Massman Const. Co. v. City Council of Greenville, Miss.

147 F.2d 925, 1945 U.S. App. LEXIS 2211
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 26, 1945
Docket11139
StatusPublished
Cited by24 cases

This text of 147 F.2d 925 (Massman Const. Co. v. City Council of Greenville, Miss.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Massman Const. Co. v. City Council of Greenville, Miss., 147 F.2d 925, 1945 U.S. App. LEXIS 2211 (5th Cir. 1945).

Opinion

*926 WALLER, Circuit Judge.

Appellant brought suit in equity against the Appellee for the recovery of the sum of $21,300 which it claimed the Appellee had wrongfully withheld as liquidated damages for the failure of the Appellant to finish the construction of four bridge piers in the Mississippi River within the time limit of 350 days fixed in the contract between Appellant and Appellee. Another contractor built the superstructure of the bridge on these piers. Appellant consumed 109 days in excess of the 350 prescribed for the completion of its contract, but it was allowed 12% days additional for extra work in sinking one of the piers to a greater depth than provided in the specifications, due to the misinformation supplied by the Appellee to Appellant as to subsurface conditions, so that the net delay in contract completion was reduced to 96% days. On account of the delay Appellee charged Appellant $250 per day for the 96% days, totalling $24,125, which it retained out of the contract price as liquidated damages, plus $875 for good measure. The following provisions in the contract are cited by the City as the basis of its right so to do:

“The bridge is to be operated as a toll project and delay in completion will cause interference with traffic and losses, such a*s lost earnings, interest in investment, administration expenses and other tangible and intangible loss and will incommode the public. To cover partially such losses and expenses, the Owner shall have the right to deduct from the total compensation otherwise due the Contractor as liquidated damages, fixed and agreed to in advance and otherwise indeterminate, * * * for each 24 hour calendar day that the entire work covered by the respective contract remains in an uncompleted state after the dates for completion herein provided: * * ■ * the sum of Two Hundred Fifty Dollars ($250.00) for each 24 hour calendar day.” (Italics supplied.)
* * * * #
“It is mutually agreed by the parties hereto that time is of the essence of this contract and in event the construction of the work is not completed within the time herein specified, it is agreed that from the compensation otherwise to be paid to the contractor, the first party may retain the sum of $250.00 per day for each day thereafter, Sundays and holidays included, that the work remains uncompleted, which sums shall represent the actual damages which the Owner will have sustained per day by failure of the Contractor to complete the work within the time stipulated and this sum is not a penalty but a stipulated damage the first party will have sustained in event of such default by the second party.”

The western end of the bridge was in the State of Arkansas, which state had agreed to construct the highway leading to its end of the bridge. However, the entire bridge was finished at least 30 days before it could be utilized on account of the lack of a road leading to it from the Arkansas side of the river. “All dressed up and nowhere to go,” the bridge sat unutilized for 30 days or more after its full completion, so that the delay by Appellant did not cause a delay in beginning the operation of the toll bridge with the attendant losses for non-operation which the contract sought to provide against. However, the City, demanding its pound of flesh, insists upon the right to have $250 per day as liquidated damages under its contract calling for the payment of a sum to cover partially such losses as lost earnings, interest on investment, administration expenses, and other •tangible and intangible loss, and discommodity to the public caused by a delay in operating the toll bridge in consequence of the delay in the completion of Appellant’s contract. The Court below denied the Appellant the right to recover the sum withheld as liquidated damages, but allowed recovery of the sum of $875, which was admitted to be due by the City.

