J.R. Youngdale Construction Co. v. United States

37 Cont. Cas. Fed. 76,135, 23 Cl. Ct. 460, 1991 U.S. Claims LEXIS 304, 1991 WL 130539
CourtUnited States Court of Claims
DecidedJuly 16, 1991
DocketNo. 207-89C
StatusPublished

This text of 37 Cont. Cas. Fed. 76,135 (J.R. Youngdale Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.R. Youngdale Construction Co. v. United States, 37 Cont. Cas. Fed. 76,135, 23 Cl. Ct. 460, 1991 U.S. Claims LEXIS 304, 1991 WL 130539 (cc 1991).

Opinion

[461]*461OPINION

SMITH, Chief Judge.

This contracts case comes before the court after the contracting officer denied the plaintiff’s request for an equitable adjustment. It arose under an April 26, 1986 contract between J.R. Youngdale Construction Company, Inc. (Youngdale) and the United States Army Corps of Engineers (Corps), for the construction of a dental clinic at Fort Irwin, California. Based upon both parties’ motions for summary judgment, their oral arguments, and an analysis of the law, the court grants the government’s motion and denies the plaintiff's cross-motion. While this result may impose a real economic loss on the plaintiff, it is fundamental to the theory of contractual freedom to make parties responsible for their choices.

FACTS

On January 16, 1985, the Corps released solicitation no. DACA05-85-B-0045 for the construction of a dental clinic at Fort Irwin’s desert training center. On March 6, 1985, the Corps determined that Youngdale was the low bidder at $2,373,379.00. Youngdale confirmed the amount on March 22, 1985.

Pursuant to Federal Acquisition Regulations (FAR), 48 C.F.R. §§ 9.104-l(c), 9.104-3(c), 9.105-1 (1984), the Corps requested a list of all contracts from Youngdale with the federal government in excess of $1,000,000.00. At the time plaintiff had eleven such government contracts. After hearing that seven of those contracts were not being performed satisfactorily, on April 22,1985, the contracting officer determined that Youngdale was not a responsible bidder. The contracting officer then referred the matter to the Small Business Administration’s (SBA) Regional Office for its determination on a Certificate of Competence (COC), per the FAR, 48 C.F.R. § 19.601 (1984).

Upon submission to the SBA, the Corps agreed to withhold award until May 24, in order to permit the SBA to make a determination. On May 22, the SBA notified the contracting officer that it would be “recommend[ing] to the [SBA] Central Office that the COC be issued.” The contracting officer called the SBA's Regional Office to protest this response. On May 30, the contracting officer wrote the Regional Office, stating his disagreement with the SBA’s recommendation. He further mentioned that both Youngdale and the next lowest bidder, Inland, had extended their bids to June 20. On June 11, the SBA Regional Office notified the contracting officer that the Central Office had the case for final disposition. The SBA also told the contracting officer that the 10-day appeal period mandated by the FAR, 48 C.F.R. § 19.-602-3(c) (1984), was to be held in abeyance until a decision had been reached.

On June 18, 1985, the Central Office notified the contracting officer that it did not have time to review the Regional Office’s decision and would therefore grant the COC. On June 20, the Central Office again contacted the contracting officer, informing him that the case was in “suspense” pending possible appeal within the required 10-day period. The contracting officer did not reply. He awarded the contract to Inland, the next lowest bidder, on June 26.

Youngdale and the SBA appealed the contracting officer’s actions to the Comptroller General. On October 28, 1985, the Comptroller General held that the contracting officer’s actions were improper and that the contract should be awarded to Youngdale. The Comptroller General determined that the June 18 telephone conversation was sufficient notice under 48 C.F.R. § 19.602-3(b) (1984). Further, the Comptroller General pointed out that the contracting officer was by law required to accept the SBA’s decision on the COC. 15 U.S.C. § 637(b)(7) (1982); 48 C.F.R. § 19.-602-4 (1984).

The Corps requested a reconsideration of the decision. On February 20, 1986, the Comptroller General issued decision B-219439.2, which affirmed his previous decision. In buttressing his finding, the Comptroller General cited a June 14 Corps memorandum, which Youngdale had received [462]*462pursuant to a Freedom of Information Act request, in which the following appears:

It is assumed that prior to or on 20 Jun [sic] 85, the SBA Central Office will tele-phonically contact the contracting officer or his representative. Per advice of legal counsel, the following outlines our strategy for action.
a. If SBA advises the contracting officer that their preliminary decision is to issue a COC but that a COC has not actually been signed by the appropriate SBA official, then the Corps should immediately award the contract to the second low bidder ...
b. If SBA has issued the COC, then the Corps must award to J.R. Youngdale____

Comp.Gen. B-219439.2, at 4-5 (February 20, 1986).

The Corps was required to award the contract to Youngdale, if Youngdale wished to accept. On March 11, 1986, the Corps wrote to Youngdale, requesting: that Youngdale hold open its bid for 120 days; that Youngdale confirm its willingness to accept at the original bid price of $2,373,379.00. This letter also stated that the Corps was aware of Youngdale’s difficulty in getting the subcontractors to hold their bids.

In a telegram dated March 18, 1986, Youngdale assented to the Corps’ demands, stating that, “this will confirm our willingness to accept the award of subject project in the amount of $2,373,379.00 and our further extension of that bid for an additional 90 days from this date.’’ Youngdale and the Corps signed contract number DACA05-85-B-0045 on April 26, 1986. Notice to proceed was given on June 16, 1986. Youngdale did not amend the contract to include damages or the right to pursue damages caused by the delay. There were no ancillary agreements.

On May 11, 1987, Youngdale made a certified claim to the Corps for an equitable adjustment of $462,597.00. Several of Youngdale’s subcontractors’ rates had increased.1 On February 7, 1989, the Corps denied the claim.

DISCUSSION

Youngdale, in its briefs and at oral argument, has alleged that the government is liable through an implied-in-fact contract. In the alternative, Youngdale argues that the government breached the express contract, ultimately signed on April 26, 1986, which contract included suspension and change of work clauses. Both arguments fail.

Implied-In-Fact Contract

Addressing the implied-in-fact contract first, defendant, in its Motion for Leave to Bring Additional Authority to the Attention of the Court, cites the only apparent foursquare case, K-W Constr., Inc. v. United States, 671 F.2d 481, 229 Ct.Cl. 413 (1982). K-W is not favorable to Youngdale.

In K-W, the plaintiff was scheduled to receive a contract to build a structure at Mather A.F.B. in California.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L. L. Hall Construction Company v. The United States
379 F.2d 559 (Court of Claims, 1966)
Heyer Products Company v. United States
140 F. Supp. 409 (Court of Claims, 1956)
Prestex, Inc. v. United States
31 Cont. Cas. Fed. 71,508 (Court of Claims, 1983)
Sun Oil Co. v. United States
572 F.2d 786 (Court of Claims, 1978)
DeMatteo Construction Co. v. United States
600 F.2d 1384 (Court of Claims, 1979)
K-W Construction, Inc. v. United States
671 F.2d 481 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,135, 23 Cl. Ct. 460, 1991 U.S. Claims LEXIS 304, 1991 WL 130539, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jr-youngdale-construction-co-v-united-states-cc-1991.