Riva Ridge Apartments v. Robert G. Fisher Co.

745 P.2d 1034, 1987 Colo. App. LEXIS 777
CourtColorado Court of Appeals
DecidedMay 14, 1987
Docket84CA0579
StatusPublished
Cited by12 cases

This text of 745 P.2d 1034 (Riva Ridge Apartments v. Robert G. Fisher Co.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riva Ridge Apartments v. Robert G. Fisher Co., 745 P.2d 1034, 1987 Colo. App. LEXIS 777 (Colo. Ct. App. 1987).

Opinion

SMITH, Judge.

Defendants, Robert G. Fisher Company, Inc. (Fisher) and The American Insurance Company (bonding company), appeal the joint and several judgment of the trial court entered in favor of plaintiffs in the amount of $4,729,130 on their claims arising out of the alleged breach of a construction management agreement. Plaintiffs, Riva Ridge Apartments (Riva Ridge), a limited partnership, and its successor in interest, American Development Corporation (ADC), cross-appeal the trial court’s entry of summary judgment denying plaintiffs claim for punitive damages. We affirm in part, modify in part, and reverse in part.

In June 1978, Riva Ridge entered into a contract wherein Fisher agreed to serve as construction manager for an apartment complex it was building in Lakewood, Colorado. Pursuant to the written construction management agreement, Fisher agreed to manage the construction and it guaranteed both that the total building cost would not exceed a fixed dollar amount and that the project would be completed within established deadlines.

The final guaranteed cost was subject to adjustment only as a result of owner initiated changes or unavoidable delays. However, if the costs as finally agreed to by the parties exceeded the guaranteed maximum amount, Fisher was obligated to bear the additional cost, and, if the deadlines were not met, it was required to pay liquidated damages for the delay. Alternatively, Fisher was entitled to bonuses for early completion of the various project buildings.

In connection with the agreement, Fisher as principal and the bonding company as surety executed a performance bond in the amount of $3,934,000 securing Fisher’s performance. The bonding company’s obligations under the performance bond were conditioned upon Fisher’s having defaulted and plaintiffs having performed all of their obligations under the construction management agreement.

Various problems and delays occurred during construction of the apartments, which were changed during construction to condominiums, and ADC, successor to Riva Ridge, ultimately discharged Fisher as construction manager in February 1979. Demand was made upon the bonding company to complete Fisher’s performance under the performance bond but it refused to do so.

ADC subsequently completed seven of the ten buildings included in the project, and at the time of trial had entered into a contract for completion of the remaining three buildings. The cost to complete all ten of the buildings is substantially in excess of the original price guaranteed by Fisher. Plaintiffs initiated this suit against Fisher and the bonding company to recover the additional costs incurred in construction of the condominiums.

I.

We first address plaintiffs’ contention raised on cross-appeal that the trial court erred, prior to trial, in granting a partial summary judgment dismissing its claim for *1037 punitive damages. We agree that this was error.

Plaintiffs alleged in their complaint, inter alia, that the bonding company’s refusal to remedy Fisher’s default, to complete the project or to obtain others to complete the project, as required by the terms of the performance bond, involved conduct which, in itself, constituted outrageous conduct and a wilful and wanton disregard of the rights of plaintiffs. Based on these allegations, they sought an award of punitive damages in excess of $400,000.

Defendants’ motion for summary judgment sought dismissal of that claim on the basis that, as a matter of law, exemplary damages cannot be awarded on a contract claim. In granting this motion the trial court concluded that despite the wording of plaintiffs’ complaint, this claim was, in essence, one sounding in contract and that, therefore, plaintiffs were not entitled to exemplary damages as a matter of law.

In Davies v. Bradley, 676 P.2d 1242 (Colo.App.1983), we held:

“Exemplary damages are not ordinarily a proper remedy in breach of contract cases_Where, however, ... the facts alleged and proved establish willful and wanton conduct and reckless disregard for the rights of the plaintiff, the maleficent intent on which exemplary damage awards in tort are based is present, and exemplary damages may be awarded though the action sounds in contract.”

See also Podleski v. Mortgage Finance, Inc., 709 P.2d 18 (Colo.App.1985); Collister v. Ashland Oil Co., 687 P.2d 525 (Colo.App.1984).

Here, under the rule in Davies v. Bradley, supra, plaintiffs’ factual allegations are, when liberally construed, sufficient to assert a claim for punitive damages under § 13-21-102, C.R.S. (1979 Cum.Supp.). The trial court, therefore, erred in determining that plaintiffs’ complaint failed to state a cognizable claim for relief and, thus, in granting defendants’ motion for summary judgment on this issue.

II.

Trial was to the court and consumed some 34 days. Defendants contend that the rulings and comments of the trial court, throughout the trial, indicate that it was biased in favor of plaintiffs and that they were, thus, not afforded a fair and impartial trial. We do not agree.

The rulings of a judge, even if erroneous, numerous, and continuous are not sufficient in themselves to show bias or prejudice. See Saucerman v. Saucerman, 170 Colo. 318, 461 P.2d 18 (1969); In re Marriage of Johnson, 40 Colo.App. 250, 576 P.2d 188 (1977). Here, although some of the rulings of the trial court may have been erroneous and/or inconsistent, the record does not disclose any bias or prejudice. It is true that the comments of the trial court which appear in the record indicate that it became frustrated with the inordinate amount of time the trial was taking and that it increasingly intervened in order to expedite the orderly presentation of the evidence. However, a careful examination of the record, in toto, has convinced us that neither the comments of the trial court nor its actions in expediting the trial operated to deny defendants a fair and impartial trial. Likewise, the trial court’s conduct does not demonstrate any bias or prejudice on its part toward the defendants.

III.

Defendants next argue that, inasmuch as negligence was not separately pled as a claim for relief, the trial court erroneously awarded damages based on its finding that Fisher was negligent in performing its duties under the contract. We disagree.

The claim upon which the court awarded damages was adequately pled in breach of contract. The trial court’s finding that Fisher had been negligent in performing its duties under the contract merely supported its ultimate finding and conclusion that there had been a substantial breach of the construction management agreement. See C.R.C.P. 8.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robert Howard v. Monica Howard
Court of Appeals of Tennessee, 2024
Corey Lynn Clark v. State of Tennessee
Court of Criminal Appeals of Tennessee, 2010
Sender v. Mann
423 F. Supp. 2d 1155 (D. Colorado, 2006)
People v. Schupper
124 P.3d 856 (Colorado Court of Appeals, 2005)
St. Paul Fire & Marine Insurance v. City of Green River
93 F. Supp. 2d 1170 (D. Wyoming, 2000)
Brighton School District 27J v. Transamerica Premier Insurance Co.
923 P.2d 328 (Colorado Court of Appeals, 1996)
Alley v. State
882 S.W.2d 810 (Court of Criminal Appeals of Tennessee, 1994)
Zick v. Krob
872 P.2d 1290 (Colorado Court of Appeals, 1993)
In Re Life Ins. Tr. Agreement of Seeman
841 P.2d 403 (Colorado Court of Appeals, 1993)
Shannon v. Colorado School of Mines
847 P.2d 210 (Colorado Court of Appeals, 1992)
Seeman v. Gumbiner
841 P.2d 403 (Colorado Court of Appeals, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
745 P.2d 1034, 1987 Colo. App. LEXIS 777, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riva-ridge-apartments-v-robert-g-fisher-co-coloctapp-1987.