Appellant, admitting the right of the City, under a subsequent agreement between it and the engineers, to retain the sum of $3700, and suing for only $21,300, claims: (1) That the provision for the payment of $250 per day was a penalty and not liquidated damages, and being a penalty the City would have no right in any case to recover as damages any sum in excess of that which it was shown to have actually sustained; (2) that the subsurface conditions under the piers was misrepresented by the City in that the data obtained by drilling, which the City furnished bidders, failed to show the true condition of the soil in the river bed, as well as the true facts as to the depth and current of the river; (3) that the engineers, having the power under the contract, and finding that the delay‘was for reasons beyond the control of the contractor, had granted an ex *927 tension of time so that the City could rightly retain only the equivalent per diem of 14.8 days; (4) that the City, acting pursuant to the aforesaid finding by the engineers, having adopted a resolution that the contract was not completed on the completion date thereof “due to circumstances beyond the control of the contractor”, ratified the act of the engineers and was bound thereby, either as a waiver of the right to damages or as an admission against interest to the effect that the delay was not the fault of the contractor; and (5) that Sundays should not be included because of the prohibition of the law of Mississippi against working on the Sabbath.

In construing a contract as to whether it calls for liquidated damages or a penalty, the main endeavor of the Court is to ascertain the intention of the parties, and that must be gleaned from the circumstances surrounding them and from a consideration of the purposes and provisions of the whole contract. Nomenclature is not controlling, 1 but the intention of the parties is the important, if not the conclusive, factor. Jones v. Mississippi Farms Co., 116 Miss. 295, 76 So. 880; 15 Amer.Jur. 674, § 243.

The quoted provisions of the contract show that the parties intended to provide for liquidated damages to cover partially “losses, such as lost earnings, interest in investment, administration expenses and other tangible and intangible loss” that would be “caused by a delay in completion” with the consequent delay in beginning the operation of the bridge. Even though we assume that the contract provided for liquidated damages instead of a penalty, nevertheless, the intent and purpose of the provision was to guard the City against a delay in opening the bridge and against only such losses as the parties anticipated would be caused by a delay in completion of Appellant’s contract.

The term “actual damages” used in the second paragraph above quoted has reference to actual damages which the parties to the contract presupposed would be caused the City by the delay in the operation of the bridge as a result of the failure of the Appellant to complete its contract within the time provided, but if the contingency upon which the presupposition is based never happens, the presupposition must vanish.

There were no losses caused to the City by the delay in the completion of the piers or the bridge, because the bridge was completed in its entirety 30 or more days before there was a road to the bridge on the Arkansas side.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roger Dale Latham v. Terry W. Johnson
262 So. 3d 569 (Court of Appeals of Mississippi, 2018)
International Marine, L.L.C. v. FDT, L.L.C.
619 F. App'x 342 (Fifth Circuit, 2015)
Hovas Construction, Inc. v. Board of Trustees
111 So. 3d 663 (Court of Appeals of Mississippi, 2012)
Dole Ocean Liner Express v. Georgia Vegetable Co.
949 F. Supp. 467 (S.D. Mississippi, 1996)
Howarth v. Feeney, 86-3543 (1992)
Superior Court of Rhode Island, 1992
Wassenaar v. Panos
331 N.W.2d 357 (Wisconsin Supreme Court, 1983)
Skip Kirchdorfer, Inc. v. United States
29 Cont. Cas. Fed. 82,028 (Court of Claims, 1981)
Interstate Industrial Uniform Rental Service, Inc. v. Couri Pontiac, Inc.
355 A.2d 913 (Supreme Judicial Court of Maine, 1976)
Huffman Towing, Inc. v. Mainstream Shipyard & Supply, Inc.
388 F. Supp. 1362 (N.D. Mississippi, 1975)
Mauldin v. Commissioner
60 T.C. No. 78 (U.S. Tax Court, 1973)
Enro Maritime Enterprises, Inc. v. S.T. Richard C. Sauer
320 F. Supp. 788 (S.D. New York, 1970)
Norwalk Door Closer Co. v. Eagle Lock & Screw Co.
220 A.2d 263 (Supreme Court of Connecticut, 1966)
Wood Naval Stores Export Ass'n v. Gulf Naval Stores Co.
71 So. 2d 425 (Mississippi Supreme Court, 1954)
Simms v. Bovee
68 A.2d 800 (District of Columbia Court of Appeals, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
147 F.2d 925, 1945 U.S. App. LEXIS 2211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/massman-const-co-v-city-council-of-greenville-miss-ca5-1945.