Asphalt Paving Co. v. United States Fidelity & Guaranty Co.

671 P.2d 1013, 1983 Colo. App. LEXIS 978
CourtColorado Court of Appeals
DecidedMay 12, 1983
Docket81CA0072
StatusPublished
Cited by8 cases

This text of 671 P.2d 1013 (Asphalt Paving Co. v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Asphalt Paving Co. v. United States Fidelity & Guaranty Co., 671 P.2d 1013, 1983 Colo. App. LEXIS 978 (Colo. Ct. App. 1983).

Opinion

STERNBERG, Judge.

Asphalt Paving Company (APC) appeals the amount of damages awarded to it on its claim against United States Fidelity & Guaranty Company (USF & G) under a performance bond. We reverse in part and remand for additional findings.

APC was awarded a contract by the Colorado Department of Highways to construct a three-mile segment of highway. APC awarded a subcontract to H.L. Gracik Construction, Inc., for certain ground preparation and finishing work. USF & G wrote a performance bond on the Gracik subcontract.

The subcontract provided that if Gracik defaulted, APC could do Gracik’s work and charge the cost to Gracik. Additionally APC could collect liquidated damages to reimburse it for any liquidated damages charged by the state to APC as a result of Gracik’s delay. Gracik further agreed to hold APC “harmless from all loss, cost or expense resulting either directly or indirectly” from the failure of Gracik to carry out the provisions of the subcontract. The prime contract was to be completed within 180 working days, and, according to a project schedule, Gracik had 135 working days to complete its work. According to the testimony of an officer of APC, there was an understanding with Gracik that its performance would be completed sooner than the 135 days allotted.

In mid-December, after 106 working days, the project was shut down for the winter. In February, when Gracik did not respond to APC’s requests to resume work, APC declared Gracik in default and notified Gracik and USF & G of its intention to complete the contract using its own labor *1015 and equipment. The entire project was completed one day late, although it took more than the allotted 135 days to complete Gracik’s portion of the work. APC submitted invoices to USF & G for material and equipment charges incurred to complete the project but USF & G refused to pay.

APC sued USF & G on the bond, seeking its direct labor costs; increased labor costs allegedly caused by the delay; indirect payroll expenses such as insurance and taxes, overhead, material, and equipment costs; profit on its cost to complete; and interest on both the invoices submitted to USF & G, and on funds withheld from it by the Department of Highways as a result of claims filed against Gracik. The trial court awarded only a portion of these amounts.

APC appeals, alleging error in the amount awarded for equipment expenses, and in the court’s failure to award any damages for increased labor costs, indirect payroll expenses, overhead, and interest.

I. Equipment Expenses

APC owned nearly all of the equipment it used to complete Gracik’s work. The equipment expenses claimed by APC were computed by using rental rates compiled by the Department of Highways. These rates were based on ownership, maintenance, and repair costs, with ownership costs figured as a percentage of the acquisition costs of new equipment. At trial, USF & G contested these figures as not being a reasonable reflection of APC’s costs because APC owned and had fully depreciated most of the equipment. USF & G did not, however, submit substitute figures.

The trial court found the method used by APC to compute its equipment expenses was not a reflection of its cost to complete the project, and awarded approximately two-thirds of the amount APC claimed. The amount is purportedly based on figures submitted by APC, which are not a part of the trial court’s record.

USF & G’s obligation on the bond was to hold APC harmless for all cost and expense caused by Gracik’s default. Because APG did not rent the equipment and did not claim that it would have rented its equipment to others at Department of Highway rates had it not been in use on this job, we agree with the trial court’s conclusion that the Department of Highway’s figures did not reflect APC’s equipment costs for the purposes of awarding damages in a contract case. See L.L. Hall Construction Co. v. United States, 379 F.2d 559 (Ct.Cl.1966). There being support in the record for the trial court’s conclusion in this regard, it is binding on review.

The document relied on by the trial court in its damage award was not admitted into evidence and thus cannot support the award of damages. Where, as here, a trial court’s findings of fact do not enable a reviewing court to determine the basis for an award of damages, a remand for more detailed findings of fact is appropriate. Murray v. Rock, 147 Colo. 561, 364 P.2d 393 (1961).

An evidentiary foundation for an award of damages did exist: The record reveals that the rates upon which APC would normally have based its bid for these items were available and are a reasonable estimate of APC’s cost to complete the job. Accordingly, this part of the judgment is remanded for supplemental findings on the reasonable charge for the equipment APC used to complete Graeik’s performance.

II. Increased Labor Costs

The trial court awarded damages to compensate APC for the wages it paid its own labor force to complete Gracik’s work. In addition to this amount, APC claimed damages for a wage increase that became effective before the project was completed, alleging it would have completed the project before the increase became effective had Gracik performed according to the schedule. APC asserts the trial court erred in not awarding damages for this amount. We disagree with this contention.

APC argued that it should have been compensated for the wage increase because it was an expense caused by Gracik’s default, and as support for this contention cites Grow Construction Co. v. State, 56 App.Div. 95, 391 N.Y.S.2d 726 (1977), and L.L. Hall v. United States, supra. Those *1016 cases would support APC’s claim if the trial court had found that Gracik’s delay was unjustified or that it unreasonably interfered with timely performance. However, there was no evidence that Gracik’s falling behind schedule was unjustified or that APC would otherwise have completed the project prior to the scheduled wage increases. APC did claim that it had to redo much of Gracik’s work because it was not done according to specifications, but it was unable to produce evidence that any of the work had been rejected. In the absence of evidence that Gracik’s default caused this expense, the trial court properly denied this claim.

III.Indirect Payroll Expenses

The trial court did not state a reason for rejecting APC’s claim for the payroll taxes, insurance, payroll processing expenses, and other costs associated with the labor it supplied to complete Gracik’s work. The parties disputed the appropriate percentage of direct payroll expenses on which to compute such costs, but there was no dispute that this expense was a “cost or expense” incurred by APC to complete Gra-cik’s performance. Based on the terms of the contract, we conclude as a matter of law that Gracik was liable for these expenses. See Connell v. Sun Oil Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pat's Construction Service, Inc. v. Insurance Co. of the West
141 P.3d 885 (Colorado Court of Appeals, 2005)
Rodgers v. Colorado Department of Human Services
39 P.3d 1232 (Colorado Court of Appeals, 2001)
Rotenberg v. Richards
899 P.2d 365 (Colorado Court of Appeals, 1995)
Mesa Sand & Gravel Co. v. Landfill, Inc.
759 P.2d 757 (Colorado Court of Appeals, 1988)
Riva Ridge Apartments v. Robert G. Fisher Co.
745 P.2d 1034 (Colorado Court of Appeals, 1987)
E.B. Jones Construction Co. v. City & County of Denver
717 P.2d 1009 (Colorado Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
671 P.2d 1013, 1983 Colo. App. LEXIS 978, Counsel Stack Legal Research, https://law.counselstack.com/opinion/asphalt-paving-co-v-united-states-fidelity-guaranty-co-coloctapp-1983.