Skip Kirchdorfer, Inc. v. United States

29 Cont. Cas. Fed. 82,028, 229 Ct. Cl. 560, 1981 U.S. Ct. Cl. LEXIS 555, 1981 WL 22058
CourtUnited States Court of Claims
DecidedNovember 6, 1981
DocketNo. 14-80C
StatusPublished
Cited by10 cases

This text of 29 Cont. Cas. Fed. 82,028 (Skip Kirchdorfer, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skip Kirchdorfer, Inc. v. United States, 29 Cont. Cas. Fed. 82,028, 229 Ct. Cl. 560, 1981 U.S. Ct. Cl. LEXIS 555, 1981 WL 22058 (cc 1981).

Opinion

This case is before the court on plaintiffs motion for summary judgment and on defendant’s cross motion for summary judgment. After careful consideration of the [561]*561parties’ submissions and without oral argument, we allow the defendant’s motion and deny the plaintiffs motion.

Skip Kirchdorfer, Inc., the plaintiff, entered into a contract with the federal government in 1977 to replace the roofs on 19 warehouse buildings in Fort Campbell, Kentucky. Part of the roofing procedure involved laying felt on the roof before the shingles were placed on top. The felt was approved by the Government prior to its placement on the roof. On two buildings, due to inclement weather, the felt was exposed for 10 to 15 days before the shingles were placed on top. The Government became concerned about the condition of the felt on these buildings and retested it to see whether it still met the specifications. Before the test results were received, in order to avoid further exposure of the felt, the plaintiff finished laying the shingles on the roof. According to the Government’s test, the felt failed to meet the specifications. The contracting officer ordered the plaintiff to replace the felt on these roofs. The plaintiff, however, disputed the Government’s method of testing the felt and requested a retesting before it would replace the roofs. When the plaintiff failed to follow the contracting officer’s order to replace the roof, the contracting officer terminated the contract.

The plaintiff made a timely appeal to the Armed Services Board of Contract Appeals (ASBCA), where the default termination was upheld and both liquidated damages and payment of excess costs were imposed on the plaintiff.

The relevant provisions of the contract include:

General Provision 32:
INSPECTION AND ACCEPTANCE (1976 OCT)
(a) All work (which term includes but is not restricted to materials, workmanship, and manufacture and fabrication of components) shall be subject to inspection and test by the Government at all reasonable times and at all places prior to acceptance. Any such inspection and test is for the sole benefit of the Government and shall not relieve the Contractor of the responsibility of providing quality control measures to assure that the work strictly complies with the contract requirements. No inspection or test by the Government shall be construed as constituting or implying acceptance. Inspection or test shall not relieve the Contractor of responsibility for [562]*562damage to or loss of the material prior to acceptance, nor in any way affect the continuing rights of the Government after acceptance of the completed work under the terms of paragraph (f) of this clause, except as herein-above provided.
(b) The Contractor shall, without charge, replace any material or correct any workmanship found by the Government not to conform to the contract requirements, unless in the public interest the Government consents to accept such material or workmanship with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(c) If the Contractor does not promptly replace rejected material or correct rejected workmanship, the Government (1) may, by contract or otherwise, replace such material or correct such workmanship and charge the cost thereof to the Contractor, or (2) may terminate the Contractor’s right to proceed in accordance with the clause of this contract entitled "Termination for Default - Damages for Delay - Time Extensions. ”
(e) Should it be considered necessary or advisable by the Government at any time before acceptance of the entire work to make an examination of work already completed, by removing or tearing out same, the Contractor shall, on request, promptly furnish all necessary facilities, labor and material. If such work is found to be defective or nonconforming in any material respect, due to the fault of the Contractor or his subcontractors, he shall defray all the expenses of such examination and of satisfactory reconstruction. If, however, such work is found to meet the requirements of the contract, an equitable adjustment shall be made in the contract price to compensate the Contractor for the additional services involved in such examination and reconstruction and, if completion of the work has been delayed thereby, he shall, in addition, be granted a suitable extension of time.
General Provision 26:
TERMINATION FOR DEFAULT - DAMAGES FOR DELAY - TIME EXTENSIONS (1969 AUG)
(b) If fixed and agreed liquidated damages are provided in the contract and if the Government so [563]*563terminates the Contractor’s right to proceed the resulting damage will consist of such liquidated damages until such reasonable time as may be required for final completion of the work together with any increased cost occasioned the Government in completing the work.
General Provision 76:
LIQUIDATED DAMAGES (1965 JAN)
In case of failure on the part of the Contractor to complete the work within the time fixed in the contract or any extensions thereof, the Contractor shall pay to the Government as liquidated damages, pursuant to the clause of this contract entitled "Termination for Default - Damages for Delay - Time Extensions,” the sum of $9.70 for each day of delay.

The contract also contained a disputes clause (General Provision 27) which obliges the contractor to continue performance in accordance with the contracting officer’s decision while an appeal is pending.

The plaintiff having exhausted his administrative remedies is seeking relief from this court. He contends that both the default termination and the imposition of liquidated damages were improper.1

Whether or not a default is excusable is, in general, a question of fact. Anthony P. Miller, Inc. v. United States, 161 Ct. Cl. 455, 474, cert. denied, 375 U. S. 879 (1963). Under the Wunderlich Act, this court may only review an administrative decision as to a question of fact to see whether it is "fraudulent or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidence.” 41 U.S.C. § 321. The Board decided the federal government met the requirement of general provision 32 - that inspection was made at the site at reasonable times. There was much conflicting evidence- on the record as to this, but there was sufficient testimony to support the ASBCA’s position. It is undisputed that plaintiff failed to replace the felt although general provision 32(b) requires the contractor to replace nonconforming materials. Provision 32(c) provides that failure to replace [564]*564the material may result in termination of the contract. Although default termination has been termed a "drastic sanction,” J. D. Hedin Construction Co. v. United States, 187 Ct. Cl. 45, 57, 408 F. 2d 424, 431 (1969), this termination is clearly within the contracting officer’s discretion. The contracting officer is obligated to exercise his discretion. Schlesinger v. United States, 182 Ct. Cl. 571, 581, 390 F. 2d 702, 707 (1968).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K-Con Building Systems, Inc. v. United States
107 Fed. Cl. 571 (Federal Claims, 2012)
M. Maropakis Carpentry, Inc. v. United States
84 Fed. Cl. 182 (Federal Claims, 2008)
L & A Jackson Enterprises v. United States
41 Cont. Cas. Fed. 77,117 (Federal Claims, 1997)
Dj Manufacturing Corporation v. United States
86 F.3d 1130 (Federal Circuit, 1996)
Mega Construction Co. v. United States
37 Cont. Cas. Fed. 76,305 (Court of Claims, 1992)
Cegers v. United States
7 Cl. Ct. 615 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
29 Cont. Cas. Fed. 82,028, 229 Ct. Cl. 560, 1981 U.S. Ct. Cl. LEXIS 555, 1981 WL 22058, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skip-kirchdorfer-inc-v-united-states-cc-1981.