Stratton v. Fike

51 So. 874, 166 Ala. 203, 1909 Ala. LEXIS 437
CourtSupreme Court of Alabama
DecidedDecember 16, 1909
StatusPublished
Cited by14 cases

This text of 51 So. 874 (Stratton v. Fike) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stratton v. Fike, 51 So. 874, 166 Ala. 203, 1909 Ala. LEXIS 437 (Ala. 1909).

Opinion

MAYFIELD, J.

Appellee sued appellant on the common counts, for work and labor done, and material furnished in remodeling and improving a residence. The defendant pleaded the general issue, and several special pleas of recoupment and set-off as per the contract under which the work was done and the material furnished. The contract set forth in the special pleas, and conceded to be the one under which the work was done, was as follows :J

“State of Alabama, County of Mobile.

“This instrument made and entered into by and between Peter J. Hamilton, as agent for Georgia K. Gage, of the first part, and Edward G. Fike, of the second part witnesseth: That for mutual consideration said parties do contract together as follows:

[207]*207“(1) Said Hamilton hereby employs said Fike as contracter to remodel and complete the brick building east of the main dwelling on the Ketchum lot southeast corner of Government and Chatham streets, and otherwise to improve and complete in first class workmanlike order, said building for residence purposes, with wiring, sewerage and water complete, all according to plans and specifications by George D. Hulburt and Company, omitting corner ornamentation of outside walls.

“(2) Said Hamilton agrees to pay said Fike for such work the sum of four thousand, nine hundred and thirteen dollars, on proper certificates of the architect, in instalments as follows: On Saturdays up to fifteen per cent of materials delivered and work performed not to exceed one thousand two hundred and fifty dollars in the first thirty days.

“(3) Said work is to be completed and the building turned over to said Hamilton, or his principal, on or before the 20th day of December, 1906. Should said building not be turned over complete, said Hamilton may retain out of the compensation hereinabove provided for the sum of ten dollars a day until the building is so turned over, delays beyond contractor’s control excepted.

“(4) Said work is to be superintended and under the direction of Willis B. Diggers, or such other architect as said Hamilton may designate.

“Witness our hands and seals in duplicate at Mobile, this first day of Sept., 1906.

“(Signed) E. G. Fike, (Seal.)

“P. J. Hamilton, (Seal.)

“Agent for Ga. K. Gage.”

“Signed, sealed, and delivered in the presence of: (Corrections before execution.) A. L. Staats.”

[208]*208The only material question raised on this appeal is whether section 3 of the above contract shall be construed as liquidated damages or as a penalty. It is usually a more or less difficult question to determine whether stipulations of this kind are in the nature of liquidated damages or of penalties. No certain or fixed rule can be given for determining in all cases whether the stipulation is the one or the other. The question must therefore be determined in each particular case upon the facts and circumstances of the given cause. The intention of the parties to the contract, however, must control in all cases, if that can be ascertained. The object and end to be attained in all constructions of contracts is to ascertain the intention of the parties, and this is no exception to the rule. ;

