Baltimore Bridge Co. v. United Railways & Electric Co.

93 A. 420, 125 Md. 208, 1915 Md. LEXIS 196
CourtCourt of Appeals of Maryland
DecidedFebruary 9, 1915
StatusPublished
Cited by21 cases

This text of 93 A. 420 (Baltimore Bridge Co. v. United Railways & Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baltimore Bridge Co. v. United Railways & Electric Co., 93 A. 420, 125 Md. 208, 1915 Md. LEXIS 196 (Md. 1915).

Opinion

Pattison, J.,

delivered the opinion of the Court.

The appellant, the Baltimore Bridge Company, on the 12th day of April, 1911, entered into a written agreement with the United Railways and Electric Company of Baltimore, the appellee, to do certain work, and furnish the material therefor, upon a viaduct of the appellee company known as the Huntington Avenue Viaduct, in the City of Baltimore, for which it was “to be paid for the full completion of the work: Steel work, $5,845.87; concrete floors, $453.00; concrete foundations or footings, $9.00 per cubic yard.”

*210 By the terms of the contract the work was to be completed “within four months from the date of the agreement, or sooner if possible,” and if not completed at such time the appellee company was authorized to retain as liquidated' damages the sum of twenty-five dollars for each day the work remained unfinished after the date designated for its completion.

The exact wording of the agreement in respect to this provision is that “time shall be of the essence of this agreement, and for each day the completion of the work is delayed beyond the time hereinbefore limited as the time for its completion, the contractor agrees that the company may retain from the final payment to be made hereunder the sum ($25.00) indicated.in Schedule E forming part hereof. It being impossible at the time of entering into this agreement to estimate the substantial damage which will result to the company from such delay, the said sum is agreed upon as the liquidated damages which the company will suffer each day by reason thereof and not as a penalty, any decision or ruling of the Courts to the contrary notwithstanding.”

The work under this agreement was not completed unti] the ninth day of October, 1911, fifty-nine days after the date designated for its completion.

The compensation that was to be paid under the contract for the work done and material furnished, had it been completed at the time named in the agreement, amounted to $6,931.57. Of this amount the appellee company retained, as liquidated damages, $1,475.00, or twenty-five dollars for each of the fifty-nine days the work remained unfinished after the date named in the contract for its completion, and paid the balance ($5,456.57) to the appellant company.

It was to recover the amount so retained by the appellee that the suit in this case was instituted. At the conclusion of the case the Court directed a verdict for the defendant, and upon such verdict a judgment was entered thereon for the defendant. It is from that judgment this appeal is taken.

*211 The work was satisfactorily done, and the inquiry here is, whether the amount stipulated in the agreement to be paid by the appellant in the event of its failure to complete the work within the designated period, is to be regarded as liquidated damages or as a penalty.

It is contended by the appellant that the amount so retained was designed to be, and in fact was, a penalty; while the appellee contends that the sum named was intended to be, and in fact was, liquidated or stipulated damages that were agreed upon at the time -of the execution of the agreement to be retained by it should the appellant company fail to complete the work within the designated period.

It was said by Judge McSherry in Willson v. Mayor and City Council of Baltimore, 83 Md. 210, “Whether a sum named in a contract to be paid by a party in default on its breach is to be considered liquidated damages or merely a penalty is one of the most difficult and perplexing inquiries encountered in the construction of a written instrument. The solution of that question * * * depends in a large measure at least upon the particular facts and circumstances of each separate case. * * * A stipulation to pay a specified sum upon the non-performance of a contract is regarded as a penalty rather than as liquidated damages if the intention of the party as to its effect is at all doubtful or is of equivocal interpretion * * * and where * * * the damages for a breach thereof are easily and exactly ascertainable.

“It is equally well settled that a sum, if it be at all reasonable and is stipulated to be paid as liquidated damages for the breach of a contract, will be regarded as such, and not as a penalty, where from the nature of the covenant the damages arising from its breach • are wholly uncertain and cannot be ascertained upon an issue of fact.” Willson v. Mayor and City Council of Baltimore, supra.

