K-Con Building Systems, Inc. v. United States

97 Fed. Cl. 41, 2011 U.S. Claims LEXIS 20, 2011 WL 228667
CourtUnited States Court of Federal Claims
DecidedJanuary 24, 2011
DocketNo. 05-914C
StatusPublished
Cited by7 cases

This text of 97 Fed. Cl. 41 (K-Con Building Systems, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
K-Con Building Systems, Inc. v. United States, 97 Fed. Cl. 41, 2011 U.S. Claims LEXIS 20, 2011 WL 228667 (uscfc 2011).

Opinion

OPINION AND ORDER

SWEENEY, Judge.

Plaintiff K-Con Building Systems, Inc. has filed three suits in this court concerning its contracts with the United States Coast Guard (“Coast Guard”) for the design and construction of prefabricated metal buildings in Elizabeth City, North Carolina, St. Peters-burg, Florida, and Port Huron, Michigan. Although the three suits share many similarities, bhere are meaningful differences that require the court to address each suit separately. In the instant case, which concerns the building in Elizabeth City, plaintiff moves for partial summary judgment on the issue of liquidated damages. For the reasons set forth below, the court denies plaintiffs motion.

I. BACKGROUND1

In April 2001, the United States General Services Administration (“GSA”) awarded plaintiff a Federal Supply Schedule contract for Prefabricated Structures and Outdoor Smoking Shelters. PL’s App. 1-9. Subsequently, in September 2003, the Coast Guard solicited proposals for the design and construction of a prefabricated building to house a component repair shop at the Coast Guard Support Center in Elizabeth City. Id. at 10, 38. Plaintiff responded to the solicitation and, on September 23, 2003, the Coast Guard placed an order under plaintiffs GSA contract for the solicited building. Id. The initial value of the order was $513,520 and the initial completion date was June 17, 2004. Id. at 10.

A. The Liquidated Damages Clause

Plaintiffs contract with the Coast Guard contained a standard liquidated damages clause, which provided for liquidated damages of $551 for each day that plaintiff failed to complete the building beyond the contractually set completion date.2 Id. at 26. At [43]*43the time the contract was executed, the Coast Guard was bound by subpart 11.5 of the Federal Acquisition Regulation (“FAR”), which described the general parameters for the use of liquidated damages clauses.3 See, e.g., id. at 210, 215, 220, 228-29. However, it was not subject to any regulations specifying precisely how to determine an appropriate liquidated damages rate. Id. at 204. Further, the Coast Guard had no settled policies or procedures concerning the determination of liquidated damages rates. Id. at 210, 228-29. Rather, the contracting officer, Cathy Broussard, prior to the solicitation of proposals for the project, determined the appropriate rate using a methodology that the Coast Guard had utilized since at least 1997, the year she joined its contracting staff. Id. at 145-46, 209-10, 228-29.

First, Ms. Broussard found that because the Coast Guard would “incur additional costs if the contractor” did not complete the work by the contract deadline and because it would be impossible to ascertain “[t]he extent or exact amount of damages” resulting from the contractor’s failure to meet the deadline, it was appropriate to include a liquidated damages clause in the contract. Id. at 145. She then concluded that the rate of liquidated damages should be based on the “probable actual damages” that the Coast Guard would incur if the contractor breached the contract by failing to complete the work on time. Id. (citing FAR 11.502).

As her next step, Ms. Broussard identified the extra costs that the Coast Guard would incur upon such a breach, breaking them down into two categories: “Travel/Per Diem, Inspection & Miscellaneous Costs” and “Administrative Costs for Government Representatives.” Id. at 145-46. The first category included travel costs for the project manager and a member of the contracting staff, costs for the time of a construction inspector, and miscellaneous costs such as telephone and mail costs. Id. at 145. Ms. Broussard arrived at a total of $8,685 per month for this first category. Id.

The second category encompassed costs for the extra time that would be spent on the project by the Coast Guard personnel involved in the contract’s administration and performance, as measured by the hourly rates for their services. Id. at 146. Ms. Broussard indicated that these costs were “[bjased on the guidelines listed” in the following Coast Guard instruction: Standard Rates, Commandant Instruction 7310.1G (May 29, 2001) (“COMDTINST 7310.1G”). Id. According to its terms, the purpose of the instruction was to establish standard rates for use in computing reimbursable charges, i.e., the cost of services provided to other government agencies and the private sector that were recoverable pursuant to reimbursable agreements. COMDTINST 7310.1G at 1. However, because “[t]he ‘direct’ portion of the standard rates inelude[d] both fixed and variable costs,” the rates were “not [to] be used to calculate reimbursement of ... foreseeable costs related to contracting ac-tions_” Id. at 2. Among the standard rates described in the instruction were those for personnel services. Id. at Enclosure (2).

Using the standard rates for personnel services contained in COMDTINST 7310.1G, Ms. Broussard calculated the annual cost for each Coast Guard employee and then multiplied those costs by a specified percentage that represented the amount of time the employee would spend on the project. PL’s App. 146. She estimated that the Construction Division chief, the Contracting Division chief, and the team leader would spend five percent of their time on the project, the project manager would spend thirty-three percent of his time on the project, the contracting officer would spend ten percent of her time on the project, and the contract specialist would spend twenty percent of her time on the project. Id. These percentages were contained in the Coast Guard’s preexisting template, and Ms. Broussard did not [44]*44know their origin. Id. at 224-25, 228-29. Ultimately, by dividing each annual amount by twelve, Ms. Broussard calculated monthly costs of $583 each for the Construction Division and Contracting Division chiefs, $513 for the team leader, $3,386 for the project manager, $1,026 for the contracting officer, and $1,739 for the contract specialist, arriving at a total monthly cost of $7,830 for the second category. Id. at 146.

As the final step of her process, Ms. Broussard divided the sum of the monthly costs for the two categories by thirty days to calculate the daily liquidated damages rate of $551. Id. At no point did Ms. Broussard make a specific written determination concerning the impact that a liquidated damages clause would have on pricing, competition, and contract administration. Id. at 215, 228-29. Nor did she document any consideration of the importance of the time of delivery or timely performance when determining that a liquidated damages clause was necessary. Id. at 220, 228-29.

B. Contract Performance

As set forth in the contract, the Coast Guard contemplated that plaintiff would design the building based on the contract specifications, submit the design to the Coast Guard in two phases (a “100% design” and a “final design”), and then, upon the Coast Guard’s approval of the final design, begin construction. See generally id. at 37-121 (containing the contract specifications); Def.’s App. 2 (containing minutes of the pos-taward kickoff meeting). The design and construction of the building were to be completed no more than 262 days after contract award. PL’s App. 20.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
97 Fed. Cl. 41, 2011 U.S. Claims LEXIS 20, 2011 WL 228667, Counsel Stack Legal Research, https://law.counselstack.com/opinion/k-con-building-systems-inc-v-united-states-uscfc-2011.