of work and material omitted were allowed in the sum of $15,285.40. These extras and deductions changed the total contract price named in the contract to $320,156.26. The amount of progress payments which had been paid to the contractor at the time of suit was $285,150. The balance of the reduced contract price remaining in the hands of the owner was by the judgment distributed as follows: Allowed to the owner attorneys' fees, $2,500; damages for defective performance of work on front of building, $6,000; damages due to delay in completing the building, $12,041.25; damages for defective performance of work on first floor, $4,000. The balance then remaining in the hands of the owner being $10,465.01, was ordered distributed amongst the lien claimants pro rata. The lien claimants for the unpaid part of their claims were given liens against the owner `s property and judgments against appellant surety company by virtue of the lien feature of the bond.

The points presented bythe appellant on this appeal are as follows: First, it is claimed that the extras and deductions - agreed upon between owner and contractor and in some contractor and in some *485 instances even the breaches of contract by the contractor amounted to such a change of and departure from the terms of the written building contract as to release and discharge the surety from its obligation upon the faithful performance bond. Second, objection to deducting owner’s damages for breaches from the contract balance before all liens were paid oút of that balance. Third, certain objections to the specific items of extras, deductions and damages. Fourth, objection to the allowance by the court of actual damages for delay instead of liquidated damages provided for by the contract.

The main point of appellant is that the extras and deductions verbally agreed upon between the owner and contractor and not in writing as provided for by the written contract, constituted such a change in the contract as to release the surety. This point has been disposed of by the case of Roberts v. Security Trust & Savings Bank, 196 Cal. 557 [238 Pac. 673], which was decided after appellant’s opening brief was filed herein. It was there held that the failure of the owner and contractor to comply with procedural requirements with regard to deductions and extras was not such a change in the contract as would release the surety company on its faithful performance bond. We think the action of the owner and contractor in the instant case in verbally agreeing to the extras and deductions instead of in writing as contemplated by the contract amounts only to a failure to comply with procedural requirements and under the authority referred to does not have the effect of releasing the surety company upon its bond. The building contract, article fourth, and paragraph 22 of the specifications expressly provided for extras and deductions and consequent modification of the total contract price without expressed limit in amount although it also provided that this should be done in writing. The contract in specifying the full contract price also says “$330,000, subject to additions and deductions as herein provided.” Therefore, the building changes were not changes in the contract nor departures from the contract, but, on the contrary, they were expressly contemplated and provided for in the building contract upon which appellant became surety. Such action was only a breach of procedure provided by the contract which consisted of following a different method of doing the things which the contract, provided might be done. In addi *486 tion to this, there is a further reason why such failure to comply with the procedural requirements of the contract does not release the surety. The court expressly found in finding number 53 that it was through no fault or neglect of the owner that such procedural requirements were not followed but was due entirely to the fault and neglect of the contractor. It was not so much a change then as a breach and that breach was made by the contractor of the very contract for the faithful performance of which by him the surety company had agreed to become liable. This finding (number 53) is attacked as being too general and not specific enough to respond to the pleading of appellant. We quote it for this reason and also because of the facts which it sets forth.

“That during the progress of said work in the construction of said building it became necessary to add certain extra work not included in the original plans and specifications; or to omit certain work therefrom; that when said extras or omissions were desired the plaintiff, H. D. Bowman, instructed the contractor, Newcomb, to submit estimates for the price of said extras, or reductions for omissions, some of said instructions being in writing and some of said instructions being oral; that in certain cases said contractor Newcomb submitted prices for proposed extras or deductions before said extra work was commenced or omissions made, and in other instances the extra work was done by said contractor Newcomb for omissions made before he had submitted the price therefor to the plaintiff, H. D. Bowman that the failure of said H. D. Bowman and Earl B. Newcomb to agree upon the price of all or any of said extras or the method of determining the price of all or any of said extras before the said extra work was done or the allowance for omissions, was not caused through any fault or neglect of the plaintiff, H. D. Bowman; that the said H. D. Bowman was at all times ready and willing to take up with the defendant, Earl B. Newcomb, the price of said extras or omissions, but that said Earl B. Newcomb failed and neglected to submit prices or agree upon the manner of determining the price therefor with said H. D. Bowman, but proceeded to complete said extra work or omit work in a number of cases prior to the price therefor or the method of determining the price therefor being fully agreed upon; *487 that said H. D. Bowman and Earl B. Newcomb did not at any time enter into any contract, written or oral, modifying the written contract of March 1st, 1922, or waive any provisions thereof, and that any departure from the method provided in said contract, plans and specifications for the doing of extra work, or omitting work called for by said contract, plans and specifications, was not caused by the fault or neglect of said H. D.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Dwyer
552 A.2d 200 (New Jersey Superior Court App Division, 1989)
United States ex rel. T. M. Page Corp. v. Hensler
125 F. Supp. 887 (S.D. California, 1954)
Warner v. Warner
215 P.2d 20 (California Supreme Court, 1950)
Hammond v. A. J. Bayless Markets, Inc.
117 P.2d 490 (Arizona Supreme Court, 1941)
Mills v. Friedman
5 P.2d 901 (California Court of Appeal, 1931)
Fairbanks v. Crump Irrigation & Supply Co.
291 P. 629 (California Court of Appeal, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
263 P. 826, 88 Cal. App. 481, 1928 Cal. App. LEXIS 323, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bowman-v-maryland-casualty-co-calctapp-1928.