L. L. Hall Construction Company v. The United States

379 F.2d 559, 177 Ct. Cl. 870, 1966 U.S. Ct. Cl. LEXIS 110
United States Court of Claims·Decided December 16, 1966·No. 269-61·Published·Cited by 46 cases

Opinion

OPINION

PER CURIAM.

This case was referred to Chief Trial Commissioner Marion T. Bennett with directions to make findings of fact and recommendation for conclusions of law. The commissioner has done so in an opinion and report filed on September 20, 1966. On October 17, 1966, the parties filed a joint motion that the court adopt and publish in its entirety as the opinion and findings of the court the opinion and findings of the commissioner. Since the court is in agreement with the opinion, findings and recommendation of the commissioner, it hereby adopts the same as the basis for its judgment in this case, as hereinafter set forth. Plaintiff is, therefore, entitled to recover from defendant the sum of $18,004.51 and judgment is entered for plaintiff in that amount.

OPINION OF COMMISSIONER *

BENNETT, Chief Commissioner.

This action for breach of contract arises out of an agreement between plaintiff and the defendant,, the latter acting through the Department of the Navy, Bureau of Yards and Docks, for the repair, restabilization of runway overruns, and the improvement of crash strips at the U. S. Naval Air Station, Cecil Field, Florida, at a total cost of $186,417.74. This contract contained the standard general provisions in Government construction contracts for changes, changed conditions, termination, and disputes, but there was no suspension-of-work clause.

In general, plaintiff sues because of the failure of defendant to make available the necessary runways for timely *561 completion of plaintiff’s work. The reason given by defendant for delay was that the remaining runways were required for military operations, since those plaintiff had worked on were still being repaired by other contractors at the site. Plaintiff’s equipment was thereby idled, eventually removed from the site, and used on other jobs. It was returned some 3 months later for completion of this contract. This and other delays, aggregating about 5 months, caused additional expense to plaintiff, not contemplated at the time of the original contract, and was contrary to the terms and intent of the contract. After a trial de novo, it is concluded upon the law and the facts that plaintiff is entitled to recover delay-damages, although not to the extent claimed. The facts are set forth in the findings and will be summarized here.

I

Cecil Field consists of two pairs of parallel runways, two running north and south and two running east and west. Navy regulations at this installation require that at least one runway in each direction be available for military use at all times.

This contract (No. NBy-19936, Spec. 19936/58) was entered into by the parties on June 30, 1959, and provided that work should commence on July 5, 1959, and should be completed 60 days thereafter on September 3, 1959. Defendant held a preconstruction conference on July 2, 1959, to advise plaintiff of various aspects of the contract, including the fact that other contractors would be performing work simultaneously with plaintiff on these runways. At that time defendant did not contemplate, and plaintiff did not anticipate, any lengthy shutdown of the type later encountered by plaintiff.

Plaintiff began work on July 6, 1959, and proceeded diligently until about 50 percent of the work was completed in late July 1959. On or about July 29, 1959, plaintiff requested that defendant make the adjacent runways available so that plaintiff could complete its work. Plaintiff was denied access to such runways until the other contractors at the site had completed work on runways where plaintiff had already finished. This was because it was necessary to maintain flight operations. However, defendant estimated such access could be given on or about Sptember 15, 1959. Further efforts failed to obtain the additional runways in August, and plaintiff proceeded at a greatly reduced tempo, idling its equipment where necessary and removing it to other jobs where possible. Plaintiff was not permitted to continue operations about September 15 as anticipated, so by the end of September all plaintiff’s equipment had been removed from the jobsite.

