Norwalk Door Closer Co. v. Eagle Lock & Screw Co.

220 A.2d 263, 153 Conn. 681, 1966 Conn. LEXIS 576
CourtSupreme Court of Connecticut
DecidedMay 25, 1966
StatusPublished
Cited by65 cases

This text of 220 A.2d 263 (Norwalk Door Closer Co. v. Eagle Lock & Screw Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norwalk Door Closer Co. v. Eagle Lock & Screw Co., 220 A.2d 263, 153 Conn. 681, 1966 Conn. LEXIS 576 (Colo. 1966).

Opinion

Alcorn, J.

In this action, the plaintiff, hereinafter called Norwalk, is seeking to recover $100,000 as liquidated damages for the breach of a written contract by the defendant, hereinafter called Eagle, and an additional sum for Eagle’s failure to deliver goods which had been ordered under the contract. Claims for consequential damages and for loss of profits and good will are no longer in issue. Eagle counterclaimed to recover $63,574.33 for goods delivered to Norwalk. Norwalk does not dispute this indebtedness. The trial court denied recovery of the $100,000 on the ground that it was a penalty, but it awarded damages to Norwalk of $1687.19 for Eagle’s failure to deliver goods ordered under the contract. The court found Eagle entitled to recover $63,574.34 on its counterclaim. This admitted indebtedness is, however, incorrectly stated in the judgment to be $61,887.15. Norwalk has appealed from the judgment, and Eagle has filed a cross appeal.

*683 The basic facts may be summarized as follows: Norwalk owned the right to manufacture door closers together with the tools, dies, patterns and other equipment necessary for their manufacture. On June 22, 1956, after extended negotiations, Nor-walk entered into a written contract with Eagle wherein Eagle undertook to manufacture door closers exclusively for Norwalk for seven years, using the tools, dies, patterns and other equipment owned and provided by Norwalk. Norwalk retained the right to extend the contract for an additional five years. Eagle assumed the cost of engineering services and equipment necessary for quantity production up to specified amounts. Beyond those amounts Norwalk assumed the expense, which was to be determined and paid on a basis specified in the contract. When the contract was made, Eagle’s chief engineer had estimated that the cost of preparing for quantity production would be approximately $78,750. Eagle actually spent $142,812.67, which was a reasonable expenditure for that purpose.

When the contract was made, Sereno L. Mastorgi was Eagle’s president and general manager. In paragraph 13 of the contract, Norwalk reserved the option to terminate the agreement on thirty days’ notice to Eagle in the event that Mastorgi should, for any reason, cease to be Eagle’s general manager. In that event, Norwalk agreed to pay Eagle specified amounts in full liquidation of all damages.

Paragraph 14 of the contract presents the principal issue between the parties. That paragraph reads as follows: “In the event that Eagle shall for any reason desire to terminate this agreement, it shall give not less than ninety (90) days’ notice of such intention to terminate unless such *684 notice shall set forth a longer period. Eagle shall in any event complete all orders received by Eagle up to that date which shall be half-way between the date of the sending of said notice and the intended termination date. If Eagle shall liquidate its business, or shall cease to occupy its present plant in Terryville, or if Eagle shall sell its shares of stock to any person, firm, or corporation other than the present holder or holders thereof, or if Eagle shall for any reason, except strike, fire, flood, act of God, or circumstances beyond Eagle’s control, cease or be unwilling or unable to manufacture and ship closers as in this agreement provided, then, in any such event, this agreement shall be deemed at the option of Norwalk, breached and terminated by Eagle. If Norwalk shall so elect to treat this agreement as breached and terminated, it shall give ten (10) days’ notice in writing to Eagle and, upon the expiration of said ten (10) days, Eagle shall forthwith deliver to Norwalk all of the items and under the terms set forth in paragraph 12 hereof. Eagle shall also pay to Norwalk the sum of $100,000.00, and upon such delivery of items as aforesaid and payment as aforesaid, this agreement and all obligations of the parties hereunder shall cease and determine, except as to obligations or liabilities incurred by either prior to the effective date of termination.”

The parties operated under the contract until September 29, 1960, when Eagle notified Norwalk that the agreement would terminate on December 31, 1960, and that it would complete all orders received from Norwalk prior to November 15, 1960. In October, 1960, Eagle sold all its assets to another corporation. On December 16, 1960, Norwalk notified Eagle of its election to treat the notice of *685 termination as a breach of the contract and demanded the return of all tools and equipment and the payment of $100,000 in accordance with paragraph 14 of the contract. 1 Between October 31 and November 10, 1960, Norwalk sent orders for a total of 11,000 door closers, part of which were filled by Eagle and for which it billed Norwalk $63,574.37. Norwalk has not paid this bill. Eagle returned to Norwalk all items due it on the termination of the contract.

