American District Telegraph Co. v. Roberts & Son, Inc.

122 So. 837, 219 Ala. 595, 1929 Ala. LEXIS 305
CourtSupreme Court of Alabama
DecidedJanuary 24, 1929
Docket6 Div. 160.
StatusPublished
Cited by20 cases

This text of 122 So. 837 (American District Telegraph Co. v. Roberts & Son, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American District Telegraph Co. v. Roberts & Son, Inc., 122 So. 837, 219 Ala. 595, 1929 Ala. LEXIS 305 (Ala. 1929).

Opinions

*598 ANDERSON, C. J.

This case was tried Iby the court without a jury, and there was a judgment for the plaintiff. The defendant appeals, and the assignments of error are predicated on two propositions only, first, that there was error in rendering a judgment for the plaintiff in any amount, and, second, if the plaintiff was entitled to recover at all, the amount! was limited by the contract to ISC'.

The main question and the one first presented in argument calls for an interpretation of the following clause in the contract, to wit:

“It is agreed by and between the parties hereto that the Contractor is not an insurer, and that the. rates hereinbefore named are based solely on the value of the service in the operation of the system described, and in case of failure to perform such service and a resulting loss its liability hereunder shall be limited to and fixed at the sum of 850.00 as liquidated damages, and not as a penalty, and this liability shall be exclusive.”

As we view this clause, it is but a limitation of the amount recoverable in case of á breach of the contract. It is Unlike those contracts or clauses construed by the courts as being invalid because providing a penalty though designated as liquidated damages.

The contract does not penalize the defendant for a failure to perform, and it only restricts, the plaintiff as to its recovery in case of a breach by the defendant, and does not attempt to penalize or fix the damages against the plaintiff in case of a breach by it. It deals only with a breach by the defendant, and in no sense penalizes it for a breach; so we are at a loss to understand the necessity for the earnest and elaborate argument by both sides on the question of when such clauses should be construed as a penalty or liquidated damages. Conceding, however, that, by limiting the amount of recoverable damages, it operates as a burden or hardship on the plaintiff, still we are not at liberty, by analogous authorities, to make a new contract for the parties or to strike therefrom a clause well understood and evidently within the intention of the parties.

As brought out by Mr. Sutherland in his work on Damages, and by Mr. Williston in his work on Contracts, much confusion has heretofore arisen, and there is little harmony in the cases dealing with the question as to when certain clauses of contracts, fixing, the amount of recovery for a breach, should be construed as liquidated damages or stricken because they provided a penalty, but the more recent cases show a tendency to uphold clauses of this character with the same degree of solemnity and importance as other parts of the contract.

As said by the United States Supreme Court in the case of Sun Printing & Publishing Ass’n v. Wm. L. Moore, 183 U. S. 642, 22 S. Ct. 240, 46 L. Ed. 366, after rejecting the contention that, when actual damages can be assessed from .the testimony, the court must disregard any stipulation fixing the amount and require proof of the damage sustained, “The decisions of this court on the doctrine of liquidated damages and penalties lend no support to the contention that parties may not bona fide, in a case where the damages are of an uncertain nature, estimate and agree upon the measure of damages which may be sustained from the breach of an agreement. On the contrary, this court has consistently maintained the principle that the intention of the parties is to be arrived at by a proper construction of the agreement made between them, and that whether a particular stipulation to pay a sum of money is to be treated as a penalty, or as an agreed ascertainment of damages, is to be determined by the contract, fairly construed, it being the duty of the court always, where the damages are uncertain and have been liquidated by an agreement, to enforce the contract.”

Mr. Sutherland in his work on Damages, § 283, vol. 1, p. 842, after discussing the decisions on the subject, lays down the following rules or test:' “First, that if by the terms of the contract, a greater sum is to be paid upon default in the payment of a lesser sum at a given time, the provision for the payment of the greater sum will be held a penalty; second, where, by the terms of a contract, the damages are not difficult of ascertainment according to such terms and the stipulated damages are unconscionable, the latter will be regarded as a penalty; third, within these two rules parties may agree upon any sum as compensation for the breach of a contract.”