Toward the latter part of November 1959, it became clear to plaintiff’s representative at Cecil Field, through his contacts with defendant, that plaintiff would be allowed to continue work in the near future, and plaintiff began re-mobilizing during late November and early December. On December 2, 1959, defendant advised plaintiff it could commence work on December 7, 1959, on one runway, that on December 14 another would be available, and that by about December 21 the last runway would also be available. Plaintiff was allowed to commence work on December 8, one day after it expected to do so, and when it requested that it be allowed to continue work on the last runway on December 21 as expected, and as defendant had previously advised, plaintiff was denied access to this runway until January 14, 1960. Plaintiff satisfactorily completed the contract on February 2, 1960, and was granted extensions of time through and including this date (152 days) at no change in the contract price. The contracting officer found that the delays were beyond the control and without fault or negligence on plaintiff’s part. Liquidated damages assessed were refunded.

Plaintiff submitted its claim for equitable adjustment under the contract to the resident officer in charge of con *562 struction and the base commanding officer on May 27, 1960, and thereafter to the contracting officer through the officer in charge of construction. Plaintiff was denied recovery on the grounds that its claim was for additional costs due to delays — a claim for damages for breach and not for additional work performed, and thus could not be the subject of compensation under the contract. Plaintiff appealed to the Armed Services Board of Contract Appeals which affirmed that the board was without authority to adjust the contract price to compensate for damages due to a delay. The board dismissed plaintiff’s claim on defendant’s motion. Thereupon, plaintiff filed timely suit in this court. The claim is properly in this court because it could not be resolved administratively under the contract provisions for adjustment of disputes. United States v. Anthony Grace & Sons, 384 U.S. 424, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966); United States v. Utah Constr. & Mining Co., 384 U.S. 394, 86 S.Ct. 1545, 16 L.Ed.2d 642 (1966). The only relevant finding of fact made administratively was that plaintiff was not to blame for the delay, and that finding is adopted here.

II

Free access — add to your briefcase to read the full text and ask questions with AI

L. L. Hall Construction Company v. The United States, 379 F.2d 559, 177 Ct. Cl. 870, 1966 U.S. Ct. Cl. LEXIS 110 (cc 1966).

379 F.2d 559 (L. L. Hall Construction Company v. The United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Al Ghanim Combined Group W.L.L.
Armed Services Board of Contract Appeals, 2026
XL Specialty Insurance v. Massachusetts Highway Department
31 Mass. L. Rptr. 147 (Massachusetts Superior Court, 2013)
Yankee Atomic Electric Co. v. United States
73 Fed. Cl. 249 (Federal Claims, 2006)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
Precision Pine & Timber, Inc. v. United States
50 Fed. Cl. 35 (Federal Claims, 2001)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Mega Construction Co. v. United States
37 Cont. Cas. Fed. 76,305 (Court of Claims, 1992)
Municipality of Anchorage v. Frank Coluccio Construction Co.
826 P.2d 316 (Alaska Supreme Court, 1992)
Amp-Rite Electric Co. v. Wheaton Sanitary District
580 N.E.2d 622 (Appellate Court of Illinois, 1991)
J.R. Youngdale Construction Co. v. United States
37 Cont. Cas. Fed. 76,135 (Court of Claims, 1991)
Colorado Environments, Inc. v. Valley Grading Corp.
779 P.2d 80 (Nevada Supreme Court, 1989)
PBI Electric Corp. v. United States
35 Cont. Cas. Fed. 75,669 (Court of Claims, 1989)
Ceco Corp. v. Carson Concrete Corp.
691 F. Supp. 850 (E.D. Pennsylvania, 1988)
New Pueblo Constructors, Inc. v. State
696 P.2d 185 (Arizona Supreme Court, 1985)
Cedar Lumber, Inc. v. United States
32 Cont. Cas. Fed. 72,561 (Court of Claims, 1984)
Arcon Construction Co. v. South Dakota Cement Plant
349 N.W.2d 407 (South Dakota Supreme Court, 1984)
Holloway Construction Co. v. United States
32 Cont. Cas. Fed. 72,389 (Court of Claims, 1984)
Degenaars Co. v. United States
31 Cont. Cas. Fed. 71,186 (Court of Claims, 1983)