Hanlon Drydock & Shipbuilding Co. v. G. W. McNear, Inc.

232 P. 1002, 70 Cal. App. 204, 1924 Cal. App. LEXIS 46
CourtCalifornia Court of Appeal
DecidedDecember 13, 1924
DocketDocket No. 4716.
StatusPublished
Cited by30 cases

This text of 232 P. 1002 (Hanlon Drydock & Shipbuilding Co. v. G. W. McNear, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hanlon Drydock & Shipbuilding Co. v. G. W. McNear, Inc., 232 P. 1002, 70 Cal. App. 204, 1924 Cal. App. LEXIS 46 (Cal. Ct. App. 1924).

Opinion

KNIGHT, J.

Plaintiff Hanlon Drydoek and Shipbuilding Company, Inc., recovered a judgment against defend *208 ant G. W. McNear, Inc., for the sum of $43,244.45 for repairing an oil tank steamer named “Asuncion.” The defendant has appealed.

Respondent and other shipbuilders were invited to submit bids for the repair of said steamer in accordance with plans and specifications dated August 7, 1920, prepared and written by appellant. On August 12-, 1920, respondent tendered its bid to perform said work in accordance with said plans and specifications for the sum of $37,000 and on the same day its bid was accepted. Respondent agreed to complete said repairs and to redeliver said steamer, in a seaworthy condition, within twenty days. Said specifications contained the following clause: “A penalty of $400.00 a day will be exacted and deducted from the contract price for each day that elapses between the actual completion of the contract and the time specified by contractor in the tender.” On August 21, 1920', the parties made a supplementary contract in writing calling for additional repairs which respondent agreed to make within said period of time for the sum of $7,000. On August 30, 1920, a second supplementary contract was entered into orally between the parties whereby respondent undertood to drydock, clean, and paint said steamer for the reasonable value of the services performed, the work to be completed also within the original twenty-day limit. Said steamer was not ready for redelivery until September 25, 1920, which the court found was twenty-three days in excess of the limitation of time fixed by the contract and for which the court in this action allowed appellant, as provided in the contract, the sum of $400 a day for each day’s delay, making a total deduction of $9,200 from respondent’s entire demand. One of the main contentions made on this appeal is that the trial court should have declared the $400 a day clause of the contract void, as being a “penalty,” and applied the measure of actual damages, which appellant claims amounted to $2,500 a day, making a total of $60,000.

Under the code provisions of this state, a contract which attempts to fix the amount of damages in anticipation ■ of a breach of an obligation is void to that extent (Civ. Code, sec. 1670), but “the parties to a contract may agree therein upon an amount which shall be presumed to be the amount of damage sustained by a breach thereof, when, from the nature of the case, it would be impracticable *209 or extremely difficult to fix the actual damage.'’ (Civ. Code, sec. 1671.) In respondent’s third separate affirmative defense, as amended, to appellant’s cross-complaint are set forth facts showing that, from the nature of the case, it was impracticable and extremely difficult, at the time the contract was made, to fix the actual damage that would result to appellant in the event that said ship was not redelivered within the time limit, all of which the court found, upon abundant evidence, to be true. Briefly stated, the evidence shows in this respect that the contract was made during the post-war period when world trading tonnage was extremely uncertain, and the value of the use of a ship could not be estimated with any degree of exactness from month to month. Evidence was given to that effect by appellant’s witnesses, who testified in substance that owing to fluctuating rates and unsettled shipping conditions, the value of the use of oil tankers or any other vessels could not be prophesied. The “Asuncion” was then nearly twenty years old, which, according to experts, was about the maximum age for efficient service of a tanker. There were no coastal or intercoastal market rates at that time for the use of oil carriers nor were there any such rates to Honolulu or the Orient. Oil companies operating along the coast were employing only their own carriers, so that owners of independent tankers were necessarily compelled to resort to the European trade, which had for its basis vague rates primarily fixed in London, regulated by the law of supply and demand for both oil and tankers and depending upon the extent and route of the voyage called for by the charter-party. The legal status of the parties to this contract was established by conditions existing on August 7, 1920, that being the date of appellant’s specifications, pursuant to which respondent’s bid was invited, tendered, and accepted. On that date appellant was negotiating for the purchase of said tanker from -the Standard Oil Company of California and for a charter-party with the Standard Oil Company of New Jersey, but neither transaction had then been consummated. It would therefore seem quite certain, in view of all of the circumstances, that it was impracticable and extremely difficult when the contract was made to fix the amount of the actual damage that might result in case of breach, and we are satisfied that the evi *210 dence in this regard fully justified the trial court in so finding. In fact, appellant expressly admits “that, at the time the contract was made, it was impracticable to say what defendant’s damage would be in case of subsequent breach and this for the reason that future rates for oil tankers or, indeed, any other vessels could not be foretold. ’ ’ But, appellant contends that proof of those facts alone do not establish a valid case of liquidated damages, for the reason that the question of the impracticability of ascertaining the damages was confined “to the time when the contract between the plaintiff and defendant was entered into and not to the time of the breach or any subsequent time.” In this respect appellant asserts that although it may have been impracticable or extremely difficult at the time the contract was made to fix the amount of actual damage that would result in case of breach, still, actual damages were ascertainable at the time of trial and that therefore the trial court should have ignored the agreement made by the parties for the payment of stipulated damages and allowed actual damages which appellant claims amounted to the sum of $2,500 a day. In other words, appellant’s legal contention is that, if at the time parties enter into a contract, it is, as the statute says, “impracticable or extremely difficult to fix the actual damages” in case of breach, and for that reason, and upon that ground they agree “upon an amount which shall be presumed to be the amount of damages sustained by a breach thereof,” such agreement shall be valid and enforceable only if those conditions continue to remain the same up to and at the time of the breach; but if, for reasons which are unforeseen when the contract was made, conditions change so that when the breach occurs it is then practicable and not difficult to fix actual damages, the agreement of the parties shall be declared unenforceable and void and the rule of actual damages applied.