This court, among others, has announced some rules or laws of construction applicable to such stipulations in contracts. In Hooper’s Case, 69 Ala. 343, the court, through Brickell, O. J., said: “In the determination of this question, as in the determination of all other questions touching the construction of contracts, the gov: erning guides are the subject of the contract and-tne intention of the parties. Considering this particular question, said Chief Justice Collier in Watts v. Sheppard, 2 Ala. 434: ‘The first general principle in the construction of all contracts is that they shall be so expounded as to carry into effect the intention of the parties. To this end, the court should, if necessary, look to the subject-matter of the contract, the situation of the parties, the motives that led to it, and the objects intended to be attained by it.’ Among principles well established in determining whether a stipulation or covenant of the character now under consideration is in its nature a penalty or liquidated damages the first is that it is the tendency and preference of the law to [209]*209regard tlie stipulation or covenant as of the nature of a penalty, rather than as liquidated damages, because then it may he apportioned to the loss actually sustained; and compensation for that loss is the full measure of justice and right. * * "And if it be doubtful, upon a just consideration of all the terms and purposes of the contract, of the relation of the parties, of their objects and purposes, and of the duty to be performed, whether the sum stated was intended as liquidated damages, or as a penalty, as the latter it will he construed. * * * And where the agreement or covenant is for the performance of several things, and the stipulation is for the payment of a sum in gross in the event of a failure to perform, in whole or in part, the sum stated will be considered as a penalty.” Again, in the case of Keeble v. Keeble, 85 Ala. 555, 556, 5 South. 149 this court announced 10 rules of construction (too lengthy to he here set out) for guidance as to such stipulations. Such stipulations have often been before the court for construction — sometimes being held to be penalties, and sometimes liquidated damages.—Watts v. Sheppard, 2 Ala. 434; Henderson v. Murphree, 109 Ala. 556, 20 South. 45; McPherson v. Robertson, 82 Ala. 459, 2 South. 333; McCurry v. Gibson, 108 Ala. 457, 18 South. 806, 54 Am. St. Rep. 177; Brahan v. Pope, 1 Stew. 135; Mansur, etc., Co. v. Tissier, etc., Co., 136 Ala. 597, 33 South. 818; Henderson, etc., Co. v. Cook, 149 Ala. 226, 42 South. 838. It will be found that the decision in each case depended upon the facts and circumstances of the particular contract under consideration.

If, from the nature of the contract, the damages for the breach cannot he calculated with any degree of certainty, a stipulated sum will usually be held to be liquidated damages — that is, it will be considered that the parties agreed in advance upon the amount, and it will [210]*210be so treated — but, if it is doubtful'from, the whole contract as to which was intended, the courts, being inclined to do equal justice to the parties if possible, will resolve the doubt in favor of the penalty construction. If the damages resulting from the breach can be definitely and certainly ascertained, then there would be no urgent necessity or occasion for agreeing in advance as to the amount thereof, and it will be construed as a penalty. The fact that the parties name the result as “stipulated damages” or as “penalty” will not control if the intention of the parties can be clearly ascertained to indicate the other. Where the damages sustained by a breach of a single stipulation in a contract are uncertain, and there is no fixed or certain standard or data, by which they can be ascertained, and the parties in the contract have fixed that amount, it is reasonable to conclude that they named and fixed that amount because the amount would be uncertain if there was a breach; and it will be so treated. It will in such case be considered by the court as the measure of compensation for the breach, if it is not out of all proportion to the probable and presumable loss.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pasquale Food Co., Inc. v. L & H INTERNATIONAL AIR., INC.
283 So. 2d 438 (Court of Civil Appeals of Alabama, 1973)
Otinger v. Water Works and Sanitary Sewer Board
177 So. 2d 320 (Supreme Court of Alabama, 1965)
Yarbrough Realty Co. v. Barar
67 So. 2d 853 (Alabama Court of Appeals, 1953)
Federal Land Bank v. Bridgeforth
173 So. 66 (Supreme Court of Alabama, 1937)
Cortner v. Anderson, Clayton & Co.
144 So. 443 (Supreme Court of Alabama, 1932)
American District Telegraph Co. v. Roberts & Son, Inc.
122 So. 837 (Supreme Court of Alabama, 1929)
Weiss v. United States Fidelity & Guaranty Co.
132 N.E. 749 (Illinois Supreme Court, 1921)
J. B. Colt Co. v. Armstrong Light Co.
85 So. 570 (Alabama Court of Appeals, 1920)
Lowy v. Rosengrant
71 So. 439 (Supreme Court of Alabama, 1916)
Baltimore Bridge Co. v. United Railways & Electric Co.
93 A. 420 (Court of Appeals of Maryland, 1915)
George v. Roberts
65 So. 345 (Supreme Court of Alabama, 1914)
Strode v. Smith
131 P. 1032 (Oregon Supreme Court, 1913)
Walshe Mfg. Co. v. W. T. Smith Lumber Co.
59 So. 455 (Supreme Court of Alabama, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
51 So. 874, 166 Ala. 203, 1909 Ala. LEXIS 437, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stratton-v-fike-ala-1909.