St. Paul Fire & Marine Insurance v. VDE Corp.

603 F.3d 119, 2010 U.S. App. LEXIS 9229, 2010 WL 1781941
CourtCourt of Appeals for the First Circuit
DecidedMay 5, 2010
Docket08-2576
StatusPublished
Cited by12 cases

This text of 603 F.3d 119 (St. Paul Fire & Marine Insurance v. VDE Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Paul Fire & Marine Insurance v. VDE Corp., 603 F.3d 119, 2010 U.S. App. LEXIS 9229, 2010 WL 1781941 (1st Cir. 2010).

Opinion

LIPEZ, Circuit Judge.

Defendant VDE Corporation (VDE) appeals from the district court’s grant of summary judgment in favor of plaintiff St. Paul Fire & Marine Insurance Company (St. Paul) releasing St. Paul from its obligations under a construction performance bond. After careful review, we affirm.

I.

The relevant facts are largely undisputed. In the spring and summer of 2005, VDE arranged for the construction and financing of a residential real estate project, Villas Del Este Project, in Gurabo, Puerto Rico (the project). In April 2005, VDE entered into a construction contract with F & R Contractors Corporation (F & R), engaging the company to serve as contractor for the project. VDE obtained financing for the project from Banco Santander Puerto Rico (BSPR).

On June 28, 2005, St. Paul, as surety, issued a performance bond (the bond) for the benefit of VDE, as obligee, to guarantee performance under the construction contract by F & R, as principal. The bond was a standard document, the American Institute of Architects document A312 performance bond (AIA A312). That same day, St. Paul issued a “dual obligee rider” to the bond, adding BSPR as a co-obligee.

Paragraph 4 of the surety bond sets forth St. Paul’s options for performance in the event that F & R defaults under the construction contract. Paragraph 4 provides:

When the Owner [VDE] has satisfied the conditions of Paragraph 3 [setting *121 forth requirements for declaring contractor default], the Surety [St. Paul] shall promptly and at the Surety’s expense take one of the following actions:
4.1 Arrange for the Contractor [F & R], with consent of the Owner, to perform and complete the Construction Contract; or
4.2 Undertake to perform and complete the Construction Contract itself, through its agents or through independent contractors; or
4.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the Owner for a contract for performance and completion of the Construction Contract, arrange for a contract to be prepared for execution by the Owner and the contractor selected with the Owner’s concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the bonds issued on the Construction Contract, and pay to the Owner the amount of damages as described in Paragraph 6 in excess of the Balance of the Contract Price incurred by the Owner resulting from the Contractor’s default; or
4.4 Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with reasonable promptness under the circumstances:
.1 After investigation, determine the amount for which it may be liable to the Owner and, as soon as practicable after the amount is determined, tender payment therefor to the Owner; or
.2 Deny liability in whole or in part and notify the Owner citing reasons therefor.

(Emphasis added.)

On November 7, 2007, VDE declared F & R in default on its obligations as contractor and terminated F & R’s right to continue work on the project. In support of its declaration of default, VDE stated that F & R had refused to abide by its contractual obligations, failed to work at a reasonable pace, abandoned work on the project, insisted on collecting payments not due, and failed to act in good faith. Two days later, VDE notified St. Paul that it had declared F & R in default and requested that St. Paul perform its obligations under the bond. VDE informed St. Paul that it “oppose[d] that the project be completed with F & R as contractor, either directly or indirectly.”

On November 16, St. Paul requested certain documentation from VDE in order to investigate VDE’s allegations of contractor default. St. Paul also acknowledged VDE’s statement that it opposed the use of F & R as completion contractor and advised VDE that “should the Surety choose to complete under Paragraph 4.2 of the Bond, the terms of the Bond do not allow the Obligee to oppose the contractor that the Surety selects as its own completion contractor, whether it be the Principal or otherwise.”

On December 6, St. Paul informed VDE that it had not yet received much of the requested documentation related to its investigation of VDE’s allegations of contractor default. St. Paul listed the missing documents and asked that VDE provide the information as soon as possible. VDE responded that same day, asserting that “[t]he time for the surety to act has expired” and declaring St. Paul in default on its obligations under the bond.

On December 14, following VDE’s declaration that St. Paul was in default, St. Paul filed this declaratory judgment action against VDE and BSPR in federal district court. St. Paul requested a declaration *122 that, inter alia, VDE had breached the terms of the bond by not permitting the surety to take action under the circumstances set forth in Paragraph 4 of the bond, and asked that St. Paul be released from its obligations under the bond. VDE and BSPR filed counterclaims, alleging that St. Paul had failed to perform its obligations under the bond.

On December 26, VDE provided St. Paul with some of the documentation previously requested, and stated again that it would “not consent to F & R performing additional work at the project, either directly or indirectly.” VDE further stated that it would provide St. Paul with an additional fifteen-day period to perform. On January 10, 2008, St. Paul notified VDE that it intended to undertake completion of the project pursuant to Paragraph 4.2 of the bond, using F & R as completion contractor. St. Paul explained that if VDE “maintains the position that the Surety may not use F & R Contractors to complete under Paragraph 4.2 of the Performance Bond, VDE will be in breach of the terms and conditions of the Bond and not only will VDE be waiving its rights under the Bond, but this will also serve to discharge the obligations of the Surety thereunder.” VDE responded the following week, maintaining that under Paragraph 4.2 of the bond it had the authority to withhold consent to the use of F & R as the completion contractor.

The district court granted summary judgment to St. Paul. The court reasoned that VDE materially breached the bond by insisting that St. Paul could not undertake to complete the project using F & R as completion contractor, contrary to the plain language of Paragraph 4.2, and released St. Paul from its obligations under the bond. The district court dismissed the counterclaims with prejudice.

VDE filed this timely appeal from the judgment. 1

II.

VDE contends that the district court erroneously granted summary judgment to St. Paul because, under Paragraph 4 of the bond, St. Paul may not undertake to perform and complete the construction contract through the original contractor without VDE’s consent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
603 F.3d 119, 2010 U.S. App. LEXIS 9229, 2010 WL 1781941, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-paul-fire-marine-insurance-v-vde-corp-ca1-2010.