Arch Insurance Company v. The Graphic Builders LLC

36 F.4th 12
CourtCourt of Appeals for the First Circuit
DecidedJune 1, 2022
Docket21-1126P
StatusPublished
Cited by2 cases

This text of 36 F.4th 12 (Arch Insurance Company v. The Graphic Builders LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arch Insurance Company v. The Graphic Builders LLC, 36 F.4th 12 (1st Cir. 2022).

Opinion

United States Court of Appeals For the First Circuit

No. 21-1126

ARCH INSURANCE COMPANY,

Plaintiff, Appellee,

v.

THE GRAPHIC BUILDERS LLC,

Defendant, Appellant,

RCM MODULAR, INC.,

Defendant.

APPEAL FROM THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MASSACHUSETTS

[Hon. Nathaniel M. Gorton, U.S. District Judge]

Before

Thompson, Lipez, and Kayatta, Circuit Judges.

Richard E. Briansky, with whom Eckert Seamans Cherin & Mellott, LLC and Peckar & Abramson, P.C. were on brief, for appellant.

Jonathan C. Burwood, with whom Watt, Tieder, Hoffar & Fitzgerald, LLP was on brief, for appellee.

June 1, 2022 LIPEZ, Circuit Judge. In this diversity case, The

Graphic Builders LLC ("Graphic"), a general contractor, is seeking

to enforce a performance bond issued by Arch Insurance Co. as

surety for a subcontractor hired to work on a major project for

Graphic. Arch, however, claims that Graphic breached the terms of

the performance bond, and it seeks a judgment declaring that it

has no liability under the bond. The district court sided with

Arch, concluding that Graphic was required to terminate the

subcontractor as a condition of seeking performance from Arch but

had not done so. See Arch Ins. Co. v. Graphic Builders LLC, 519

F. Supp. 3d 54, 60-61 (D. Mass. 2021). Accordingly, the court

granted summary judgment for Arch.

On appeal, Graphic argues that the district court erred

in concluding that Arch's obligation to provide the warranty

performance it seeks was conditioned on termination of the

subcontractor. Graphic asserts that both the bond's language and

relevant precedent support its position. We disagree and therefore

affirm the district court's judgment.

I.

When reviewing a grant of summary judgment, we consider

the facts in the light most favorable to the nonmoving party. See,

e.g., Modeski v. Summit Retail Sols., Inc., 27 F.4th 53, 56 (1st

Cir. 2022). In this case, there is no material disagreement about

the facts, which we set forth below. Graphic and Arch debate only

- 2 - whether those facts give rise to Arch's obligations under the

performance bond.

In 2017, Graphic was hired for a construction project in

Charlestown, Massachusetts, that consisted of converting an

existing commercial building to loft-style apartments and

constructing a four-story apartment building on the same property.

Graphic and the property owner agreed on a modular method of

construction for the new building, and Graphic then selected an

experienced modular manufacturer, RCM Modular, Inc., to fabricate

and assemble the structure at a cost of about $8.6 million. Among

the obligations included in the subcontract was a "Special

Manufacturers [sic] Warranty" for the modular units' windows and

doors.1

A performance bond issued in conjunction with the

subcontract rendered Arch, as surety, "jointly and severally"

responsible for RCM's obligations. Section 3 of the bond, which

is reproduced in Section II below, specifies the actions by Graphic

1Graphic asserts in its brief that Arch was obliged "to issue a post-completion window warranty and other warranties," but it does not specify what "other warranties" are at issue. At oral argument, Graphic's counsel stated that only the window warranty is at issue. Following Graphic's lead, we focus on the window warranty and consider waived any assertion that a different analysis would apply to "other warranties."

- 3 - that would trigger Arch's "obligation under th[e] Bond," including

declaring RCM in default and terminating the subcontract.2

Shortly after RCM delivered the modular units to Graphic

in May 2018, Graphic complained to RCM that the units were

defective. Graphic reported that, among other issues, the windows

leaked and the exteriors of the modules were misaligned. In a

letter to Arch recounting the sequence of events that followed its

initial complaints, Graphic reported that it had received "no

meaningful response from RCM." It therefore "engaged in remedial

efforts to correct the defectively delivered and installed

modules."3 Issues remained, however, and Graphic and RCM met at

the project site in September 2018 to "develop[] a remediation

plan to correct the defective work[,] including producing the

window manufacturer's warranty." According to Graphic, "RCM

2Arch's performance bond is in a standard format commonly used in the construction industry and known as an American Institute of Architects A312 Performance Bond (2010 ed.). See, e.g., St. Paul Fire & Marine Ins. Co. v. VDE Corp., 603 F.3d 119, 124 (1st Cir. 2010) (noting that a leading commentator on construction law has described the A312 performance bond as "one of the clearest, most definitive, and widely used type of traditional common law 'performance bonds' in private construction" (quoting Philip L. Bruner & Patrick J. O'Connor, Jr., 4A Bruner & O'Connor on Construction Law § 12:16 (2009))). 3Although the record is somewhat unclear on this point, it appears that a substantial amount of the remedial work was done by third-party subcontractors hired by Graphic but that RCM itself was asked to address the window deficiencies.

- 4 - failed to complete the remediation plan," and the manufacturer

refused to provide a warranty.

There followed a series of letters from Graphic to RCM

and Arch, initially providing notice only of RCM's potential

default and then, on April 30, 2019, notifying RCM and Arch of

RCM's default. The April 30 letter stated that Graphic was

declaring RCM in default because, among other reasons, it had

failed to deliver a window warranty and had not "undertake[n]

remedial steps to defectively rendered Work and forc[ed] Graphic

to do so at its own expense." Graphic noted, however, that it was

"not yet terminating its Subcontract with RCM," but reserved the

right to do so. Graphic followed up with another letter to Arch,

dated May 3, reiterating the notice of default and advising that

"Graphic is not yet taking the next step of terminating the

Subcontract and making demand on the Bond in the hope that RCM

and/or Arch" would arrange to quickly complete the unfinished work

and "make a good faith move to reduce the large financial impacts

Graphic has suffered."4 In a letter dated May 3, Arch acknowledged

receipt of Graphic's April 30 and May 3 communications, noting its

4 The May 3 letter detailed the expedited remedial work Graphic deemed necessary to allow building occupancy by June 1 and asked that "RCM and/or Arch deploy, without further delay, the qualified staff, materials and equipment needed to correct defectively rendered Work" or to complete unfinished work. Among the listed requests, subject to the project owner's agreement, was "a warranty bond as a substitute for the window warranty that RCM has been unable to deliver."

- 5 - understanding that Graphic was "not attempting to make a claim on

the Arch Performance Bond."

In September 2019, Graphic sent a detailed letter to

Arch, with a copy to RCM, stating that it was providing notice of

RCM's default pursuant to the terms of the performance bond and

demanding that Arch pay $3.175 million in remedial costs that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
36 F.4th 12, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arch-insurance-company-v-the-graphic-builders-llc-ca1-2022.