The trial court concluded that paragraph 14 of the contract, calling for payment of $100,000, was not a provision for liquidated damages but was a penalty and consequently was unenforceable. This conclusion is attacked by Norwalk in its appeal. Incidental to this claim is the issue as to pleading and burden of proof.

The complaint did not allege the contract in full or incorporate it by reference. It alleged that paragraph 14 of the contract provided “that in the event Defendant desired to terminate the agreement for any reason, or if Defendant liquidated its business or ceased to occupy its then plant in Terryville, Connecticut, or if Defendant for any reason ceased or was unwilling or unable to manufacture and ship door closers as provided in said agreement, then, in any such event, at the option of Plaintiff, the said agreement could be deemed by Plaintiff as breached and terminated by Defendant, and Defendant would thereupon be required to pay to Plaintiff the sum of $100,000.00.” Eagle in its answer admits the existence of a contract “but refers to said contract for a correct statement of the terms thereof.” Eagle did not file a special *686 defense. Norwalk claims that Eagle, because it did not plead penalty as a special defense, failed to raise that issue properly at the trial, and that that failure precluded the court from resting a decision on that ground.

It is settled law that a contract provision which imposes a penalty for a breach of the contract is contrary to public policy and is invalid, but a contractual provision which fixes liquidated damages for a breach of the contract is enforceable if it satisfies certain conditions. Berger v. Shanahan, 142 Conn. 726, 731, 118 A.2d 311, and cases cited. The conditions which will justify an agreement for liquidated damages are: “(1) The damage which was to be expected as a result of a breach of the contract was uncertain in amount or difficult to prove; (2) there was an intent on the part of the parties to liquidate damages in advance; and (3) the amount stipulated was reasonable in the sense that it was not greatly disproportionate to the amount of the damage which, as the parties looked forward, seemed to be the presumable loss which would be sustained by the contractee in the event of a breach of the contract.” Id., 732.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tsiropoulos v. Radigan
Connecticut Appellate Court, 2016
Peterson v. McAndrew
Connecticut Appellate Court, 2015
Old Colony Construction, LLC v. Southington
Supreme Court of Connecticut, 2015
HH East Parcel, LLC v. Handy & Harman, Inc.
947 A.2d 916 (Supreme Court of Connecticut, 2008)
Barrie School v. Patch
933 A.2d 382 (Court of Appeals of Maryland, 2007)
Lieberman v. Emigrant Mortgage Co.
436 F. Supp. 2d 357 (D. Connecticut, 2006)
Medvalusa Health Programs, Inc. v. Memberworks, Inc.
872 A.2d 423 (Supreme Court of Connecticut, 2005)
American Car Rental, Inc. v. Commissioner of Consumer Protection
869 A.2d 1198 (Supreme Court of Connecticut, 2005)
McKeever v. Fiore
829 A.2d 846 (Connecticut Appellate Court, 2003)
Executive Airlines v. Electric Boat Corp.
271 F. Supp. 2d 392 (D. Connecticut, 2003)
Paul v. Levine, No. Cv00 0180414 S (Feb. 25, 2002)
2002 Conn. Super. Ct. 2233 (Connecticut Superior Court, 2002)
Ranciato v. Nolan, No. Cv 97-0401729 S (Feb. 7, 2002)
2002 Conn. Super. Ct. 1531 (Connecticut Superior Court, 2002)
Honey Dew Associates, Inc. v. M & K Food Corp.
241 F.3d 23 (First Circuit, 2001)
Cintas Corporation v. Hoffman Fuel Co., No. Cv 99-0424019s (Oct. 6, 2000)
2000 Conn. Super. Ct. 12411 (Connecticut Superior Court, 2000)
Ferraina v. Industrial Health Care Co., No. Cvh-6214 (Feb. 24, 2000)
2000 Conn. Super. Ct. 1972 (Connecticut Superior Court, 2000)
Hartford Ins. Co. v. Adt SEC. Sys., No. Cv98 035 71 49, (Apr. 22, 1999)
1999 Conn. Super. Ct. 5285 (Connecticut Superior Court, 1999)
American Bank of Connecticut v. Mango, No. Cv 95 126053 (Dec. 29, 1998)
1998 Conn. Super. Ct. 15627 (Connecticut Superior Court, 1998)
Anthony P. Guiliano v. Cleo Inc. - Concurring
Court of Appeals of Tennessee, 1997
Vloski v. American Protective Services, No. Cv93 0353966s (Nov. 14, 1996)
1996 Conn. Super. Ct. 8984 (Connecticut Superior Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
220 A.2d 263, 153 Conn. 681, 1966 Conn. LEXIS 576, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norwalk-door-closer-co-v-eagle-lock-screw-co-conn-1966.