Southgate Water District v. City & County of Denver Ex Rel. Board of Water Commissioners

862 P.2d 949, 17 Brief Times Rptr. 6, 1992 Colo. App. LEXIS 471, 1992 WL 387059
CourtColorado Court of Appeals
DecidedDecember 31, 1992
Docket89CA1719
StatusPublished
Cited by8 cases

This text of 862 P.2d 949 (Southgate Water District v. City & County of Denver Ex Rel. Board of Water Commissioners) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southgate Water District v. City & County of Denver Ex Rel. Board of Water Commissioners, 862 P.2d 949, 17 Brief Times Rptr. 6, 1992 Colo. App. LEXIS 471, 1992 WL 387059 (Colo. Ct. App. 1992).

Opinion

Opinion by

Judge REED.

In this action for declaratory relief, the controversy at issue concerns the validity of various monetary charges imposed upon plaintiff, the Southgate Water District, under a written Participation Agreement between it and defendant, the City and County of Denver, acting through its Board of Water Commissioners. We affirm in part and vacate in part.

Under the terms of the agreement at issue, Denver constructed an extension to and enlargement of its water distribution facilities to supply treated water to an area located outside Denver’s city limits, part of which is serviced by Southgate. Thereafter, disputes arose between the parties as to the charges made by Denver for South-gate’s share of the construction costs under the agreement. As a result, Southgate instituted the present action seeking declaratory relief as to some of these items (some of which had been paid by Southgate and for which reimbursement was sought).

Specifically, Southgate claims that certain “participation charges” made by Denver were in breach of the written agreement because they were in excess of the actual cost of construction attributable to Southgate’s use of the extended system. Except as to certain items which are not the subject of this appeal, the trial court found that these disputed charges were in compliance with the agreement and that Southgate was liable therefor. As to these charges, we affirm the ruling of the trial court.

Southgate also contends that other charges for particular items of administrative expenses, allocation of overhead, and damage claims are not authorized under the contract and challenges the trial court’s denial of its claims regarding such charges. As to this portion of the judgment, we affirm in part and vacate in part.

In addition to its claims for breach of contract, Southgate contends that Denver, in supplying water to Southgate’s service area and in charging for the construction costs attendant thereto, was operating as a public utility. It thus sought a judicial declaration that the participation charges, notwithstanding Southgate’s agreement to them in the written contract, violate the standards of reasonableness applicable to utility rate making because they did not appropriately reflect the cost of service to *952 Southgate or to its utilization of the system. Accordingly, it sought judicial review of those charges to conform to a “reasonable” standard.

With respect to these claims, the trial court’s judgment declared that Southgate was liable on the basis of its contractual agreement and that the provisions of § 31-35 — 402(l)(f), C.R.S. (1986 RepI.VoI. 12B) preclude judicial review as to the reasonableness of the same. We agree and affirm the judgment of the trial court dismissing Southgate’s claim for judicial review.

I.

In this case, Southgate, a quasi-municipal corporation organized under the Colorado Special District Act, § 32-1-101, et seq., C.R.S., was the purchaser and distributor of water supplied by defendant, the City and County of Denver. At all relevant times, Denver was acting through its Board of Water Commissioners (Water Board), which is responsible for setting rates and charges for water service customers inside and outside the municipal limits.

The Participation Agreement at issue here was signed January 26, 1982. Before that time, by attachment to and extension of Denver’s integrated system into the Southgate area, Denver supplied water to Southgate pursuant to two successive distributorship contracts entered into in July 1961 and April 1981. By the terms of these agreements, Denver was granted the exclusive right to supply water to South-gate for service to the latter’s customers in Arapahoe and Douglas counties. Denver, in turn, was obligated to continue this service as long as it had surplus water available after satisfying the needs of the Denver inhabitants. This contractual undertaking was for an indefinite duration, subject to rights of termination including that by mutual consent.

By the early 1980’s, many areas within the Southgate service area were preparing for further development, and Southgate, under the existing system, had neither the capacity to meet contemplated peak load demand nor the ability to operate its water system to render optimum service at the area’s ultimate development.

As a result, Southgate sought to make additional contractual arrangements with Denver for the latter physically to expand its facilities within the Southgate area. This included extension of existing conduits and increasing the storage capacity to supply the expanded system.

Thus, a series of negotiations took place during 1980 and 1981 between Southgate and Denver, which resulted in the Participation Agreement at issue here. That contract identified seven major water facilities necessary to alleviate existing service problems and accommodate new development in Southgate. It provided that Denver was required to construct transmission, pumping, and storage facilities, including additional reservoir and pumping capacity and the extension of both main line and interconnecting conduit, to achieve an integrated or looped system of distribution fed by several reservoirs.

In order to meet the anticipated demands of other water districts also located in this general area, the contract included a provision that Denver would construct the new facilities larger than that necessary to meet the requirements of Southgate alone. A further condition was that, in the event the parties were unable to agree regarding design criteria, Denver’s engineering analysis involved in sizing and costs of each component facility would prevail. The contract also provided that title to the facilities would vest in Denver upon completion of construction.

The actual facilities to be constructed as outlined under the contract are: a 48-inch conduit, no. 55; a 60-inch conduit, no. Ill; a 48-inch conduit, no. 128; a 60-inch conduit, no. Ill, phase I; Lone Tree reservoir; Lone Tree pump station (with specified structure and capacity); and Highlands pump station (with specified structures and capacity).

The contract contained a specific schedule in which each of these facilities is list *953 ed. As to each facility there is set forth the estimated total cost, the percentage of the actual costs that Southgate is obligated to pay (and the estimate thereof), and the portion of the total costs to be borne by Denver and another water district.

One of the major issues on appeal concerns the charges for the conduits and the method by which they were computed under the contract.

Central to this issue is the undisputed fact that, with the knowledge of both parties, the conduits were described in the contract as, and were built, “oversize,” that is, in excess of Southgate’s needs. This allowed excess capacity in the system for Denver’s sale to third parties.

In order to compute the percentage of total cost to be paid by Southgate, there was first computed the estimated cost of a conduit to meet the capacity requirements of Southgate alone. This figure was then divided by the estimated cost of the oversize conduit to be built. This resulted in an agreed percentage of the actual costs of the oversized conduit to be paid by South-gate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BP Am. v. Colo
2016 CO 23 (Supreme Court of Colorado, 2016)
BP America Production Co. v. Colorado Department of Revenue
2016 CO 23 (Supreme Court of Colorado, 2016)
Nixon v. City & County of Denver
2014 COA 172 (Colorado Court of Appeals, 2014)
BP America Production Co. v. Colorado Department of Revenue
2013 COA 147 (Colorado Court of Appeals, 2013)
Kincheloe v. Milatzo
678 P.2d 855 (Wyoming Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
862 P.2d 949, 17 Brief Times Rptr. 6, 1992 Colo. App. LEXIS 471, 1992 WL 387059, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southgate-water-district-v-city-county-of-denver-ex-rel-board-of-water-coloctapp-1992.