Community Heating & Plumbing Company, Inc. v. Admiral Frank B. Kelso, Ii, Acting Secretary of the Navy

987 F.2d 1575, 38 Cont. Cas. Fed. 76,488, 1993 U.S. App. LEXIS 4508, 1993 WL 66230
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 11, 1993
Docket92-1362
StatusPublished
Cited by206 cases

This text of 987 F.2d 1575 (Community Heating & Plumbing Company, Inc. v. Admiral Frank B. Kelso, Ii, Acting Secretary of the Navy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Community Heating & Plumbing Company, Inc. v. Admiral Frank B. Kelso, Ii, Acting Secretary of the Navy, 987 F.2d 1575, 38 Cont. Cas. Fed. 76,488, 1993 U.S. App. LEXIS 4508, 1993 WL 66230 (Fed. Cir. 1993).

Opinion

BENNETT, Senior Circuit Judge.

This is an appeal from a decision of the Armed Services Board of Contract Appeals (board) denying the claims brought by Community Heating and Plumbing Co., Inc. (Community), against the Secretary of the United States Navy (Navy). 1 The claims arose out of a contract to remove and replace the condensate and steam system located at the Marine Corps Air Station, Cherry Point, North Carolina. Community seeks compensation for; 1) the costs associated with the installation of conduit sleeves in existing manholes; and, 2) the costs which arose from delays experienced by the project. 2 We affirm the decision of the board.

The Conduit Sleeve Claim

On May 18, 1982, Community submitted a bid in response to the Navy’s Invitation for Bids. On May 19, Navy Contract Specialist Rosalind D. Rogers replied by mail informing Community that although it was the apparent low bidder, its bid appeared “somewhat out of line” as compared to the Navy’s estimate and the other bids received. In fact, Community’s estimate for the project was 14% below the Navy estimate and 5% below the second lowest bid received. Accordingly, Ms. Roger’s letter instructed Community to check its proposal and confirm its bid price in writing. In addition, Navy officials decided that if the bid were confirmed, Community should also be required to meet with the Navy officials to reverify the project’s scope. On June 1,1982, Community confirmed its bid, and on June 3 a bid confirmation meeting was held at the Navy’s offices. Those present at the meeting included Mr. Levy for Community and Mr. Manger (LANT-DIV Engineer), Mr. Hiteshaw (the drafter of the project drawings), and Ms. Rogers for the Navy. 3 The only evidence in the record regarding the discussions which took place at the meeting was the testimony of those in attendance and a memorandum written by Ms. Rogers the following day.

On June 4, 1982, the day after the meeting, Mr. Levy wrote a letter to the Navy *1578 referencing the meeting and stating in part:

The items listed below were discussed and approved during our June 3, 1982 conference.
3. The conduit sleeves shown on Sheet M-5 in the lower righthand corner are for the new manholes only for both condensate and steam.

(Emphasis added.)

The Navy responded to Community’s June 4 communication with a letter dated June 21, 1982. That letter made no express objection to Community’s contract interpretation regarding the conduit sleeves, but it did state in part:

The meeting referred to in your letter was held as part of the bid confirmation process in order to insure that you had considered all components of the job in preparing your bid. Contract awards on formally advertised procurements must be made in strict accordance with the terms of the Invitation for Bids.
It is requested that you verify in writing the correctness of your bid in accordance with the Invitation for Bids.

On June 30, 1982, the bid was confirmed in writing, and on July 15, 1982, the contract, No. N62470-81-C-1345, was awarded to Community.

After the contract was awarded, the Navy directed Community to furnish conduit sleeves in new and existing manholes “where needed.” Community then brought a claim for additional compensation, ASBGA No. 38167, arguing that the contract required installation of conduit sleeves at new manholes only. Upon consideration of the evidence, the board ruled in favor of the Navy in a final decision dated February 24, 1992. The board held that the contract was unambiguous since there was “no way” the contract could be construed in the manner advocated by Community. Community now appeals.

Standard of Review

Under 41 U.S.C. § 609(b) (1988), the decision of the board on any question of law is not final or conclusive, but the decision on any question of fact “shall be final and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.” See Triax-Pacific v. Stone, 958 F.2d 351, 353 (Fed.Cir.1992).

Community argues that the contract contained latent ambiguity and, because the June 4 letter gave notice of Community’s contract interpretation, the Navy is bound to that interpretation by its failure to object. Lykes-Youngstown Corp. v. United States, 420 F.2d 735, 190 Ct.Cl. 348, cert. denied, 400 U.S. 865, 91 S.Ct. 102, 27 L.Ed.2d 104 (1970); Maxwell Dynamometer Co. v. United States, 386 F.2d 855, 181 Ct.Cl. 607 (1967); Midwest Transit, Inc., PSBCA No. 1504, 87-3 BCA (CCH) If 20,079 at 101,656. However, Community’s alternate contract interpretation cannot be adopted if the present contract is unambiguous, Perry & Wallis, Inc. v. United States, 427 F.2d 722, 725, 192 Ct.Cl. 310 (1970) (holding that where a contract is not ambiguous, the wording of the contract controls its meaning and resort cannot be had to extraneous circumstances or subjective interpretations), or if the ambiguity is patent. Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985) (holding that the existence of a patent ambiguity raises a duty to inquire, regardless of the reasonableness of contractor’s interpretation).

Community asserts that the contract, as it pertains to the conduit sleeves, is ambiguous. It contests the Navy’s reading of the contract, which was adopted by the board, and argues in favor of an alternative contract interpretation based upon its own reading of the contract language, specifications and drawings. However, contracts are not necessarily rendered ambiguous by the mere fact that the parties disagree as to the meaning of their provisions. Brunswick Corp. v. United States, 951 F.2d 334, 337 (Fed.Cir.1991); Blake Constr. Co. v. United States, 597 F.2d *1579 1357, 1359, 220 Ct.Cl. 56 (1979); John C. Grimberg Co. v. United States, 7 Cl.Ct. 452, 457 (Cl.Ct.), aff'd without opinion, 785 F.2d 325 (Fed.Cir.1985). That the parties disagree with a specification, or that a contractor’s interpretation thereof is conceivable, does not necessarily render that specification ambiguous so as to require that it be construed against the drafter. Ace Constr. Co. v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Langdon Engineering & Mgt
Armed Services Board of Contract Appeals, 2025
Lacy Mechanical, Inc.
Armed Services Board of Contract Appeals, 2024
Vigor Works, LLC
Armed Services Board of Contract Appeals, 2023
The Boeing Company v. United States
968 F.3d 1371 (Federal Circuit, 2020)
Optimization Consulting, Inc.
Armed Services Board of Contract Appeals, 2019
Shaw v. United States
131 Fed. Cl. 181 (Federal Claims, 2017)
Pyrotechnic Specialties, Inc.
Armed Services Board of Contract Appeals, 2017
The Concourse Group, LLC v. United States
131 Fed. Cl. 26 (Federal Claims, 2017)
Level 3 Communications, LLC v. United States
129 Fed. Cl. 487 (Federal Claims, 2016)
T.W. Laquay Marine, LLC v. United States
127 Fed. Cl. 748 (Federal Claims, 2016)
Amador County, California v. Kempthorne
170 F. Supp. 3d 135 (District of Columbia, 2016)
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
987 F.2d 1575, 38 Cont. Cas. Fed. 76,488, 1993 U.S. App. LEXIS 4508, 1993 WL 66230, Counsel Stack Legal Research, https://law.counselstack.com/opinion/community-heating-plumbing-company-inc-v-admiral-frank-b-kelso-ii-cafc-1993.