Weiss v. United States Fidelity & Guaranty Co.

132 N.E. 749, 300 Ill. 11
CourtIllinois Supreme Court
DecidedOctober 22, 1921
DocketNo. 13678
StatusPublished
Cited by18 cases

This text of 132 N.E. 749 (Weiss v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weiss v. United States Fidelity & Guaranty Co., 132 N.E. 749, 300 Ill. 11 (Ill. 1921).

Opinion

Mr. Justice Duncan

delivered the opinion of the court:

Julius Weiss, plaintiff in error, recovered a judgment in the municipal court of Chicago in a first-class action against the United States Fidelity and Guaranty Company, defendant in error, in the sum of $3497.64. On appeal to the Appellate Court for the First District the judgment was reversed without remanding and a judgment entered in that court in favor of plaintiff in error for $872.64. A writ of certiorari was granted by this court for review of the record on error.

Plaintiff in error was the owner of a three-story building located at 837 West Twelfth street, in Chicago, consisting of a store and two flats above it.' Owing to the widening of Twelfth street by the city it became necessary to remodel this building, and accordingly a contract was entered into between the plaintiff in error and the Oscar Osberg Company on October n, 1916, providing that in consideration of an agreed price of $5700 the Oscar Osberg Company would remodel the building according to the plans and specifications of a named architect and the company would furnish a surety bond in the sum of $5700. In case the company should commit any breach of the covenants or agreements in the contract, it was to be optional with the plaintiff in error to terminate the contract and engage another contractor to complete the job, and the company was to be liable for any and all damages that might ensue as the result of such breach, and such damages were to be deducted from the part of the contract price that should remain due the company. The contract also contained this clause: “It is further agreed by and between the parties that the work upon said job is to be commenced immediately and it is to be finished not later than January 15, 1917, and for every day that it shall take the said party of the first part after January 15, 1917, to complete the said job, the said party of the first part shall pay as liquidated damages to the said party of the second part the sum of fifteen ($15) dollars per day.” On the same day a bond was executed to plaintiff in error by the Oscar Osberg Company as principal and the defendant in error as surety in the sum of $5700 for the faithful performance of the contract on the part of the Oscar Osberg Company.

Plaintiff in error’s statement of claim set up in hac verba the building contract and the bond signed by the defendant in error as surety, and alleged that the contracting company failed to complete the building contract by January 15, 1917, and continued to work on the building until April 28, 1917, and then refused to complete the contract; that by and with the consent of the defendant in error the plaintiff in error completed the building through other contractors and performed all the terms and conditions of the contract to be performed; that the building was completed July 10, 1917, at an additional cost to plaintiff in error above the contract price of $907.64, and that he is entitled to recover of defendant in error said last sum and $15 per day for the 175 days from January 15, 1917, to the completion of the contract, July 10, 1917.

In its affidavit of merits defendant in error set up as a defense that plaintiff in error failed to exercise his option to terminate the contract and to use diligence to avoid loss thereunder; that he did not suffer damages of $15 per day for failure to complete the work on time and waived the provision as to completion of the contract and requested the contractor to continue the work; that he failed to demand architect’s certificates of work performed; that there were alterations causing delay for which no credit was given; that plaintiff in error was a party to the failure to complete on time; that he did not finish the job with the consent of the defendant in error; that defendant in error did not execute bonds for performance of the contract at 837 West Twenty-first street, and that plaintiff in error failed to keep the agreement to be kept by him but was guilty of conduct relieving the defendant in error of any and all liability.

The trial was before the court without jury. Plaintiff in error proved his contract as set out in his statement of claim and the execution and delivery of the bond by defendant in error. He also proved the breach of the building contract by the contractor and his abandonment of the same as set forth in the statement of claim. He further proved that in December, 1916, he notified defendant in error that the contractor would not be able to complete the building by January 15, 1917, as agreed, and that defendant in error by one of its agents thereafter visited the contractor and requested it to hurry up' and complete the contract as soon as possible; that after the contractor abandoned the contract plaintiff in error notified defendant in error thereof and requested it to complete the contract; that it declined so to do and notified plaintiff in error to complete the contract, and that in the event the contract price should not be sufficient to pay all claims for labor and material it would then consider any claim which he might have on it and would pay such amount as it might be liable for in accordance with the provisions of its bond; that plaintiff in error then completed the contract and paid all liens and claims by and with the consent of defendant in error, including the claim of the subsequent contractor, and was required to pay out, in addition to the contract price for repairing the building, the sum of $872.64, and was delayed 175 days in the completion of his building by the refusal of the contractor to complete it. Defendant in error introduced no evidence whatever. It submitted no propositions of law to the court, except at the close of plaintiff in error’s evidence: it made an oral motion that the court make a finding for it. Thereupon the plaintiff in error introduced further evidence, but defendant in error did not renew its motion or make any other motion whatever.

The trial court gave judgment for $872.64,—the amount paid by plaintiff in error in excess of the contract price,— and in addition thereto the further sum of $2625 as agreed liquidated damages for 175 days at $15 per day for failure to complete the building in the time agreed. The Appellate Court held that the provision of the contract for $15 per day for every day that it should take the contractor to finish the building after January 15, 1917, was for a penalty and not recoverable by plaintiff in error and gave judgment for the actual damages proved, $872.64, with this finding of fact: “We find as an ultimate fact in this case that the plaintiff, Julius Weiss, was damaged in the sum of $872.64 by reason of the failure of the Oscar Osberg Company to carry out its building contract with him, for which sum the United States Fidelity and Guaranty Company is liable as surety on the bond in question.” The Appellate Court by this finding has made no finding contrary to the facts found by the trial court. This court is therefore bound by the facts found by the trial court.

The evidence introduced by plaintiff in error did prove the statement in the affidavit of merits that defendant in error did not execute a bond for performance of the contract at 837 West Twenty-first street, but it did execute a bond for the performance of the contract at 837 West Twelfth street. The contractor’s contract by mistake described the property as at 837 West Twenty-first street.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Karimi v. 401 North Wabash Venture, LLC
2011 IL App (1st) 102670 (Appellate Court of Illinois, 2011)
Hickox v. Bell
552 N.E.2d 1133 (Appellate Court of Illinois, 1990)
Morris v. Flores
528 N.E.2d 1013 (Appellate Court of Illinois, 1988)
Northern Illinois Gas Co. v. Energy Cooperative, Inc.
461 N.E.2d 1049 (Appellate Court of Illinois, 1984)
Norwalk Door Closer Co. v. Eagle Lock & Screw Co.
220 A.2d 263 (Supreme Court of Connecticut, 1966)
Bethlehem Steel Company v. City of Chicago
234 F. Supp. 726 (N.D. Illinois, 1964)
Chisholm v. Reitler
352 P.2d 794 (Supreme Court of Colorado, 1960)
Burnett v. Nolen
84 N.E.2d 155 (Appellate Court of Illinois, 1949)
Hoefeld v. Sixty-third & Halsted Realty Co.
7 N.E.2d 402 (Appellate Court of Illinois, 1937)
Paramount Pictures Distributing Corp. v. Gehring
283 Ill. App. 581 (Appellate Court of Illinois, 1936)
Waller v. Wilson
282 Ill. App. 418 (Appellate Court of Illinois, 1935)
Christian Mills, Inc. v. Berthold Stern Flour Co.
247 Ill. App. 1 (Appellate Court of Illinois, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
132 N.E. 749, 300 Ill. 11, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weiss-v-united-states-fidelity-guaranty-co-ill-1921.