When the contract in question was entered into, the nature and amount of damages that might arise as the result of a breach were conjectural and uncertain, and the parties had the right to fix the same by the contract, and, having intended to do so, the court is not authorized to nullify this provision by declaring it a penalty, although the actual damage sustained may be in excess of the sum fixed by the contract. Stratton v. Fike, *599 166 Ala. 203, 51 So. 874; Keeble v. Keeble, 85 Ala. 552, 5 So. 149. We therefore hold that the clause in question was binding on the parties as fixing the amount of recoverable damages for a breach of the contract.

Another question, however, arises as to those counts of the complaint in tort for the negligent breach of duty growing out of the contract and whether or not the clause can apply as to the limitation of a liability for the negligence of the defendant. This court is committed to the doctrine that, where parties enter into a relation carrying a legal duty, while one may limit the scope of his duties, he cannot stipulate for protection against negligence in the performance of the duties he does assume. Thompson v. Mobile Light & R. Co., 211 Ala. 525, 101 So. 177, 34 A. L. R. 921. Contracts against liability will not be construed to cover negligence in the delivery of a telegram. Am. Union Tel. Co. v. Daughtery, 89 Ala. 191, 7 So. 660; W. U. Tel. Co. v. Chamblee, 122 Ala. 428, 25 So. 232, 82 Am. St. Rep. 89; W. U. Tel. Co. v. Anniston Cordage Co., 6 Ala. App. 351, 59 So. 757. True, these cases involved the duties of public service utilities, but the defendant here was serving the public in the installation of a signal service system as a protection against loss by fire, and the installation of the system by the property owner lowered the rate of the insurance, and we see no good reason why the cases, supra, should not apply to the defendant. It was at least a quasi public service utility.

We do not understand the case of W. U. Tel. Co. v. Westmoreland, 151 Ala. 319, 44 So. 382, as holding to the contrary. In the first place, without questioning the soundness of same, there is much said in the opinion in this case that was unnecessary to a decision of the questions involved. That case involved the right of the plaintiff, under the circumstances, to recover for mental anguish and also her right to recover punitive damages. There are expressions to the effect that, whether an action be upon contract or tort arising out of the breach of duty, no punitive damages being involved, the amount of recovery is the same, meaning, of course, that the actual damages for a breach of the contract or a negligent breach of the duty is the same, but there is nothing in the case to indicate that a contractual limitation of the former would also operate as a restriction on the latter.

The case of Wells Fargo & Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blake v. Bank of America, N.A.
845 F. Supp. 2d 1206 (M.D. Alabama, 2012)
Faulk v. Rhodes
62 So. 3d 517 (Court of Civil Appeals of Alabama, 2010)
Royal Ins. Co. v. Whitaker Contracting Corp.
824 So. 2d 747 (Supreme Court of Alabama, 2002)
Alverson v. Trans-Cycle Industries, Inc.
726 So. 2d 670 (Court of Civil Appeals of Alabama, 1998)
Sutton v. Epperson
631 So. 2d 832 (Supreme Court of Alabama, 1993)
City of Montgomery v. JYD Intern., Inc.
534 So. 2d 592 (Supreme Court of Alabama, 1988)
Corral v. Rollins Protective Services Co.
732 P.2d 1260 (Supreme Court of Kansas, 1987)
Matthews v. Mountain Lodge Apartments, Inc.
388 So. 2d 935 (Supreme Court of Alabama, 1980)
Industrial Tile, Inc. v. Stewart
388 So. 2d 171 (Supreme Court of Alabama, 1980)
McCay v. Big Town, Inc.
307 So. 2d 695 (Supreme Court of Alabama, 1975)
Foont-Freedenfeld Corp. v. Electro-Protective Corp.
314 A.2d 69 (New Jersey Superior Court App Division, 1973)
Shaer Shoe Corp. v. Granite State Alarm, Inc.
262 A.2d 285 (Supreme Court of New Hampshire, 1970)
Baker v. Wheeler, Lacey & Brown, Inc.
128 So. 2d 721 (Supreme Court of Alabama, 1961)
Schepps v. American District Telegraph Co. of Texas
286 S.W.2d 684 (Court of Appeals of Texas, 1955)
Housing Authority of Birmingham Dist. v. Morris
14 So. 2d 527 (Supreme Court of Alabama, 1943)
Life & Casualty Ins. v. Porterfield
194 So. 173 (Supreme Court of Alabama, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
122 So. 837, 219 Ala. 595, 1929 Ala. LEXIS 305, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-district-telegraph-co-v-roberts-son-inc-ala-1929.