Appellant concedes that in determining whether a provision in a contract is for liquidated damages, or for a penalty, the fundamental rule, so often announced, is that the construction of these stipulations depends, in each case, upon the intent of the parties, as evidenced by the entire agreement construed in the light of the circumstances under which it was made (Nakagawa v. Okamoto, 164 Cal. 718 [130 Pac. 707]), and that such intent is to be determined “obviously” as appellant says “at the time the contract is entered inte, *211

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reliance Insurance Co. v. Utah Department of Transportation
858 P.2d 1363 (Utah Supreme Court, 1993)
Cook v. King Manor and Convalescent Hospital
40 Cal. App. 3d 782 (California Court of Appeal, 1974)
Bilardi Construction, Inc. v. Spencer
6 Cal. App. 3d 771 (California Court of Appeal, 1970)
Barlan, Inc. v. Reagan
220 Cal. App. 2d 116 (California Court of Appeal, 1963)
Caplan v. Schroeder
364 P.2d 321 (California Supreme Court, 1961)
Claremont Press Publishing Co. v. Barksdale
187 Cal. App. 2d 813 (California Court of Appeal, 1960)
Smith v. Royal Manufacturing Co.
185 Cal. App. 2d 315 (California Court of Appeal, 1960)
Los Angeles City School District v. Landier Investment Co.
177 Cal. App. 2d 744 (California Court of Appeal, 1960)
Thompson v. Goubert
335 P.2d 754 (California Court of Appeal, 1959)
Ricker v. Rombough
120 Cal. App. Supp. 2d 912 (California Court of Appeal, 1953)
Ricker v. Rombough
120 Cal. App. 2d 912 (Appellate Division of the Superior Court of California, 1953)
Better Food Markets, Inc. v. American District Telegraph Co.
253 P.2d 10 (California Supreme Court, 1953)
Bay Shore Motors v. Baker
202 P.2d 865 (California Court of Appeal, 1949)
Associated Press v. Emmett
45 F. Supp. 907 (S.D. California, 1942)
Rice v. Schmid
115 P.2d 498 (California Supreme Court, 1941)
Byron Jackson Co. v. United States
35 F. Supp. 665 (S.D. California, 1940)
Nester v. Western Union Telegraph Co.
25 F. Supp. 478 (S.D. California, 1938)
Six Companies of California v. Joint Highway Dist. No. 13
24 F. Supp. 346 (N.D. California, 1938)
Saunders v. McKee
1936 OK 439 (Supreme Court of Oklahoma, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
232 P. 1002, 70 Cal. App. 204, 1924 Cal. App. LEXIS 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hanlon-drydock-shipbuilding-co-v-g-w-mcnear-inc-calctapp-1924.