St. Paul Fire & Marine Insurance v. City of Green River

93 F. Supp. 2d 1170, 2000 U.S. Dist. LEXIS 6022, 2000 WL 506263
CourtDistrict Court, D. Wyoming
DecidedMarch 27, 2000
Docket1:98-cv-01007
StatusPublished
Cited by24 cases

This text of 93 F. Supp. 2d 1170 (St. Paul Fire & Marine Insurance v. City of Green River) is published on Counsel Stack Legal Research, covering District Court, D. Wyoming primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Paul Fire & Marine Insurance v. City of Green River, 93 F. Supp. 2d 1170, 2000 U.S. Dist. LEXIS 6022, 2000 WL 506263 (D. Wyo. 2000).

Opinion

ORDER GRANTING PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT

BRIMMER, District Judge.

This case is about the extent of a performance bond surety’s obligation to finish a construction project within the underlying construction contract’s completion deadline after a default by the surety’s principal. After reading the briefs, hearing oral arguments, and being fully advised in the premises, the Court FINDS and ORDERS as follows:

Background

The material facts are not in dispute. On February 10, 1997, Westates Construction Co. (“Westates”) entered a contract with the State of Wyoming Joint Powers Water Board (the “Board”) for the construction of a water treatment plant in Green River, Wyoming (the “Project”). Under the terms of the construction contract, Westates was to achieve substantial completion of the Project on or before December 1, 1998. Significantly, the construction contract provided that time was of the essence and that the Board would be entitled to liquidated damages in the *1172 amount of $2,500 per day for delays after the completion deadline, with allowance made for any extensions granted under the contract.

Prior to construction, St. Paul Fire & Marine Insurance Company (“St.Paul”), as surety, provided a performance bond to the Board, the obligee, to guarantee the principal Westates’ performance under the construction contract. Paragraph 4 of the performance bond defines St. Paul’s options for performance under the bond in the event of a default by Westates:

When the Owner has satisfied the conditions of Paragraph 3 [requiring, inter alia, notice to the Surety, declaration of Contractor default, and Owner’s agreement to pay the Surety the balance of the contract price], the Surety shall promptly and at the Surety’s expense take one of the following actions:
4.1 Arrange for the Contractor, with consent of the Owner, to perform and complete the Construction Contract; or
4.2 Undertake to perform and complete the construction contract itself, through its agents or through independent contractors; or
4.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the Owner for a contract for performance and completion of the Construction Contract, arrange for a contract to be prepared for execution by the Owner and the contractor selected with the Owner’s concurrence, to be secured with performance and payment bonds executed by a- qualified surety equivalent to the bonds issued on the Construction Contract, and pay to the Owner the amount of damages as described in Paragraph 6 in excess of the Balance of the Contract Price incurred by the Owner resulting from the Contractor’s default; or
4.4Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with reasonable promptness under the circumstances:
1. After investigation, determine the amount for which it may be liable to the Owner and, as soon as practicable after the amount is determined, tender payment therefor to the Owner; or
2. Deny liability in whole or in part and notify the Owner citing reasons thereof.

Construction began on March 3, 1997. The Project experienced significant delays of which the causes are in dispute. On January 16, 1998, the Board terminated its contract with Westates, filed suit against Westates in state court, and made a claim against the St. Paul performance bond. St. Paul began a due diligence investigation of the Project to ascertain how it should proceed regarding its duties under the performance bond. Simultaneously, negotiations were commenced involving representatives of the Board, Westates, and St. Paul. These negotiations resulted in a compromise proposal, outlined in a term sheet, which provided, among other things, for: (1) a mutual release between the Board, Westates, and St. Paul, with claims preserved against Forsgren Associates, Inc., the project engineer; (2) removal of Forsgren from construction management responsibilities (though he would continue to provide design services); (3) dismissal of the Board’s lawsuit against Westates; (4) rescission of the Board’s notice of termination; and (5) completion of the Project by St. Paul. The compromise proposal allowed St. Paul to utilize Wes-tates personnel, though St. Paul would retain management decision making authority. The compromise proposal also called for a May 14, 1999 completion date. According to the term sheet, St. Paul was to provide more detailed information regarding completion of the Project to the Board at a February 25,1998 meeting.

*1173 As planned, representatives of St. Paul made presentations to the Board on February 25, 1998. At the meeting, two letters from Steven Grunsfeld of St. Paul were delivered to the Board. In the first letter, Mr. Grunsfeld indicated St. Paul’s willingness to proceed under the compromise proposal, which had not been officially approved by either St. Paul or the Board. In the second letter, Mr. Gruns-feld reported St. Paul’s preliminary determination that the Board’s termination of Westates was wrongful, but announced St. Paul’s election to complete the Project itself under Paragraph 4.2 of the performance bond, albeit under a reservation of rights.

In a February 28, 1998 letter, Dr. Joseph J. Oliver, Chairman of the Board, announced the Board’s response to St. Paul’s communications. Dr. Oliver wrote:

St. Paul representatives stated [at the February 25, 1998 meeting] that St. Paul would complete the [Project] no sooner than September 24, 1999, despite a contract completion date for the Project of December 1, 1998. Accordingly, the [Board] is justifiably insecure that St. Paul will complete the Project in a timely manner.
In addition, St. Paul representatives have made clear St. Paul’s intention to utilize the personnel employed by Wes-tates ... to complete the Project ... even though the [Board] does not consent to Westates or its personnel completing the Project. St. Paul’s announced intention to use Westates to finish the Project without consent of the [Board] is an anticipatory breach of the requirements of Section 4.1 of the Performance Bond.
Accordingly, please be advised that the [Board] refuses to allow St. Paul to complete [the Project] under Section 4.2 of the Performance Bond.

On March 3, 1998, St. Paul brought an action in this Court seeking a declaratory judgment that the Board’s refusal to permit St. Paul to complete the Project was a material breach of the performance bond, thus exonerating St. Paul from any further obligation under the bond. In its answer to St. Paul’s Fourth Amended Complaint, filed on January 15, 1999, the Board asserted counterclaims against St. Paul for breach of contract, breach of the covenant of good faith and fair dealing, tortious bad faith, and violation of Wyo.Stat.Ann. § 26-15-124(c), which allows for recovery of attorney’s fees where an insurance company’s refusal to pay the full amount of a claim is unreasonable or without cause. St. Paul moved for summary judgment and the Board moved for partial summary judgment on its second, third, and fourth counterclaims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barlovento, LLC v. AUI, Inc.
D. New Mexico, 2020
Flatiron-Lane v. Case Atlantic Co.
121 F. Supp. 3d 515 (M.D. North Carolina, 2015)
Fidelity & Deposit Co. v. Jefferson County Commission
756 F. Supp. 2d 1329 (N.D. Alabama, 2010)
County of Brunswick v. Lexon Insurance
710 F. Supp. 2d 520 (E.D. North Carolina, 2010)
St. Paul Fire & Marine Insurance v. VDE Corp.
603 F.3d 119 (First Circuit, 2010)
Sleeper Village v. NGM Ins.
2010 DNH 064 (D. New Hampshire, 2010)
Raito, Inc. v. Cardi Corp.
Superior Court of Rhode Island, 2010
Raito, Inc. v. Cardi Corporation
Superior Court of Rhode Island, 2010
Hunt Construction Group, Inc. v. National Wrecking Corporation
542 F. Supp. 2d 87 (District of Columbia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
93 F. Supp. 2d 1170, 2000 U.S. Dist. LEXIS 6022, 2000 WL 506263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-paul-fire-marine-insurance-v-city-of-green-river-wyd-2000.