In the case of Geiger v. The Western Md. R. R. Co., 41 Md. 15, our predecessors said: “Where the parties have declared in clear and unambiguous terms that a certain sum shall be paid by way of compensation, upon a breach of the *212 contract, * * * the damages arising from the breach of which are uncertain, and incapable of being ascertained by any fixed pecuniary standard, and especially where the contract provides that the sum so claimed shall be paid as liquidated damages, the sum so fixed and agreed upon will be considered as compensation for damages resulting from the breach, and not as a penalty.” See cases there-cited, also Crawford v. Heatwold (Va.), 34 L. R. A. (N. S.), 587; Stratton v. Fike, 166 Ala. 210; Railroad Co. v. Gaba, 78 Kan. 432; Nilson v. Jonesboro, 57 Ark. 168; Ward v. Hudson River Bldg. Co., 125 N. Y. 230; Barber Asphalt Paving Co. v. City of Wabash, 86 N. E. 1036; Wallace Iron Works v. Monmouth Park Assn. (N. J.), 19 L. R. A. 456.

In the more recent case of the United Surety Co. v. Summers, 110 Md. 95, in which the agreement between Lawrence, a builder and contractor, and Summers, for the furnishing- and erection of the re-enforced concrete work in and about a certain building then in course of erection, provided that in case the work was not completed within seventy working days Lawrence should pay to Summers, the owner, fifty dollars for each day in excess of seventy days occupied in the work, the rule was again stated by Judge Peaece, speaking for the Court and quoting from Ward v. Hudson River Bldg. Co., supra, to he, that “Where the parties have stipulated for a payment in liquidation of damages, which are in their nature uncertain and unascertainahle with exactness, and may he dependent upon extrinsic considerations and circumstances, and the amount is not, on the face of the contract, out of all proportion to the probable loss, it will be treated as liquidated damages.” And the stipulation in that ease was held to be for liquidated damages and' not a penalty. See also cases of Filston Farm v. Henderson, 106 Md. 355; Graham v. Cooper, 119 Md. 358.

In 2 Joyce, Damages,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cas Severn, Inc. v. Awalt
75 A.3d 382 (Court of Special Appeals of Maryland, 2013)
Barrie School v. Patch
933 A.2d 382 (Court of Appeals of Maryland, 2007)
Stroh v. Omni Arabians, Inc.
748 A.2d 1015 (Court of Special Appeals of Maryland, 2000)
United Cable Television of Baltimore Ltd. Partnership v. Burch
732 A.2d 887 (Court of Appeals of Maryland, 1999)
LANDOVER MALL LTD. PARTNERSHIP v. Kinney Shoe Corp.
944 F. Supp. 443 (D. Maryland, 1996)
Schrier v. Beltway Alarm Co.
533 A.2d 1316 (Court of Special Appeals of Maryland, 1987)
Anne Arundel County v. Norair Engineering Corp.
341 A.2d 287 (Court of Appeals of Maryland, 1975)
Traylor v. Grafton
332 A.2d 651 (Court of Appeals of Maryland, 1975)
Oregon, State Highway Com'n v. DeLong Corp.
495 P.2d 1215 (Court of Appeals of Oregon, 1972)
Siler v. Marshall
247 A.2d 385 (Court of Appeals of Maryland, 1968)
H. J. McGrath Co. v. Wisner
55 A.2d 793 (Court of Appeals of Maryland, 1947)
Foster v. Hudson Valley Lumber Co.
37 F. Supp. 381 (D. Maryland, 1941)
Title & Trust Co. v. United States Fidelity & Guaranty Co.
7 P.2d 805 (Oregon Supreme Court, 1931)
Hammaker v. Schleigh
147 A. 790 (Court of Appeals of Maryland, 1929)
Secord v. Portland Shopping News
269 P. 228 (Oregon Supreme Court, 1928)
Hanlon Drydock & Shipbuilding Co. v. G. W. McNear, Inc.
232 P. 1002 (California Court of Appeal, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
93 A. 420, 125 Md. 208, 1915 Md. LEXIS 196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baltimore-bridge-co-v-united-railways-electric-co-md-1915.