Nolan Brothers, Inc. v. The United States

437 F.2d 1371, 194 Ct. Cl. 1, 1971 U.S. Ct. Cl. LEXIS 156
CourtUnited States Court of Claims
DecidedFebruary 19, 1971
Docket371-67
StatusPublished
Cited by18 cases

This text of 437 F.2d 1371 (Nolan Brothers, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nolan Brothers, Inc. v. The United States, 437 F.2d 1371, 194 Ct. Cl. 1, 1971 U.S. Ct. Cl. LEXIS 156 (cc 1971).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

DAVIS, Judge.

“The claimant, Nolan Brothers, Incorporated, undertook in August 1962 to construct for the Corps of Engineers two rock jetties out into the Gulf of Mexico from Matagorda Peninsula in Texas. The contract price ultimately amounted to some nine million dollars. In March 1964, when about one-third of the work was done, the defendant exercised its contract right to terminate performance for the Government’s convenience. The contractor did not contest this action but submitted, under the convenience-termination article, its termination claims on the total-cost basis, and efforts were made to settle the demands by negotiation. These were unsuccessful and, as the termination clause contemplated, the contracting officer then issued a unilateral determination in which he allowed the plaintiff $5,386,183 out of the $8,153,902 sought. Nolan Brothers appealed to the Corps of Engineers Board of Contract Appeals which granted only $101,315 more. This action followed.” Nolan Brothers, Inc. v. United States, 405 F.2d 1250, 1252, 186 Ct.Cl. 602, 604 (1969). In that first opinion we held that the convenience-termination was lawful, and that an award pursuant to that provision of the contract was the contractor’s sole remedy. Under that ruling, we dismissed, without passing on its truth, the first count of the petition in which the plaintiff alleged that the Government breached the contract by furnishing an inadequate design and defective specifications for the jetties, and also by negligently failing to apprise the contractor of certain facts. We then returned the case to the trial commissioner to consider, “on the basis of the administrative record under the standards of the Wunderlich Act”, the remaining claim that the Board of Contract Appeals had been wrong in failing to enlarge the termination award. 1 The commissioner was also to consider the counterclaims filed by the Government *1374 attacking aspects of the case in which the Board upheld the contractor. Plaintiff asks for $1,272,555 additional, and the defendant demands $1,155,190 back.

Trial Commissioner Mastín G. White has written a careful and comprehensive opinion covering the termination-award issues still in dispute, and each of the parties has sought review of certain adverse parts of his recommendation. 2 We depart from him on the major question relating to pre-termination equipment ownership expense for interest, taxes, storage, and insurance. This is discussed in Part I of this opinion (along with related subsidiary matters). In Part II, we adopt, for the most part, Commissioner White’s opinion on the remaining issues in the case.

I

Pre-termination Equipment Ownership Expense

The convenience-termination article (clause 23) provided (in paragraph (e)) that, in such a termination, the contractor should be reimbursed for: the total cost of all contract work performed prior to termination; the cost of settling and paying claims arising out of the termination under subcontracts or orders; the reasonable cost of the preservation and protection of property; any other reasonable costs incidental to the termination; and a specified percentage as profit. Under these standards, the parties have agreed that the plaintiff is entitled to be reimbursed for the expense arising from the ownership of its equipment on the job prior to the termination of the contract. The parties do not agree, however, concerning the amount that should be allowed with respect to this item. The Board awarded $875,000 for equipment ownership expense during the pre-termination period. Plaintiff contends that the Board should have allowed it $1,502,956. On the other hand, the defendant alleges in one of its counterclaims that the plaintiff should have been given only $404,118, instead of $875,000.

1. Nolan’s controversy with the Board centers on the use of the Contractors’ Equipment Ownership Expense Schedule, published by the Associated General Contractors of America, Inc. (“AGC”). This manual, first put out in 1920, is a widely-used guide to construction contractors’ equipment ownership expense, reflecting both the experience of equipment owners throughout the country and also the average of operating conditions. In tabular form, the schedule lists numerous forms of construction equipment, and for each one gives the percentages of capital investment in the item to be charged off annually for the three following expense-categories: depreciation; major overhauling and repair; interest, taxes, storage, insurance. It also states the average number of months that the particular item is likely to be used per year, and the contractor’s expense for that item per working month. 3

*1375 The theory of the Schedule, to use its own words, is that “the annual equipment expense * * * must be recovered by a contractor from the work that he performs. To do this, it is necessary to establish for each item a monthly charge of such amount that when multiplied by the average of working months it will yield a revenue equal to the annual expense * * For instance, the expense of storing equipment between jobs must be recovered from the jobs worked, even though no storage may have occurred during the performance of those particular jobs. All proper expenses during the life of the item are allocable and allocated to the periods the equipment is actually working.

In determining the amount of plaintiff’s pre-termination equipment ownership expense, the Board based the allowances for depreciation, and for major repairs and overhaul, on this AGC Schedule, but it did not do the same for interest, taxes, storage, and insurance. For those classes of cost, it declined to follow the Schedule. Nothing was allowed for interest, and the sum for taxes, storage, and insurance was based on figures said to be the plaintiff’s actual expenditures, with respect to the equipment, for those cost-elements during the pre-termination period. Plaintiff’s claim is that the AGC Schedule should have been used for the latter group of cost-items, as well as for depreciation and major overhaul. The defendant supports the Board.

The settlement of this dispute turns, not so much on general principles of contract law or on judicial precedent, as on the provisions of a particular Defense Department regulation. The convenience-termination clause in this contract expressly said that “any determination of costs” for a unilateral (i. e. nonnegotiated) termination award, such as we have here, “shall be governed by the principles for consideration of costs set forth in Section 15, Part 4 of the Armed Services Procurement Regulation, as in effect on the date of this contract.” One of those cost principles is contained in ASPR 15-402.1, which deals with the very subject before us. 4 *1376 The meaning and reach of that regulation controls the answer to the controversy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Red River Holdings, LLC v. United States
802 F. Supp. 2d 648 (D. Maryland, 2011)
White Buffalo Construction, Inc. v. United States
52 Fed. Cl. 1 (Federal Claims, 2002)
McDonnell Douglas Corp. v. United States
42 Cont. Cas. Fed. 77,274 (Federal Claims, 1998)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Edo Corporation v. Beech Aircraft Corporation
911 F.2d 1447 (Tenth Circuit, 1990)
Servidone Construction Corp. v. United States
36 Cont. Cas. Fed. 75,797 (Court of Claims, 1990)
G.M. Shupe, Inc. v. United States
32 Cont. Cas. Fed. 72,712 (Court of Claims, 1984)
Holloway Construction Co. v. United States
32 Cont. Cas. Fed. 72,389 (Court of Claims, 1984)
A. J. Baltes, Inc. v. Department of Highways
13 Ct. Cl. 1 (West Virginia Court of Claims, 1979)
Meva Corp. v. United States
511 F.2d 548 (Court of Claims, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
437 F.2d 1371, 194 Ct. Cl. 1, 1971 U.S. Ct. Cl. LEXIS 156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nolan-brothers-inc-v-the-united-states-cc-1971.