Solai & Cameron, Inc v. Plainfield Community Consolidated School District No. 202

871 N.E.2d 944, 374 Ill. App. 3d 825, 313 Ill. Dec. 217, 2007 Ill. App. LEXIS 761
CourtAppellate Court of Illinois
DecidedJuly 10, 2007
Docket03-06-0186
StatusPublished
Cited by9 cases

This text of 871 N.E.2d 944 (Solai & Cameron, Inc v. Plainfield Community Consolidated School District No. 202) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Solai & Cameron, Inc v. Plainfield Community Consolidated School District No. 202, 871 N.E.2d 944, 374 Ill. App. 3d 825, 313 Ill. Dec. 217, 2007 Ill. App. LEXIS 761 (Ill. Ct. App. 2007).

Opinion

JUSTICE WRIGHT

delivered the opinion of the court:

Paul H. Schwendener, Inc. (PHS), appeals from an order of the circuit court of Will County granting partial summary judgment in favor of Hartford Fire Insurance Company (Hartford) and Solai & Cameron, Inc. (S&C). 1 We affirm and remand.

I. BACKGROUND

On April 5, 2001, Plainfield Consolidated School District No. 202 (Plainfield) hired PHS as the general contractor to build Plainfield’s tenth and eleventh elementary school facilities, a fourth middle school facility, and additions to the second high school facility. The general contract required PHS to substantially complete all of the school projects by July 15, 2002.

PHS entered into subcontracts dated June 25, 2001, with S&C for the electrical work on the fourth middle school facility (Fourth Middle School Project) and the second high school additions (Second High School Project). Section 2.c. of the S&C electrical subcontracts provides, in relevant part:

“If during the course of the project, this subcontractor continually fails to properly execute his responsibilities, the General Contractor shall issue a three (3) day written notice identifying this condition. If after this three (3) day notice is issued, subcontractor continues to fail in properly executing his responsibilities, the General Contractor shall have the right to properly complete this subcontract with its own or other forces. All costs for the General Contractor to then complete this subcontract shall be charged to this subcontractor.”

S&C, as “Contractor,” secured performance bonds dated June 18, 2001, from Hartford, as “Surety,” corresponding to each electrical subcontract, for the benefit of PHS, as “Owner,” under the terms of the performance bonds. The performance bonds provide, in relevant part:

“3. If there is no Owner Default, the Surety’s obligation under this bond shall arise after:
3.1 The Owner has notified the Contractor and the Surety at its address *** that the Owner is considering declaring a Contractor Default and has requested and attempted to arrange a conference with the Contractor and the Surety to be held not later that fifteen days after receipt of such notice to discuss methods of performing the Construction Contract. If the Owner, the Contractor and the Surety agree, the Contractor shall be allowed a reasonable time to perform the Construction Contract, but such an agreement shall not waive the Owner’s right, if any, subsequently to declare a Contractor Default; and
3.2 The Owner has declared a Contractor Default and formally terminated the Contractor’s right to complete the contract. Such Contractor Default shall not be declared earlier than twenty days after the Contractor and the Surety have received notice as provided in Subparagraph 3.1; and
3.3 The Owner has agreed to pay the Balance of the Contract Price to the Surety in accordance with the terms of the Construction Contract or to a contractor selected to perform the Construction Contract in accordance with the terms of the contract with the Owner.
4. When the Owner has satisfied the conditions of Paragraph 3, the Surety shall promptly and at the Surety’s expense take one of the following actions:
4.1 Arrange for the Contractor, with consent of the Owner, to perform and complete the Construction Contract; or
4.2 Undertake to perform and complete the Construction Contract itself, through its agents or through independent contractors; or
4.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the Owner for a contract for performance and completion of the Construction Contract, arrange for a contract to be prepared for execution by the Owner and the contractor selected with the Owner’s concurrence, to be secured with performance and payment bonds, executed by a qualified surety equivalent to the bonds issued on the Construction Contract, and pay to the Owner the amount of damages *** in excess of the Balance of the Contract Price incurred by the Owner resulting from the Contractor’s default; or
4.4 Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with reasonable promptness under the circumstances:
.1 After investigation, determine the amount for which it may be liable to the Owner and, as soon as practicable after the amount is determined, tender payment therefor to the Owner; or
.2 Deny liability in whole or in part and notify the Owner citing reasons therefor.
5. If the Surety does not proceed as provided in Paragraph 4 with reasonable promptness, the Surety shall be deemed to be in default on this Bond fifteen days after receipt of an additional written notice from the Owner to the Surety demanding that the Surety perform its obligations under this Bond, and the Owner shall be entitled to enforce any remedy available to the Owner. If the Surety proceeds as provided in Subparagraph 4.4, and the Owner refuses the payment tendered or the Surety has denied liability, in whole or in part, without further notice the Owner shall be entitled to enforce any remedy available to the Owner.”

The working relationship between PHS and S&C began to deteriorate in March 2002. By letter dated March 20, 2002, PHS sent a letter to S&C, with a copy to Hartford, regarding S&C’s inadequate performance on both electrical subcontracts. The letter contained the three-day notice to comply required by section 2.c. of the S&C electrical subcontracts. The letter also stated, “please note that a copy of this notice to comply has been sent to your bonding company as required in Section 3.1 of the Performance Bond and serves as their notification of default.”

On March 25, 2002, PHS sent a second letter to S&C, with no indicated copy to Hartford, concerning S&C’s failure to properly perform on both electrical subcontracts. This letter threatened to remove S&C from both school projects unless substantial improvements were made in the following week. The letter discussed a March 27, 2002, meeting to review S&C’s progress on the projects.

PHS and Hartford communicated by telephone on April 2, 2002, regarding S&C’s performance on the electrical subcontracts. On April 12, 2002, PHS retained Nu-Line Electric Co., Inc. (Nu-Line), to consult on the status of S&C’s unfinished work.

Pursuant to the terms of the electrical subcontract, by letter dated May 1, 2002, PHS notified S&C it had 24 hours to properly man and equip the Second High School Project or PHS would complete the electrical subcontract. PHS sent a copy of this letter to Hartford. On May 2, 2002, Hartford’s claim representative telephoned PHS and agreed to discuss the situation with S&C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
871 N.E.2d 944, 374 Ill. App. 3d 825, 313 Ill. Dec. 217, 2007 Ill. App. LEXIS 761, Counsel Stack Legal Research, https://law.counselstack.com/opinion/solai-cameron-inc-v-plainfield-community-consolidated-school-district-illappct-2007.